Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Calculate the Total Duration for the Four Activity Project
Solution:
Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.
Define Masonry substructure- underwater inspection of bridge? In early days, masonry, particularly stone masonry was extensively used for bridge piers and abutments. Typically,
Explain the Watersheds - Hydrology The surface area on which runoff generated will flow to a common stream or body of water by gravity. Often separated by higher elevations/top
A footing, 2 m square, is founded at a depth of 1.5 m in a sand deposit, for which the corrected value of N is 27. The water table is at a depth of 2 m from the surface. Verify the
Question What is major disparity between capping beams and ground beams for piles? Answer Capping beams for piles plan to transferring loads from directly spaced c
Question In soil compaction test , if test result exceeds 100%, should engineers accept result? Answer Soil compaction is method of increasing soil density by re
Landslides induced by rainfall After rainfall, groundwater pressure is built up and this elevates ground water table. Water inside the pores of soil reducesthe effective stres
Cement is usually purchased as a powdery substance that is mixed with sand, aggregate, gravel, and water to form concrete. As the cement itself is usually a powder, it is hard to c
wbm road
Q. Inspection and Quality Control Certificate : A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certif
A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of high-strength steel wire (E, = 2 x 10 5 N/mm 2 ) jacked at 4 points, 9
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd