Q. What is Sedimentation tank ?

This is a process in which the water is passed through bases or tanks in which the velocity of water is so reduced or water is given a period of rest that permits the heavy Suspended particles settle at the bottom by action of gravity and force in the Sedimentation tank . This is necessary because water contains suspended matter which might choke the filters.

There are two types of Sedimentation.

1. Plain Sedimentation

2. Sedimentation with coagulants or Chemical Sedimentation.

Detention Period - 6-to8 hrs for Plain Sedimentation & 1.5 To 3 hrs for Chemical Sedimentation.

Depth of flow - 3 to 6 meters.

Velocity of flow - 30 cm / min.

Length of tank = 3 to 4 time of width of tank.

Bottom slope - 1: 100

In case of circular tank dia less than 60m.

Type of Sedimentation Tank -

1. Horizontal flow Sedimentation Tank

2. Up ward flow Sedimentation Tank

3. Circular Sedimentation Tank


Related Discussions:- What is sedimentation tank

Manufacturing of cement, describe with neat sketch the process of manufactu...

describe with neat sketch the process of manufacturing of cement in the modern factory by dry process

PORTAL FRAME, EXPLAIN SITUATION OF THE PORTAL FRAME CAN CAUSE SWAY WITH THE...

EXPLAIN SITUATION OF THE PORTAL FRAME CAN CAUSE SWAY WITH THE AID OF A DIGRAM

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

How to find back bearings?, Example: The following fore bearings were ...

Example: The following fore bearings were observed respectively for lines, AB, BC, CD, DE, EF and FG. Find out their back bearings: (i) 148°                          (ii

Choosing between trailer suction hopper and grab dredgers, Question In ...

Question In search reclamation, what are considerations in choosing between trailer suction hopper dredgers and grab dredgers ? Answer Trailer suction hopper dred

Calculate the uniformly distributed load, Given: pretensioned rectangula...

Given: pretensioned rectangular beam b=6" h=20" f'c=4000psi f'ci=3000psi fti=.165ksi fts=.38ksi fci=1.8ksi fcs=1.8ksi R=0.80 Required: (a)Pi and e to maximize Md+

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

Municipal Hydraulics, Hello I have an assignment due feb 1st at 3 pm. I wan...

Hello I have an assignment due feb 1st at 3 pm. I wanted to know if it was possible that it gets solved

Explain the geophysical methods, Why are undisturbed samples needed? Descri...

Why are undisturbed samples needed? Describe any one procedure of obtaining undisturbed samples for a multi-storeyed building project. For what purpose are geophysical methods u

WMM, GRADATION OF WMM

GRADATION OF WMM

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd