engineering economics, Civil Engineering

Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working days of 10 hr each. The average height of excavation will be 18 ft, and the average angle of swing will be 80 degrees. The 3-cy shovel has a maximum digging height of 30 ft and the 5-cy machine;s maximum digging height is 34 ft. The efficiency factor will be a 50-min hour. Appropriate-size units can be used with either shovel. How many days will it require to complete the work? (5-cy machine, 105 days to complete
estion #Minimum 100 words accepted#
Posted Date: 7/11/2019 2:30:43 AM | Location : Ethiopia







Related Discussions:- engineering economics, Assignment Help, Ask Question on engineering economics, Get Answer, Expert's Help, engineering economics Discussions

Write discussion on engineering economics
Your posts are moderated
Related Questions
Determine the dimension of the vertical side walls for a rectangular open channel designed to convey 150 cfs of storm water runoff. The runoff is collected in the parking lots and

Design of Flexural Members: Here you have learnt how to design simple steel beams of rolled steel sections subjected to transverse loading. You have also known how to take

A No 10 steel rebar is tested in tension by monitoring the load reading of the testing machine it was found that the specimen yielded at aload of 41600lb and fractured at 48300 lb


The discharge of water collected from a constant head permeameter in a period of 15 minutes is 500 ml. The internal diameter of the permeameter is 5 cm and the measured difference

Cumulative distribution function - Poisson distribution: Find the cdf of Y = X 1 , + X 2 where X I and X 2 independently follow Poisson distribution with parameters λ l an


Stabilised Pavement Layers: Soil stabilisation is the process of treating a soil in such a manner as to alter and improve its properties for use as a pavement layer on sub-gr

Explain the Components of a rebound Hammer? Several components of a rebound hammer are displayed in below Figure. 1. Concrete surface; 2. Impact spring; 3. Rider on gui

A masonry wall with vertical back has a backfill 5 m behind it. The ground level is horizontal at the top and the ground water table is at ground level. Measured the horizontal pre