Prepare a project to lay fiber optic cable

Assignment Help Project Management
Reference no: EM1343235

You are preparing a project to lay fiber optic cable...

You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000. It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.

a. At the end of week 1:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

b. At the end of week 3:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

c. At the end of the project:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

Reference no: EM1343235

Questions Cloud

Project management of applications : Project Management of Applications - Show the role of the project manager in the in-house development of a customized application.
Show the project cash flow analysis : Your company plans to produce a product for two more years and then to shut down production and you are considering replacing an old machine used in production with a new machine.
Monitoring and controlling project cost : Earned Value Analysis - Monitoring and Controlling Project Cost - What are some key components to monitor the health of the project, as it relates to earned value?
Question about milton manufacturing overhead activity : Evaluate the company's bid if the bid is based upon full manufacturing cost plus 30 percent and evaluate the amount of overhead that would be applied to the proposed project if activity-based costing is used.
Prepare a project to lay fiber optic cable : Prepare a project to lay fiber optic cable - What is your SPI and what is your CPI
Modify the integrated project plan : Modify the integrated project plan as a result of a team meeting to incorporate the changes to the plan as provided by the CBDF and the trickiest part of this assignment is to evaluate how you will do this.
Entertainment - due to electrical code changes : All the equipment that bands bring to the stage will need to be checked by fire marshals
Show the integrated project plan : Post the liquor license; validating IDs, validating the per-person limit, etc.
Risk management - identifying risks : Risk Management: Identifying Risks - Risk management is a matter of identifying the situations that could cause your project to fail.

Reviews

Write a Review

Project Management Questions & Answers

  Risk identification with project contingency planning

How does risk identification help with project contingency planning?

  Activities required to successfully manage project

From a project management perspective outline the activities required to successfully manage this project, ensuring that it is on time, and within budget.

  Types of computer and telephone monitoring systems

Examine and discuss the types of computer and telephone monitoring systems being used in the workplace. What are the ethical issues involved with these type of monitoring systems?

  Successful or unsuccessful information systems project

Discuss either a successful or an unsuccessful information systems project (either a project that you know about personally from work, or one that you learned about by researching news accounts of IS projects on the Web).

  Differentiating primary and secondary research

Explain the difference between "primary" and "secondary" research.

  Role of project management in modern organizations

Describe the role of project management in modern organizations.

  Explain the six methods for estimating task duration

Explain the six methods for estimating task duration and show how each method affects the accuracy of task duration estimates.

  Developing a cost analysis of items of library project

Develop a cost analysis of the above items relating to the library project so we have hard numbers to work with and have a monetary value for reporting and audit purposes.

  Show the project risk management in project planning

Explain why should all projects include risk in their project planning? What are some of the drawbacks if risks are not considered

  Subject-s actions using consequential and humanist theories

Evaluate your subject's actions using Consequential theories. Evaluate your subject's actions using Humanist theories.

  Steps in project risk management process

What are the basic steps in the project risk management process?

  Risk management component of successful project management

Risk management is a major component of successful project management.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd