How can a temporary diversion to laid, Civil Engineering

Assignment Help:

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months.

Ans.-

Temporary diversion constructed around an obstruction to traffic and not likely to be in use for more than 10 days.

In case of disruption to rail traffic over a major bridge lasting over 6 months the semi permanent diversion should be laid to the following specification as for as possible -

In this case temporary diversion not to be laid.

i. Radius of curve - Not less than 450 m.

ii. Gradient - Not steeper than 1 in 100.

iii. Super elevation - Normally no super elevation is provided but if it is provided it should be limited to suit the speed permitted over the diversion and run out at a rate not exceeding 12 mm in 10 m.

In addition to above specified standers for semi permanent diversion are as under -

i. The existing bank should not be cut to lay diversion.

ii. The gradient should be suitably compensated for curvature in order to ensure that in spite of the curvature the gradient does not exceed the limiting value.

iii. If a bridge is on diversion with cribs a straight 7 level portion of 30 m should be provided on either approach of the bridge.

iv. To guard the diversion against possible settlement provide a blanket and roll it if possible.


Related Discussions:- How can a temporary diversion to laid

Water control for sheet pile walls, Q. Water control for sheet pile walls? ...

Q. Water control for sheet pile walls? Ground water flow into excavations constructed by sheet pile walls must be minimized in order to save the cost of the provision of pumpin

Determine about the hard-drawn steel wires, Determine about the Hard-drawn ...

Determine about the Hard-drawn steel wires Hard-drawn steel wires which are indented or crimped are preferred for pre-tensioned members as their bond characteristics are superi

Traditional marine piling system of steel tubular pile, Question What i...

Question What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures? Answer In design

Hydraulics, The atmospheric pressure is given 680 mm Hg at a certain mounta...

The atmospheric pressure is given 680 mm Hg at a certain mountain location of elevation 2000 m. air density is 1.007 kg/m3. Find the pressure in kPa.

Survey, 3-d figure of line ranger

3-d figure of line ranger

Why does pipe jacking machine usually get stuck, Q. Why does pipe jacking m...

Q. Why does pipe jacking machine usually get stuck when the ground condition change from soil to very hard rock? When pipejacking machine moves from anarea of soil to very hard

Potential advantages of segmental tunnelling, Q. Potential advantages of se...

Q. Potential advantages of segmental tunnelling when compared with hand-shield pipe-jacking? In segmental tunnelling, jacks are installed at the shield so that itisn't necessar

Levelling, principle of direct levelling

principle of direct levelling

Load and loa effects, AFor the given reinforced concrete moment frame schoo...

AFor the given reinforced concrete moment frame school building determine; 1. The wind load acting on the middle truss in the roof truss assembly. 2. The net wind pressure (Wnet) o

Levelling, important terms used in levelling

important terms used in levelling

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd