Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

Pavement width - geometric design of roads, Pavement Width: The pavem...

Pavement Width: The pavement widths commonly adopted are : Single lane                 :           3.75 m Intermediate lane     :           5.5 m Two lane

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Survey, chaining on level surface

chaining on level surface

Aggregaters, What Aggregate''s class III

What Aggregate''s class III

Calculate snow weight, Snow weight In spatial trusses, Snow load is muc...

Snow weight In spatial trusses, Snow load is much more important than building. As in buildings snow load is only a small proportion of the overall weight of the building, it w

Minimisation of differential settlement, Minimisation of Differential Settl...

Minimisation of Differential Settlement You are aware that differential settlement causes more distress to the structure, when compared with that of total settlement. The var

Choice of pavement - road pavements, Choice of Pavement: The advantag...

Choice of Pavement: The advantages and drawback of the two types of pavements are summarized in Table, to enable a choice to be made. Table : Advantages and drawback of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd