Explain about void ratio drops, Civil Engineering

Assignment Help:

A clay layer 25 metres thick has a saturated unit weight of 19.2 kN/m2. Ground water level occurs at a depth of 5 metres. It is proposed to construct a reinforced concrete foundation, 12.5 m × 50 m, on top of the layer, to transmit a uniform pressure of 150 kN/m2.

Verify the settlement at its centre, suppose that the void ratio drops from 0.725 to 0.700 due to loading. E for the clay is 30 MN/m2.

 


Related Discussions:- Explain about void ratio drops

Show the design of howe truss, Q. Show the Design of Howe truss? Design...

Q. Show the Design of Howe truss? Design of Howe truss is the opposite to that of Pratt truss in that the diagonal members are slanted in the direction opposite to that of Prat

Demonstrate the economical design of concrete, Demonstrate the economical d...

Demonstrate the economical design of concrete A safe, serviceable and economical design of concrete structures requires a comprehensive knowledge of the loads expected to be a

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

Beneficial points of sliding bearings over roller bearings, What are key be...

What are key beneficial points of sliding bearings over roller bearings ? In roller bearing for a given movement a roller bearing exhibit modify in pressure centre from its un

Road materials, Road Materials Earthwork and pavements constitute a si...

Road Materials Earthwork and pavements constitute a significant part of the cost of a road. Hence it is desirable that thorough investigations be done about the availability o

Test on complete bearings, Q. Test on complete bearings? Two bearings s...

Q. Test on complete bearings? Two bearings should be selected at random from the 'lot'. Various tests should be conducted on these 'test bearings'. These bearings should be exc

Define contaminants - underwater inspection of bridge, Define Contaminants ...

Define Contaminants - underwater inspection of bridge? There are various substances that may be inadvertently incorporated into the concrete matrix (e.g. glass, coal, gypsum),

Ranging, defference between direct and indirect ranging..

defference between direct and indirect ranging..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd