Calculate uniform annual cost for maintenance and repair, Civil Engineering

Assignment Help:

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest rate at 7% and end-of-year disbursements, the uniform annual cost for maintenance and repair for the dozer is most nearly:

Year                 Maintenance and Repair Costs

1                                   $4,500

2                                  $9,000

3                                  $11,800

4                                  $13,500

5                                  $22,500

Solution:  The Equivalent Uniform Annual Cost (EUAC) can be computed for this irregular series of payments in two steps: 

Step 1:   Compute the Present Worth for five years using the single payment present worth factors.

PW of cost   = 4500(P/F, 7%, 1) + 9000(P/F, 7%, 2) + 11800(P/F, 7%, 3) +  13500(P/F, 7%, 4) + 22500(P/F, 7%, 5)

 = 4500(.9346) + 9000(.8734) + 11800(.8163) + 13500(.7629) + 22500(.7130)      

= $48,040.29

Step 2:   With the PW of cost known, compute the EUAC using the capital recovery factor.

  EUAC   = 48,040(A/P, 7%, 5)

      = 48,040(.2439) 

      = $11,717.03


Related Discussions:- Calculate uniform annual cost for maintenance and repair

Difference between direct circulation and reverse drilling, Question Wh...

Question What is main difference between direct circulation drilling and reverse circulation drilling? Answer In straight circulation drilling and reverse circulati

Construction of the building, a) Certain data for the materials used in the...

a) Certain data for the materials used in the construction of the building, e,g, insulation, building materials, air spaces, etc.  b)  Draw, with appropriate dimensions, the cro

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Designing 10 story building, Hi need help with designing a 10 story concret...

Hi need help with designing a 10 story concrete building with basement car park. Need help with calculations in line with eurocodes. Is this something you can help with?

Explain the normal depth equation, Explain the Normal Depth Equation T...

Explain the Normal Depth Equation The equation is derived from the Chezy-Manning equation. As written below it determines the diameter of a circular storm or sanitary sewer wh

Civil and statistics, application of normal distribution in civil engineeri...

application of normal distribution in civil engineering

Sewer, what are the procedure of surveying for sewer projects/

what are the procedure of surveying for sewer projects/

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd