A manufacturing facility consists of five departments, 1, 2, 3, 4 and 5. It produces four components having the manufacturing product routings and production volumes indicated in the table below. (a) Generate a from-to chart. (b) Find a relationship chart using the following rules: "A" for 85-66 trips between departments, "E" for 65-46, "I" for 45-26, "O" for 25-6, and "U" for 5-0. (c) Find closeness ranks.
Component
Production Routing
Units per Week
1
1-2-3-4-5
20
2
2-3-5-1
25
3
4-5-3
10
4
5-4-3-2-1
30
Determine the ratio between moment and load: Any close coiled helical spring of circular section extends 1 mm while subjected to an axial load of W and then given an angular r
Q. Describe about consumable electrode? This type of electrode is prepared from metal. Its one end is kept in electrode holder and then electric supply is passed through it. Th
What is differential approach (differential formulation) in fluid mechanics? What are velocity and acceleration fields, give examples. Find, study and write down the differential f
diference between thermal and thermodynamic equallibrim
What type of low lube oil security recommended for API612 steam turbines.(Electronic/Mechanical). Please give refrences
what is the difference between polar and mass moment of inertia?
Copper-Lead Alloys Copper-lead alloys, having a large percentage of lead have determined a considerable employ as bearing material lately. Straight, copper-lead alloys of such
Submerged Arc Welding Single pass filler welds upto (8.0 mm) maximum and groove welds made with a single pass or a single pass each side, may be made using an E7os-x elect
Breather tube : Check breather tube for blockage and also air filter box hole where breather tube is connected, for any blockage.
Find out the amount of energy spent: 6 cubic metre of water is to be lifted to a height of 40 metres and delivered having velocity of 4 metres/sec. If this operation takes 12
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd