A project has several activities. These activities are shown in the table below, together with their time estimates (in weeks) and the crashing costs information:
Activity Normal Time Normal Cost Crash Time Crash Cost Immediate PredecessorsA 2 $50 1 $70 ---B 4 $80 2 $160 AC 8 $70 4 $110 AD 6 $60 5 $80 AE 7 $100 6 $130 BF 4 $40 3 $100 DG 5 $100 4 $150 C, E, F
A. What is the critical path when normal activities are used?
B. Evaluate the minimum total direct cost for each of the following project durations (based on the cost associated with each activity): 13, 14, 15, 16, 17, and 18 weeks.
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd