Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

Soil classification - road materials, Soil Classification: Based on p...

Soil Classification: Based on particle size, the soils can be classified as under, adopting the IS soil classification system: 0.002   0.075   0.425   2.36     4.75

Internal force of preloaded fasteners, Q. Internal force of preloaded faste...

Q. Internal force of preloaded fasteners? Force in a bolt in a bolted joint relies on the preloading force applied to it at the time of the tightening operation. For example, w

Priciples of working from whole to part in surveying, What are the principl...

What are the principles of working from whole to part in surveying?

Calculate the percent change in load on the wall form tie, A concrete wall ...

A concrete wall form tie with an ultimate strength capacity of 2,400-lbs is designed for use in a concrete wall form with an 18-in center to center spacing. During formwork inspect

Explain the design of graded filter, Q. Explain the design of graded filter...

Q. Explain the design of graded filter? Use of graded filter has been traditionally used below the revetment and protection works. The material used in the granular / graded fi

Equipments required for under water inspection of bridge, Define Equipments...

Define Equipments and tools required for under water Inspection of Bridge? Since the underwater inspection of stone masonry substructures involve only a cursory inspection of t

Explain the geophysical methods, Why are undisturbed samples needed? Descri...

Why are undisturbed samples needed? Describe any one procedure of obtaining undisturbed samples for a multi-storeyed building project. For what purpose are geophysical methods u

AUTOCAD, do you people deal with autocad

do you people deal with autocad

Cement bag question., composition of cement in cover bag should be written ...

composition of cement in cover bag should be written or not/ If written which country uses ?please specify the name ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd