You are preparing a project to lay fiber optic cable...
You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000. It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.
a. At the end of week 1:i. What is your SPI?ii. What is your CPI?iii. What is your EAC?
b. At the end of week 3:i. What is your SPI?ii. What is your CPI?iii. What is your EAC?
c. At the end of the project:i. What is your SPI?ii. What is your CPI?iii. What is your EAC?
How does risk identification help with project contingency planning?
From a project management perspective outline the activities required to successfully manage this project, ensuring that it is on time, and within budget.
Examine and discuss the types of computer and telephone monitoring systems being used in the workplace. What are the ethical issues involved with these type of monitoring systems?
Discuss either a successful or an unsuccessful information systems project (either a project that you know about personally from work, or one that you learned about by researching news accounts of IS projects on the Web).
Explain the difference between "primary" and "secondary" research.
Describe the role of project management in modern organizations.
Explain the six methods for estimating task duration and show how each method affects the accuracy of task duration estimates.
Develop a cost analysis of the above items relating to the library project so we have hard numbers to work with and have a monetary value for reporting and audit purposes.
Explain why should all projects include risk in their project planning? What are some of the drawbacks if risks are not considered
Evaluate your subject's actions using Consequential theories. Evaluate your subject's actions using Humanist theories.
What are the basic steps in the project risk management process?
Risk management is a major component of successful project management.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd