Differences between pipe jacking and micro-tunnelling, Civil Engineering

Assignment Help:

Q. Differences between pipe jacking and micro-tunnelling?

Pipe jacking is a general scheme of installation of pipes with a tunnelling shield in front and the pipes are jacked from a jacking pit toa receiving pit. Tunnelling shield for pipe jacking can be mechanical and electrical equipment for conducting the excavation work or itcould be a manual shield for workers going inside the shield to do manual excavation. For microtunneling, it is a type of pipe jacking of small sized non-man-entry pipes that are remotely controlled. Generally there are two general kinds of micro-tunnelling machines:

(ii) Pressurised slurry

Similar to Pressurised slurry TBM, excavated material is transported from excavation face to surface suspended in aslurry. 

(iii)Auger machine

Excavated material is transported from excavation face to drive pit by a cased screw auger.


Related Discussions:- Differences between pipe jacking and micro-tunnelling

To make open sqare &rectangular, how to calculate the section weight for op...

how to calculate the section weight for open square tube

How to calculate the dry density and void ratio, A moist soil sample compac...

A moist soil sample compacted into a mould of 1000 cm 3 capacity and weight 35 N, weighs 53.5 N with the mould. A representative sample of soil taken from it has an initial weight

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Drawing, how to draw an elipse

how to draw an elipse

Functions components of a typical expansion joint, Question What are the fu...

Question What are the functions components of a typical expansion joint ? Answer In a characteristic expansion joint, it normally contains following mechanism-joint sealant, jo

Water-bound macadam road construction for unpaved roads, how can I come up ...

how can I come up with the research on the water bound macadam road construction

Explain flocculation, Explain Flocculation Most important factor ef...

Explain Flocculation Most important factor effecting particle removal efficiency objective - to bring particles into contact so that they will collide, stick together

The regulations and specification that followed for compacti, what are The ...

what are The regulations and specification that followed for compaction works for earth dam in Oman.

Major drawbacks of using inverted siphons, Question What is key application...

Question What is key application of inverted siphons? What are major drawbacks of using inverted siphons ? Answer Inverted siphons are planned at locations in which sewer s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd