A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest rate at 7% and end-of-year disbursements, the uniform annual cost for maintenance and repair for the dozer is most nearly:

Year                 Maintenance and Repair Costs

1                                   $4,500

2                                  $9,000

3                                  $11,800

4                                  $13,500

5                                  $22,500

Solution:  The Equivalent Uniform Annual Cost (EUAC) can be computed for this irregular series of payments in two steps: 

Step 1:   Compute the Present Worth for five years using the single payment present worth factors.

PW of cost   = 4500(P/F, 7%, 1) + 9000(P/F, 7%, 2) + 11800(P/F, 7%, 3) +  13500(P/F, 7%, 4) + 22500(P/F, 7%, 5)

 = 4500(.9346) + 9000(.8734) + 11800(.8163) + 13500(.7629) + 22500(.7130)      

= $48,040.29

Step 2:   With the PW of cost known, compute the EUAC using the capital recovery factor.

  EUAC   = 48,040(A/P, 7%, 5)

      = 48,040(.2439) 

      = $11,717.03


Related Discussions:- Calculate uniform annual cost for maintenance and repair

Plastic, what is plastic?its types and composition and its uses as engineer...

what is plastic?its types and composition and its uses as engineering material

Optimum binder content in bituminous pavement, Q. Optimum binder content in...

Q. Optimum binder content in bituminous pavement? Amount of binder to be added to a bituminous mixture can't be too excessive or too little. Principle of designing the optimum

Traverse surveying, How to calculate the whole circle bearing from the incl...

How to calculate the whole circle bearing from the included angles?

Obstacle measurement.., ..describe how u can obtain the length of an inacce...

..describe how u can obtain the length of an inacceble length of a land when a river cross it

Steel Design Assignment, I have a steel design assignment for my class that...

I have a steel design assignment for my class that will be given to us on Friday at 6 pm and will be due at 10 pm. I was wondering if you guys would be able to help me with that?.

Haley''s formula in pile driving, Question What is major difference bet...

Question What is major difference between "hammer efficiency" and "coefficient of restitution" at what time using Haley's formula in pile driving?   Answer Hammer ef

Crushing strength test - tests on stones, Crushing Strength Test: F...

Crushing Strength Test: For conducting this test, specimen of size 40 × 40 × 40 mm is build from parent stone. Then finely the sides are dressed and placed in water for thr

Semi dense bituminous concrete, Semi Dense Bituminous Concrete: Semi ...

Semi Dense Bituminous Concrete: Semi Dense Bituminous Concrete (SDBC) is similar to BC, but with a higher void content (5-10 per cent, as against 3-5 per cent in the case of

Find the youngs modulus of the rod, Find the Youngs modulus of the rod: ...

Find the Youngs modulus of the rod: A composite rod is made by joining a copper rod end to end with a second rod of different material but of same cross-section. At 25oC, the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd