Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Calculate the Total Duration for the Four Activity Project
Solution:
Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.
A clay layer 25 metres thick has a saturated unit weight of 19.2 kN/m 2 . Ground water level occurs at a depth of 5 metres. It is proposed to construct a reinforced concrete founda
Question What is major dissimilarity between standpipe, standpipe piezometer and piezometer ? Answer Standpipe usually contains plastic pipes with punctured holes at
explain ranging and reciprocal ranging
i have three civil engineering fluid mechanics. 1 manometer problem 2 estimate the discharge for a channel 3 pipe system - direction of flow in line and what the value of flow in l
Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly: Solution: n = 360 months interest = 7%-annual ÷ 12-months/year
Define Cleanliness of Surface - Limitations of Ultrasonic System? Sound energy transmission is greatly affected by marine growth on the surface of the concrete element. Ultraso
Explain the Wetted Perimeter (P) The linear length of the interface between the fluid's cross-sectional plane edges in contact with the pipe or channel wall.
Define Dupuit Equations for Unconfined Aquifers Using natural log: Q = ΠK((h 2 ) 2 - (h 1 ) 2 )/ln(r 2 /r 1 ) Using log 10 : Q = K((h 2 ) 2 - (h 1 ) 2 )/((1,055)l
Explain the Equation for a Suppressed Rectangular Weir If the approach velocity is negligible, velocity head can be excluded and the equation becomes the Francis weir equation
detail methods of underwater concreting
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd