Calculate the monthly payment for home mortgage, Civil Engineering

Assignment Help:

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly:

Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

          = 0.583% per month

 $300,000(A/P, 0.00583, 360) = Apply the equation:      

i (1+i)n/ (1+i)n -1

 = 0.006650339

 A = 300,000 x 0.006650339 = $1,995.10 per month


Related Discussions:- Calculate the monthly payment for home mortgage

Categories of losses of prestress, Categories of losses of prestress We...

Categories of losses of prestress We may put various losses in either of two categories : Losses which take place during transfer of  prestress and those which take place after

Explain about bentonite slurry and polymeric slurry, Q. Explain about Bento...

Q. Explain about Bentonite slurry and polymeric slurry? For the construction of diaphragm walls, bentonite slurry is generally used to form a filter cake on walls of trenches t

Size of drainage near roads, how to calculate the size of drainage(box) wid...

how to calculate the size of drainage(box) width and height?

Cost-volume relationship, Cost-volume relationship: Cost-volume relati...

Cost-volume relationship: Cost-volume relationship is illustrated through a simple example dealing with the cost of operating an automobile. To perform the analysis following

Break even point, Break even point: EM Electricals, Inc., contains fix...

Break even point: EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200

Test for determination of uitimate compressive strength, Q. Test for determ...

Q. Test for determination of Ultimate Compressive Strength The test pieces are to be loaded either till the failure of the steel laiminate or till the irreversible squeezing ou

Can you explain permeable spurs, Q. Can you explain Permeable Spurs? A ...

Q. Can you explain Permeable Spurs? A permeable spur may be constructed by driving two or more rows of bally piles with sufficient penetration below riverbed level to provide a

EARTH FILL dam, different components of all types of earth fill dam

different components of all types of earth fill dam

Civil Engineering, I. A horizontal 500 lb force acts at a point D of cranks...

I. A horizontal 500 lb force acts at a point D of crankshaft AB which is held in static equilibrium by a twisting couple and by reactions at A and B. Knowing that the bearings are

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd