Calculate the total duration for the four activity project, Civil Engineering

Assignment Help:

Calculate the Total Duration for the Four Activity Project

1260_Calculate the Total Duration for the Four Activity Project 1.png

Solution:     

Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.

1026_Calculate the Total Duration for the Four Activity Project 2.png


Related Discussions:- Calculate the total duration for the four activity project

Explain the scaling - underwater inspection of bridges, Explain the Scaling...

Explain the Scaling - underwater inspection of bridges? Scaling is the gradual and continuing loss of the surface mortar and aggregate over an area. This condition is commonly

Window, sliding window lowered window sash or glazed window circular window...

sliding window lowered window sash or glazed window circular window

Define limitations of radiography - inspection of bridge, Define Limitation...

Define Limitations of Radiography - Underwater Inspection of Bridge? i. Radiography is a costly and time consuming method, which re- quires extensive safety measures to be adop

How the raft is designed as a floating foundation, A raft, 9 m × 27 m, is f...

A raft, 9 m × 27 m, is founded at a depth of 3 m in sand with a value of  N = 25 up to great depth. Verify the total load which the raft can support. If the raft is designed as

Explain the installation of shock transmission unit, Explain the Installati...

Explain the Installation of Shock Transmission Unit? It is not always necessary to install STUs while a structure is under construction but the holding down anchor bolts and th

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Bridge abutment be placed under an embankment, Question It should be necess...

Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with dive

What is rail lubrication, Q. What is Rail Lubrication? Rail Lubrication...

Q. What is Rail Lubrication? Rail Lubrication is done on sharp curves where lateral wear is considerable. The function of Rail Lubrication is to lubricate or oil the running fa

Determine the specific gravity of solids, The Atterberg limits of a clay so...

The Atterberg limits of a clay soil are: Liquid limit = 63%, Plastic limit = 40%, and shrinkage limit = 27%. If a sample of this soil has a volume of 10 cm 3 at the liquid limit a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd