How can a temporary diversion to laid, Civil Engineering

Assignment Help:

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months.

Ans.-

Temporary diversion constructed around an obstruction to traffic and not likely to be in use for more than 10 days.

In case of disruption to rail traffic over a major bridge lasting over 6 months the semi permanent diversion should be laid to the following specification as for as possible -

In this case temporary diversion not to be laid.

i. Radius of curve - Not less than 450 m.

ii. Gradient - Not steeper than 1 in 100.

iii. Super elevation - Normally no super elevation is provided but if it is provided it should be limited to suit the speed permitted over the diversion and run out at a rate not exceeding 12 mm in 10 m.

In addition to above specified standers for semi permanent diversion are as under -

i. The existing bank should not be cut to lay diversion.

ii. The gradient should be suitably compensated for curvature in order to ensure that in spite of the curvature the gradient does not exceed the limiting value.

iii. If a bridge is on diversion with cribs a straight 7 level portion of 30 m should be provided on either approach of the bridge.

iv. To guard the diversion against possible settlement provide a blanket and roll it if possible.


Related Discussions:- How can a temporary diversion to laid

Dry process of cement, i want a complete flow chart of dry process of cemen...

i want a complete flow chart of dry process of cement

Survey, how to draw longitudinal profile

how to draw longitudinal profile

Calculus, how can i get the centroids of the a given curve?. is there''s a ...

how can i get the centroids of the a given curve?. is there''s a formula for?

Design for the limit state of collapse in bending, Design for the limit st...

Design for the limit state of  collapse in bending Following assumptions are taken in the design for the limit state of  collapse in bending or flexure. Plane sections norm

Retaining walls, Retaining Walls: Needed to retain the fill portion, a...

Retaining Walls: Needed to retain the fill portion, and generally constructed in dry stone masonry with pucca bunds (Figure). Figure: Typical Design for a Retaining

Show the functions of diaphragm walls, Q. Show the Functions of diaphragm w...

Q. Show the Functions of diaphragm walls? The functions of diaphragm walls are as follows: (i)  It is designed to maintain soils during the construction of underground

Determine the variation of safe bearing capacity of soi, State the algebrai...

State the algebraic equations showing the variation of safe bearing capacity of soil (for clay and sand to be given separately) in shallow foundation with: (i) depth of foundati

Water absorption test for precast concrete pipes, Question What is the ...

Question What is the major purpose of carrying out water absorption test for precast concrete pipes? Answer Cement will mix with additional water than is compulsory t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd