PERT/CPM problem with three (3) time estimates

A project is composed of 8 tasks. The three-time estimates (in days) for each activity plus the precedence requirement for each are shown in the table below:

Activity Activity Time Estimates
(in days) ImmediatePredecessor
A 2, 3, 4 None
B 3, 4, 11 None
C 1, 2, 3 A, B
D 4, 5, 12 C
E 3, 5, 7 C
F 2, 3, 4 E
G 2, 3, 10 C
H 2, 3, 4 D, G, F
I 2, 3, 10 D, F
J 1, 2, 3 H
K 1, 2, 3 I, J

A. Draw a network for the project using AON method.

B. Determines the critical path(s) and identify them by a) double lining the arrows connecting the activities on the CP (like ===) AND b) writing the letter representing the activities on the CP in the answer-sheet-set.

C. Do a complete path analysis and fill the table in the answer-sheet set

D. What are the chances that the project will finish within 25 days?

E. What are the chances that the project will take longer than 23 days to finish?

Reference no: EM1343272

Questions Cloud

Prepare and distribute meeting notes : Prepare and distribute meeting notes from Friday's developers check-in meeting and route initial comps to the client for a launch due today
Scheduling and project management of dell : Scheduling and Project Management of Dell - What are the difficulties or limitations for implementing PERT and CRM in Dell
Project planning - breakdown structure and control : Show what controlling measures should be taken during the planning phase and then provide a generic method for creating a project schedule starting with the creation of the work breakdown structure.
What is the critical path when normal activities are used : What is the critical path when normal activities are used and evaluate the minimum total direct cost for each of the following project durations
Draw a network for the project using aon method : Draw a network for the project using AON method and evaluate the critical paths and identify them by double lining the arrows connecting the activities on the CP
Would you recommend that this project be adopted : Fortran Corporation - Would you recommend that the project be adopted
Environmental forces : Explain in your own words how heredity and environmental forces have combined to affect your development. Give one example of each and your answer should not exceed more than 100 words.
Purpose a production budget for second quarter of year : Purpose a production budget for the second quarter of the year and purpose a budget for the second quarter of the year showing the projected cost of the direct materials (plastic) that will be needed.
Creation of the work breakdown structure : Give a generic method for creating a project schedule starting with the creation of the work breakdown structure (WBS).

Reviews

Write a Review

Project Management Questions & Answers

  Benefits of developing using dashboard

The benefits of developing and using the dashboard in your organization.

  Performance dashboards

What training will be required if any, and what IT support will be necessary to maintain and sustain the dashboard

  Explain about project scope management

Explain why is Project Scope Management important to the success or failure of a project

  Controlling measures taken during the planning phase

What controlling measures should be taken during the planning phase.

  What is project''s terminal year cash flow now

Consider that in five years, Grant Publishing actually is able to get $140,000 for the equipment even though it has a book value of only $100,000 and what is the project's terminal year cash flow now?

  Project management practices

If you don't have personal experience with a project, research how project management practices have made projects successful.

  Project management - the value of progress reports

Show why are progress reports an integral part of project communications and what should they include? How are they different from a final report?

  Definition of quality dimensions

Provide an example of a "best buy" from your professional experience where quality aspects were not met in accordance to the text definition of quality dimensions.

  Analysis of the overall project risk

Analysis of the overall project risk

  Tools use to ensure projects are in control

What is meant by project control? What are some tools and mechanisms that we can utilize to ensure projects are in control?

  Show the project software scheduling

Project Software Scheduling - Explain how does the development of project software compare to other methods of scheduling.

  Explaining performance improvement project

Discuss a performance improvement project you have been involved in or had knowledge of.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd