Calculate the monthly payment for home mortgage, Civil Engineering

Assignment Help:

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly:

Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

          = 0.583% per month

 $300,000(A/P, 0.00583, 360) = Apply the equation:      

i (1+i)n/ (1+i)n -1

 = 0.006650339

 A = 300,000 x 0.006650339 = $1,995.10 per month


Related Discussions:- Calculate the monthly payment for home mortgage

Explain about overhauling of level xing, Q. Explain about Overhauling of Le...

Q. Explain about Overhauling of Level xing? Each level crossing except those laid with PSC sleepers must be opened out and the condition of sleepers and fittings, rails and fas

Surving, describe the methods of reducing the levels,and their relative adv...

describe the methods of reducing the levels,and their relative advantages and disadvantages.

Explain the operating point - pumping system, Explain the Operating Point -...

Explain the Operating Point - Pumping System Intersection of the characteristic curve and the system curve. This is the head and flow rate data for the pump "operation". The op

Water absorption test for precast concrete pipes, Question What is the ...

Question What is the major purpose of carrying out water absorption test for precast concrete pipes? Answer Cement will mix with additional water than is compulsory t

Raised check rails for obtuse crossing, Raised Check Rails for obtuse cross...

Raised Check Rails for obtuse crossing In order to provide guided path way in throat portion of 1 in 8 1/2 BG obtuse diamond crossing, the check rails are raised by welding of

Road survay, how many programmes in road survey by level matichine and ts?

how many programmes in road survey by level matichine and ts?

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd