Question: Workers at a packaging operation shovels a granular product from a large pile into sacks that are then sealed and placed on pallets for shipping. A sequence of 25 subgroups each consisting of the weights of 5 sacks has been recorded as follows:
Observations
Subgroup #
Sack 1
Sack 2
Sack 3
Sack 4
Sack 5
1
35.4
35.6
34.8
34.7
2
36
34.9
35.9
3
35.2
35
35.1
4
35.8
5
34.2
36.1
6
7
34.5
8
36.2
9
10
11
35.3
12
13
14
15
16
17
18
19
20
21
34.6
22
23
24
25
a- What is the appropriate control chart that can be used by the quality engineer in this case?
b- Determine the control limits (show your calculations)
c- Construct the appropriate control chart for the data above using MINITAB.
d- Is the process in-control? If not, when does the out-of-control behavior occur?
e- If the process is found to be out of control, drop the out-of-control points and use MINITAB to re-construct the control chart.
f- Is the process now in-control? If not, what to do next?
your mission is to analyse the australian car manufacturing industry by performing a 5 forces analysis and a life cycle
Which contract type is the most appropriate for the product or service purchase?
What do you see as the advantages and disadvantages of using project management software such as MS Project to organize a project, specifically looking at the project scope checklist below.
Question related to Replacement Project - At least something that could get me started and allow me to check my work when finished.
Analyze the development of the team in terms of the four-phase model. Does this model describe how the team evolved and analyze the group in terms of situational factors that influence team development.
stakeholder analysis for a communication management planwhat items should a communication management plan address? how
When would a project manager not allow changes to a baseline?
Describe three types of flexible benefits programs, and state the one you would recommend be implemented.
Explain how risk has impacted a project that you have been associated with as a team member or project leader.
Design the open pit mine slope and we have to do analysis - Project proposal in this want literature survey ,research problems ,research methods ,summary ,references
Define and show formal and informal communication networks as well as the three important functions of formal communication networks.
cost of production report using fifoequivalent productionbangor products manufactures electronics language translators.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd