Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

Chain survrying, How do we overcome obstacle like river in chain survey?

How do we overcome obstacle like river in chain survey?

Define the approach velocity, Define the Approach Velocity Typical prob...

Define the Approach Velocity Typical problems have negligible approach velocity.  v 1 = Q/A, where A = the cross-sectional area of flow in the channel. The value is not the ve

Fore bearing and back bearing, write a c program to calculate the included ...

write a c program to calculate the included angles for given fore bearing and back bearing.

Calculate surface loading rate for each clarifier, A wastewater plant is op...

A wastewater plant is operating at 10MGD with a suspended solids concentration of 200mg/L. It has 6 clarifiers operating in parallel. Each clarifier is 40 foot in diameter and 10 f

Determine the expected extension at the jack, A cylindrical concrete tank,...

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  10 5   N/mm 2 )  jacked  at 4 points, 9

Bridge, Explain economical span if bridges

Explain economical span if bridges

Shape factor, For a solid circular shaft transmitting torque, the shape fac...

For a solid circular shaft transmitting torque, the shape factor is

Find out load carrying capacity, Q.for ISMB200 having 6.70 m span simply su...

Q.for ISMB200 having 6.70 m span simply supported so find out load carrying capacity.

Define hand tools for underwater inspection of bridge, Define Hand Tools fo...

Define Hand Tools for Underwater Inspection of Bridge? Hand tools involve scrapers, wire brushes, chain and wire ropes. Tools of this kind are suited in which cleaning is confi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd