1) A propped cantilever beam ABC is 7m long.It has the point C fixed and Point A on a roller support.It carries a 200Kn point load at a distance 3m from A.There is a moment of 80KN
Explain the Scaling - underwater inspection of bridges? Scaling is the gradual and continuing loss of the surface mortar and aggregate over an area. This condition is commonly
Q. Granular fill or rock fill essential at the base of concrete retaining walls? It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom
BRICKS Brick is obtained by moulding good clay into a block, which is dried and then burnt. It is the oldest building block to replace stone. Manufacture of brick started havin
Q. What do you mean by Settlement Cracks? Settlement cracks normally take place in diagonal position. Sometimes vertical cracks may also take place (Figure (a)). Settlement cra
state and prove Heisenberg uncertainity principle?
Q. What is Switch and Expansion Joint? Switch Expansion, Joint (SEJ) is an expansion joint installed at each end of LWR/CWR to permit expansion/contraction of the adjoining bre
Q. Avoidance of designing acute angle of concrete pavement The stress persuaded in acute angle corners of concrete pavement is far much higher than right-angle corners of the
built in truss
3-d figure of line ranger
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd