Determine the critical path and project duration in days

Assignment Help Project Management
Reference no: EM1343240

Given the following project to landscape a new building site.

Activity Immediate Predecessor Activity duration(days) Resources used

A: Get Plants - 2 X,Y
B: Get flowers A 2 X
C: Obtain soil A 3 X
D: Obtain Fertilizer B,C 4 X,Y
E: Select Labor D 3 W,X
F: Set date D 1 W,X,Y
G: BEGIN E,F 2 X,Y

(a) Determine the critical path and project duration in days.

(b) Given that each resource is assigned 100% to each task, identify the resource constraints.

(c) Level the resources and determine the new project duration and critical path

(d) Find what alternative solutions can be used to shorten the project duration and not over-allocate the resources.

Reference no: EM1343240

Questions Cloud

Explain what is the cost variance and schedule variance : Explain what is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project and how is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
It project managers and traditional project managers : What is the difference between IT project managers and traditional project managers if there are so many similarities in project management discipline
Emotional intelligence - importance for project managers : Self-awareness refers to a person's capacity for being aware of how they are feeling and managing emotions refers to a person's capacities to ensure that feelings do not interfere with getting things accomplished.
Description of risk management : Write a paper regarding a project, either real or fictitious, where one is able to discuss how risks were identified, ranked, and monitored.
Determine the critical path and project duration in days : Determine the critical path and project duration in days and given that each resource is assigned 100% to each task, identify the resource constraints.
Project management of applications : Project Management of Applications - Show the role of the project manager in the in-house development of a customized application.
Show the project cash flow analysis : Your company plans to produce a product for two more years and then to shut down production and you are considering replacing an old machine used in production with a new machine.
Monitoring and controlling project cost : Earned Value Analysis - Monitoring and Controlling Project Cost - What are some key components to monitor the health of the project, as it relates to earned value?
Question about milton manufacturing overhead activity : Evaluate the company's bid if the bid is based upon full manufacturing cost plus 30 percent and evaluate the amount of overhead that would be applied to the proposed project if activity-based costing is used.

Reviews

Write a Review

Project Management Questions & Answers

  Work breakdown structure differ from the project network

How does the Work Breakdown Structure differ from the Project Network (Diagram)?

  Gantt chart of critical paths and contingency planning

Analyze the organizations basic legal, social and economic issues, managerial, operational, and financial issuesProject management. Also include 1 Gantt chart example along with 1 PERT chart example.

  Applications and uses of risk measurement techniques

Identify at least three risk measurement techniques describing their use and application.

  Definition of quality dimensions

Provide an example of a "best buy" from your professional experience where quality aspects were not met in accordance to the text definition of quality dimensions.

  Determining earliest-latest and slack times for activity

The following are activity times for the project. Find the earliest, latest, and slack times for each activity. Then Find the critical path.

  Assistance on project management

How would you proceed and what tools would you use - when was a time that a situation like this was handled successfully

  Public activity in the u.s. economy

Provide the reasons why this activity is a major part of the public activity in the U.S. economy.

  Characteristics of effective project manager

Fully explain and describe the functions and necessary characteristics of an effective project manager.

  Matrix and projected project organization structure

Based on the facts in the case, do you believe that Rachel is working in a functional, a matrix, or a projected project organization structure?

  Computing number of weeks take to complete the project

What is the critical path? How many weeks will it take to complete the project?

  Calculating cost using a one-month planning horizon

Calculate the total cost using a one-month planning horizon.

  Evaluate the use of complex models of project risk

Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd