Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Calculate the Total Duration for the Four Activity Project
Solution:
Scheduling work activity has associated time duration. The durations shown in the Table were estimated for the project diagrammed below. The entire set of activities would then require 3-days, since the activities follow one another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3-days (answer is c). If another activity proceeded in parallel with this sequence, the 3 day minimum duration of these four activities is unaffected. More than 3 days would be required for the sequence if there was a delay or a lag between the completion of one activity and the start of another.
Determine the minimum speed of the stunt rider, so that when he leaves the ramp at A he passes through the center of the hoop at B. [5 Points] 2. How far h should the landing ramp
define distribution factor and shape factor
what is the type of slope protection that use rocks and put cements between those rocks??the concept is same as brick layer
Q. What are the various types of tiles available in the market for floors and walls? What basic precautions would you take for their laying and choosing the type, colour and siz
define scale and sludge and mention the scale and sludge forming substance and explain the prevention methods
What is sag rod..?
Explain the Basic requirement of Design of shock transmission unit? The STU must withstand the specified design load. The stroke of the piston must be bigger than the movement
Concordant Prestressing In this type of prestressing, tendons follow a concordant profile. The concordant profile of tendons does not change the support reactions in a statica
Soil pressure enhances with depth due to the overburden or self-weight of the soil and because of loads imposed upon the soil. For example, the pressure variation below the dept
Mechanism of taking up loads for concrete paving blocks Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd