One of the tools used to manage large projects is known as the critical path method (CPM). In CPM the manager builds a network of all phases of a project and then evaluates the network to determine critical aspects of the project. In a CPM network, each vertex is an event, such as the start or completion of a task. The arcs connecting the vertices represent the duration of the activity. Unlike the examples in the text, they also store the name of the activity. To better understand the concept, let's look at a possible CPM plan to build a house. The network for this project is shown in Figure 11-26.

921_Steps for Building a House.jpg


Figure: Steps for Building a House

In the plan we see that it will take 10 days to prepare the building plan (A) and 5 days to get it approved (B). Furthermore, we can't start building until we have selected the contractor (C). We could construct the shortest path from the start to the end for our plan, but it would be of little value. On the other hand, if we determined the maximum path-that is, the path with the greatest sum of the weights-we would know which steps in our plan are critical. If a critical step slips even one day, we slip our end date. We can slip noncritical dates, however, without slipping our end date, so long as the slip does not change the critical path for the project.
Modify Algorithm 11-12, "Minimum Spanning Tree of a Graph," to determine the maximum path through the graph. Then provide a menu that allows the project manager to answer the following questions:

a. What is the shortest possible completion time (SPCT)? The SPCT is the longest path through the graph from beginning to end.

b. What is the earliest start time (EST) for each activity? The EST is the sum of the weights in the maximum spanning tree up to the activity.

c. What is the latest start time (LST) for each activity? The LST is the SPCT for the whole project minus the SPCT for the rest of the project (starting from the current activity).

d. What is the slack time for each activity? The slack time is LST - EST.

e. Is an activity a critical path item? (Critical path items have a slack time of zero.)

f. What is the critical path for the project? (The critical path is the sub graph consisting of the maximum spanning tree.)

Reference no: EM131159036

Questions Cloud

Write an algorithm that finds sum of the degrees for a node : Write an algorithm that finds the sum of the degrees for a node, using the adjacency list representation.
Write an algorithm that print minimum spanning tree of graph : Write an algorithm that prints the minimum spanning tree of a graph. At the end, print the weight of the spanning tree. A suggested report format is shown in the following example.
Draw a path diagram for the project : The Galaxy project consists of 8 interdependent tasks, labeled A through H. You've consulted experts, and have determined an optimistic, likely and pessimistic completion time (in days) for each of the tasks. The dependencies, and the times, are l..
What are the different factors to be considered for reactor : During exocytosis in a skeletal muscle, there will be release of calcium ions fromintracellular vesicles in the sarcoplasmic reticulum in response to high levels ofRyanodine binding to Ryanodine Receptors in the transverse tubules.
What is the shortest possible completion time : What is the shortest possible completion time (SPCT)? The SPCT is the longest path through the graph from beginning to end. What is the earliest start time (EST) for each activity?
What lessons might the society of muslim women : What lessons might the Society of Muslim Women (SMW) be able to share with programs that seek to prevent wife abuse in other countries?
Write program that simulates a mouses movement through maze : Write a program that simulates a mouse's movement through the maze, using a graph and a depth-first traversal. When the program is complete, print the path through the maze.
Why are these rites significant in their respective cultures : Anthropological fieldwork requires the anthropologist to think critically about his or her own cultural practices and beliefs. He or she must be able to reflect upon personal beliefs and values and have those beliefs and values challenged. Choos..
What impact do you think this on the journalism profession : Google Jayson Blair and Stephen Glass and read about them. Both men were involved in fabricating news and then publishing this information in the newspapers. How often do you think this kid of deception occurs in the media, and what factors contri..

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Implement near-field communications

The mobile phone industry is beginning to implement Near-Field Communications (NFC) technology that will facilitate contactless payments among smartphones.

  Annual returns will depend on both size of the station

Even though independent gasoline stations have been having a difficult time, Susan Solomon has been thinking about starting her own independent gas station.  Susan's problem is to decide how large her station should be.

  Calculate the circumfrential and longitudinal stresses

Calculate the circumfrential and longitudinal stresses in the plates when the internal pressure is 800KN/m sq. If the ultimate tensile stress of the material used is 600 MN/m sq, and the efficiency of the longitudinal joint is 70 per cent, determi..

  What is the smallest possible total area

A wire 10 feet long is to be cut into two pieces, each of which is to formed into a square. What is the largest possible total area of the two squares? What is the smallest possible total area?

  Problem regarding the integer programming problem

Solve the integer programming model for the below problem.  For this problem, solve the integer programming model by using QM for Windows.

  Find the pmf-mean and variance of the child''s birth rank

A random child is chosen in the town (with equal probabilities). Find the PMF, mean, and variance of the child's birth rank.

  Calculation based on the probability issues

What is the probability that the first selected candy is lemon or that the second selected candy is cherry?

  What is the temperature inside the refrigerator

A can of soda is taken from the refrigerator, and is left in a room whose temperature is 24°C. After half an hour the temperature of the can was 12°C and after another half an hour the temperature of the can was 16°C. What is the temperature insid..

  Maximum permitted rate of water flow

Water is to be transported through a network of pipelines from the big dam to the low valley for irrigation. A network is shown where arcs represent pipelines and the number on each arc represents the maximum permitted rate of water flow in cubic-..

  Modifications of the tatham capital budgeting model

Need LP tutorial help involving optimization and the use of Solver. Solve the following modifications of the Tatham Capital Budgeting model (solve each part independently of the others)

  Problem regarding the location decisions

A manufacturer of oak barrels has factories in an area at the location coordinates provided in the following table. Each coordinate unit represents approximately 10 miles. The yearly demand at each factory is also given.

  Algebraically solve for phytolifes formula and its unit cost

Write up the standard linear program for PhytoLife. Graph and show PhytoLife's feasible set and a cost line. Using graphical techniques show the most attractive point. Algebraically solve for PhytoLife's formula and its unit costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd