Calculate roller production, Civil Engineering

Assignment Help:

Calculate Roller Production

An excavating contractor determined through a test strip, that a smooth steel-wheel vibrating roller compactor operating at 3-mph can compact a 6-inch layer of borrow material to a proper density in four passes. The width of the smooth steel drum is 8.0-ft and operates 50-min per hour.   The number of compacting rollers required to maintain a material delivery rate of 540-bank cubic yards per hour is most nearly (1 bank cubic yard = 0.83 compacted cubic yards):

Solution: Calculate roller production.

Step 1: Compute a conversion factor to standardize the various units of measure:

(5280 ft/mile) x (1 cubic yard / 27 cubic feet) x (1 foot / 12 inches) = 5280/27/12 = 16.3

Step 2: Compute compacted cubic yards (CCY) per hour:

Compacted cubic yards per hour = (16.3 x 8-ft x 3-mph x 6-inch x 50-min/60-min) ÷ 4 passes = 489 CCY/hr

Step 3: Compute compacted cubic yards (CCY) per hour to bank cubic yards (BCY)

489-CCY/hr ÷ 0.83-CCY/BCY = 589.2 bank cubic yards per hour

Step 4: Compute the number of roller compactors needed.

Thus, 540 BCY/hr ÷ 589.2 BCU/hr = 0.92 < 1-roller compactor  

Therefore, only one roller is required to keep up with the delivery of borrow material.


Related Discussions:- Calculate roller production

Common building stones, Common Building Stones Here describe some commo...

Common Building Stones Here describe some commonly used stones are following: a. Granite       b. Basalt and trap c. Slate          d. Sand stone   e. Marble        f.

Construct the correct network for project, A project requires that activiti...

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can

Define the design of piers and abutments erected in water, Define the Desig...

Define the Design of Piers and Abutments Erected in Water? All piers and abutments erected in water are generally designed to be protected from scour or erosion.  However, both

Define non-destructive inspection of concrete substructures, Define Non-des...

Define Non-destructive inspection of Concrete Substructures? If there is evidence of significant deterioration, then a Level III inspection, involving either non-destructive or

Unsealed contraction joints in concrete pavement, Unsealed contraction join...

Unsealed contraction joints in concrete pavement For unreinforced concrete pavement, contraction joint is an approximately 3mm wide groove with a depth of about one-third to o

#transportation engineering sessional.., #how the result of DETERMINATION O...

#how the result of DETERMINATION OF THE 10 PERCENT FINES value can be interprited?

Improvements to public bus transport, Improvements to Public Bus Transport:...

Improvements to Public Bus Transport: Since buses carry a large number of passengers, improvements in bus transport is a cheap solution. Some of the possible improvements are

Use of primers in joint sealant, Q. Use of primers in joint sealant? Mo...

Q. Use of primers in joint sealant? Most of the joint sealants applied in concrete joints are adhesive and recommended joint width/depth of joint sealant is from 2:1 to 1:1 as

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd