Calculate the monthly payment for home mortgage, Civil Engineering

Assignment Help:

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly:

Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

          = 0.583% per month

 $300,000(A/P, 0.00583, 360) = Apply the equation:      

i (1+i)n/ (1+i)n -1

 = 0.006650339

 A = 300,000 x 0.006650339 = $1,995.10 per month


Related Discussions:- Calculate the monthly payment for home mortgage

Chain survey, what are the obstacles in chain survey in brief

what are the obstacles in chain survey in brief

Explain about the pre-tensioning systems, Pre-tensioning systems In the...

Pre-tensioning systems In the previous unit we have seen different steps in a pretensioning operation. Tendon wires or strands (formed as a rope type arrangement made of  sever

Total station - uses and mining, Total station - uses and mining: Use...

Total station - uses and mining: Uses:- Total stations are mainly used by land surveyors and Civil Engineers, either to record features as in Topographic Surveying or to

Advance structure engg, need help for assignment that requires strand 7 and...

need help for assignment that requires strand 7 and autocad

Stress strain curves, stress strain curves for any materials with an explan...

stress strain curves for any materials with an explanation

Concrete technology, material for formwork and their specifications

material for formwork and their specifications

Pavement layers, What role does modulus of elasticity play in the pavement ...

What role does modulus of elasticity play in the pavement layer arrangement

Explain in brief about the term - anchorage, Explain brief about the term -...

Explain brief about the term - Anchorage A device used to anchor tendons at the end of a concrete member is called as an anchorage in the case of post-tensioned concrete. In th

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd