Calculate the monthly payment for home mortgage, Civil Engineering

Assignment Help:

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly:

Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

          = 0.583% per month

 $300,000(A/P, 0.00583, 360) = Apply the equation:      

i (1+i)n/ (1+i)n -1

 = 0.006650339

 A = 300,000 x 0.006650339 = $1,995.10 per month


Related Discussions:- Calculate the monthly payment for home mortgage

Design, what is the procedure to design the beam and column?

what is the procedure to design the beam and column?

Sanitary, Design a sewer network

Design a sewer network

State the increase in earth pressure at rest, A wall with a smooth vertical...

A wall with a smooth vertical back and 9 metres high retains a moist cohesionless soil with a horizontal surface. The soil weighs 15 kN/m3 and has an angle of internal friction of

Minimum and maximum distance between bars, Q. Minimum and maximum distance ...

Q. Minimum and maximum distance between bars? Minimum distance between bars and maximum distance between bars In some codes, a minimum distance amid bars is specified to

Surveying, earthen dam and gravity dam

earthen dam and gravity dam

Addition of water to bored piles, Addition of water to bored piles In ...

Addition of water to bored piles In water bearing ground, some water head (about 1 m) above the existing ground water table is sustained to stabilize the bore at the time of e

Flat footed rail, pls tell about flat footed rail and it weight how much fo...

pls tell about flat footed rail and it weight how much for 40 * 80 *10 mm

Define about the inclined borings, Define about the Inclined Borings In...

Define about the Inclined Borings Inclined  brings may also be used in exploration of  inclined strata and for the detection of weak pockets (lenses),  buried channels,  caviti

Wastewater, Why is there a concern for dissolved organics and color in the ...

Why is there a concern for dissolved organics and color in the water supply and in water treatment plant?

Construction mesurment, Measurement quantity of excavation, concrete, formw...

Measurement quantity of excavation, concrete, formwork as my assignment brief.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd