Calculate the monthly payment for home mortgage, Civil Engineering

Assignment Help:

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly:

Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

          = 0.583% per month

 $300,000(A/P, 0.00583, 360) = Apply the equation:      

i (1+i)n/ (1+i)n -1

 = 0.006650339

 A = 300,000 x 0.006650339 = $1,995.10 per month


Related Discussions:- Calculate the monthly payment for home mortgage

Explain damage inspections - underwater inspection of bridge, Explain the D...

Explain the Damage inspections - underwater inspection of bridge? Sometimes referred to as post-event inspections, damage inspections are typically unscheduled inspections aime

How to find back bearings?, Example: The following fore bearings were ...

Example: The following fore bearings were observed respectively for lines, AB, BC, CD, DE, EF and FG. Find out their back bearings: (i) 148°                          (ii

What are the causes of building collapse, The Passage of time is single rea...

The Passage of time is single reason. Buildings also collapse because of weak foundations. Earthquakes, hurricanes and other natural disasters can also damage the structure of the

Construction Planning, A contractor has both a 3-cy and a 5-cy shovel in th...

A contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working day

Explain about best hydraulic section, Q. Explain about Best hydraulic secti...

Q. Explain about Best hydraulic section? The best hydraulic section of an open channel is considered by provision of maximum discharge with a given cross sectional area. Chann

Scale., how many scale are there and what are they use

how many scale are there and what are they use

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Stabilised pavement layers, Stabilised Pavement Layers: Soil stabilis...

Stabilised Pavement Layers: Soil stabilisation is the process of treating a soil in such a manner as to alter and improve its properties for use as a pavement layer on sub-gr

How can designer cater for stability of minor slips, Question Soil nail...

Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd