Calculate the monthly payment for home mortgage, Civil Engineering

Assignment Help:

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly:

Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

          = 0.583% per month

 $300,000(A/P, 0.00583, 360) = Apply the equation:      

i (1+i)n/ (1+i)n -1

 = 0.006650339

 A = 300,000 x 0.006650339 = $1,995.10 per month


Related Discussions:- Calculate the monthly payment for home mortgage

Treatment plant - sewer construction, Treatment plant - sewer construction:...

Treatment plant - sewer construction: Problem: How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant? Solution An a

Recognize the losses of prestress, Recognize the losses of prestress Re...

Recognize the losses of prestress Recognising the losses of prestress which take place after the prestressing OF concrete structural elements, it is to be appreciated that pres

Preparation for underwater inspection - tool and equipment, Preparation for...

Preparation for Underwater Inspection - Availability of Tools and Equipment The engineer-in-charge, before taking up the inspection, should list out the complete equipment req

Determine the total lateral pressure on the wall, A masonry retaining wall ...

A masonry retaining wall is 1.5 m wide at the top, 3.5 m wide at the base and 6 m high. It is trapezoidal in section and has a vertical face on the earth side. The backfill is leve

Moment, difference between moment and bending moment

difference between moment and bending moment

Majority carriers are hols in, Majority carriers are hols in which type? ...

Majority carriers are hols in which type? Answer: In P-type semiconductors hols are majority carriers .

WMM, GRADATION OF WMM

GRADATION OF WMM

Water or hydraulic horsepower (whp), Water Or Hydraulic Horsepower (whp) ...

Water Or Hydraulic Horsepower (whp) The work performed by a pump is a function of the head added by the pump (h A ), the flow rate required (Q) and the mass of the fluid (accou

Mixed ground with soils and boulders, Ground settlement occurs when pipe-ja...

Ground settlement occurs when pipe-jacking machine enters mixed ground with soils and boulders? The rate of cutting through soils is faster than cutting through boulders for pi

Guiding considerations in planning, Guiding Considerations in Planning: ...

Guiding Considerations in Planning: The following factors have a bearing on planning water transport facilities : (a)        Availability adequate land to accommodate the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd