Side clearance of pipes in trenches

From the design point of view, it's predominant to minimize the width of pipe trenches due to thebelow reasons:

(i)  Higher cost of excavation is related with wider pipe trenches.

(ii) Width of trench affects the loads on installed pipelines in consideration of embankment condition and wide trench condition. For minimum pipe trench width, loads on pipelines can be decreased.

Though sufficient space has to be provided to allow for proper compaction. This is helpful to decrease the reaction at critical locations of pipelines under traffic and fill loads. Furthermore consideration must be given to accommodate temporary works for deep trenches where shoring has to be provided at the time of construction.


Related Discussions:- Show the side clearance of pipes in trenches

Explain strain compatibility in mini-piles, Q. Explain Strain compatibility...

Q. Explain Strain compatibility in mini-piles? In designing the axial capacity of mini-piles, grout can be taken into account in the contribution of axial load capacity. Though

Explain the erosion and sedimentation, Explain the Erosion and Sedimentatio...

Explain the Erosion and Sedimentation Erosion: Removal of soil or other channel material caused by the rapid movement of water over the channel surface. The removed material

Explain the term - uniaxial - biaxial -triaxial prestressing, Explain the t...

Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di

Explain the primary treatment for wastewater, Explain the Primary Treatment...

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed

Levelling, principles of levelling

principles of levelling

One layered spatial structures, Classification of the damage according to t...

Classification of the damage according to the type of structures The level of damage in spatial trusses has also been classified into three different levels based on th

CBR of soil, Why IRC 37-2012 has taken 90th percentile for pavement design ...

Why IRC 37-2012 has taken 90th percentile for pavement design of expressway or NH while they hav taken 80th percentile for state highway design ????????

Element stiffness matrices, i have seen the example of the above topic on y...

i have seen the example of the above topic on your page and i would like to have a solution for it

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd