Draw a path diagram for the project

Assignment Help Operation Management
Reference no: EM131159038

Have you read, studied, and understood all of the course materials, including the Module Home Page and the sources listed under Background Info?  If you haven't, then do so before attempting this homework.

The Galaxy project consists of 8 interdependent tasks, labeled A through H. You've consulted experts, and have determined an optimistic, likely and pessimistic completion time (in days) for each of the tasks. The dependencies, and the times, are listed below.

Task

Precursor(s)

Optimistic

Likely

Pessimistic

A

(start)

2

6

9

B

A

18

19

20

C

A

10

12

14

D

A

12

18

24

E

(start)

13

1

16

F

B, C, D

8

12

16

G

D, E

6

8

10

H

F, G

17

20

21

(end)

H

 

 

 

1. Draw a path diagram for the project.

2. Calculate the expected length of each task.  Fill in the following worksheet.

Task

Optimistic (O)

Likely (L)

Pessimistic (P)

Expected Task E = (O + 4L +P/6)

A

2

6

9

 

B

18

19

20

 

C

10

12

14

 

D

12

18

24

 

E

13

14

16

 

F

8

12

16

 

G

6

8

10

 

H

17

20

21

 

3. Use the following worksheet to determine the lengths of all possible paths. Determine the critical path. What is its length?

Path (Listing of tasks on the path)

Expected Path Length Ep = ∑E

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The Mojo Project consists of 14 interrelated tasks, A through N.  Their estimated normal completion times, normal costs, crash times and crash costs are given below. (Times in weeks; costs in thousands of dollars.)

Task

Predecessors

Normal Time

Normal Cost

Crash Time

Crash Cost

A

(start)

3

4

2

5

B

(start)

5

6

4

7

C

A

2

3

2

4

D

A

4

8

3

10

E

A

3

5

2

7

F

B

9

14

7

16

G

B

4

5

3

7

H

C, D

4

7

2

9

I

D

6

2

5

3

J

F

12

10

11

15

K

H

4

6

3

7

L

E, I, J

10

18

8

20

M

K, L

8

10

6

14

N

G

7

5

6

8

Use an online application (e.g., Sporkforge, 2014) to find the critical path, using the estimated normal times. Copy the output of the app into your upload as an image.

4. Which tasks are on the critical path?

5. What is the expected completion time of the project?

6. Which (if any) tasks should be crashed, to make up the lost time? Why?

7. What is the additional cost of crashing the project?

Provide references and citations.  At a minimum, you should reference the course materials.

For Part 1: Draw a PERT-CPM diagram clearly showing all the paths, plus the critical path. You may draw the diagram by hand, and paste a scanned image into your upload, but it must be totally legible.

For Part 2: A PERT-CPM diagram is not required.  Use an online app; paste an image of the app output into your paper.

Show, and explain, all the calculations supporting your answers.

Unambiguously state your answers.

There are no guidelines concerning length.  Write what you need to write - neither more, nor less.

Required Reading

Critical path calculator. (2008). Retrieved from sporkforge.com: https://sporkforge.com/sched/critical_path.php

*Rensvold, R. (2014d). PERT-CPM [course page].

Additional Reading

Campbell, S. (1982).  Critical path method.Appraisal Journal, 50(4); 607-15.

Foltz, B. (2012).  Operations management 101:  Critical path analysis part II (Video).  Retrieved on 8 Oct 2014 from https://www.youtube.com/watch?v=acSKQmVsVPg

Attachment:- Assignment.rar

Reference no: EM131159038

Questions Cloud

Which knee joint is absolutely larger and why : What differences exist between the sacral bones of Homo erectus and Australopithecus afarensis shown in Figure 10.4? Which species arrived first? What can we determine about the nature of bipedalism by comparing these two?
Calculate the present value of cash inflows : Calculate the present value of cash inflows associated with each project.  -  Select the optimal group of projects, keeping in mind that unused funds are costly.
Write an algorithm that finds sum of the degrees for a node : Write an algorithm that finds the sum of the degrees for a node, using the adjacency list representation.
Write an algorithm that print minimum spanning tree of graph : Write an algorithm that prints the minimum spanning tree of a graph. At the end, print the weight of the spanning tree. A suggested report format is shown in the following example.
Draw a path diagram for the project : The Galaxy project consists of 8 interdependent tasks, labeled A through H. You've consulted experts, and have determined an optimistic, likely and pessimistic completion time (in days) for each of the tasks. The dependencies, and the times, are l..
What are the different factors to be considered for reactor : During exocytosis in a skeletal muscle, there will be release of calcium ions fromintracellular vesicles in the sarcoplasmic reticulum in response to high levels ofRyanodine binding to Ryanodine Receptors in the transverse tubules.
What is the shortest possible completion time : What is the shortest possible completion time (SPCT)? The SPCT is the longest path through the graph from beginning to end. What is the earliest start time (EST) for each activity?
What lessons might the society of muslim women : What lessons might the Society of Muslim Women (SMW) be able to share with programs that seek to prevent wife abuse in other countries?
Write program that simulates a mouses movement through maze : Write a program that simulates a mouse's movement through the maze, using a graph and a depth-first traversal. When the program is complete, print the path through the maze.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd