Determine the equivalent of free float, Civil Engineering

Assignment Help:

The free float is equal to:

a. Latest allowable event occurrence time + Early finish time

b. Earliest event occurrence time + early finish time

c. Latest allowable event occurrence time - Early finish time

d. Earliest event occurrence time - Early finish time

Ans: Earliest event occurrence time - Early finish time


Related Discussions:- Determine the equivalent of free float

Find the normal stress, Find the normal stress: Figure 1 shows the pro...

Find the normal stress: Figure 1 shows the projection of a rectangular prism ABCD, formed by adhesive bonding of two triangular prisms ABC and ACD. The state of stress in the

Relaxation losses in prestressing steels, Relaxation losses in prestressing...

Relaxation losses in prestressing steels The relaxation losses in prestressing steels vary with type of steel, initial prestress, age, and temperature and, therefore, shall be

Calculate the cost to finance the construction project, A contractor is bid...

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Railway bridge, how to measure the waterways of railway bridges

how to measure the waterways of railway bridges

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd