Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

Tests on limestones, Tests on Limestones Practical tests are made on li...

Tests on Limestones Practical tests are made on lime stones to decide their suitability is following:     i.       Physical tests    ii.        Heat test    iii.

Find the maximum stress, Find the maximum stress: A circular bar rigid...

Find the maximum stress: A circular bar rigidly fixed at both ends is 1 m long and tapers uniformly from 20 cm diameter at one end to 10 cm diameter at the other end. Find the

Timber, Cross-section of exogeneous tree

Cross-section of exogeneous tree

Determine the types of untensioned reinforcement, Determine the types of un...

Determine the types of untensioned Reinforcement  Reinforcement used as untensioned steel should be one of the following types : (a)  Mild steel and medium tensile steel bar

Define the impact damage - underwater inspection of bridge, Define the Impa...

Define the Impact Damage - underwater inspection of bridge? Impact from moving vessels or logs carried during the floods can inflict damage to the structure. The impact or coll

Calculate the resultant hydrostatic force, Five 1m diameter, 2m high cylind...

Five 1m diameter, 2m high cylindrical drums filled with earth are placed upright and side-by-side in a straight line across a 5m wide creek to form a simple dam completely blocking

Verify the earth pressure at rest, A retaining wall, 6 m high, retains dry ...

A retaining wall, 6 m high, retains dry sand with an angle of friction of 30° and unit weight of 16.2 kN/m 3 . Verify the earth pressure at rest. If the water table rises to the to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd