Question
What is the reason that shallow bedrock condition adverse for open berth piers?
Answer Most severe load on piers generally is horizontal load due to berthing of large vessels. Because widths of open berth piers are quite small thus they provides a short lever arm to counteract moment induced by berthing loads. Besides, dead load of open berth piers are normally quite light and therefore resisting moment provided by dead load of pier structures might not be sufficient to counteract the moment generated by berthing loads.
To aid in providing adequate confrontation to overturning moment by berthing load, soil resistance on top of bedrock contributes to stabilizing moment. Commonly adopted marine piling type such as driven steel tubular piles with reinforced concrete infill, driven piles be able to at mainly be founded on top of rockhead surface. In case rockhead level is shallow, then little soil cover might result in insufficient lateral resistance to berthing load.
Q. There is a railway colony of 500 house holds source of water is from a tube well 800 m away. The colony is 10 m higher then the ground at source. Tube well is 60 meters deep. De
The material that have lowest resistivity is Answer: Silver is the material
defference between direct and indirect ranging..
Sketch a curve showing the relation among dry density and moisture content for Standard Proctor test and indicate the salient features of the curve. Describe why soils are compacte
minimun difference in level of inlet and oulet pipe level invert in manhole
what is snowcem?
can you please provide with an example for mobilisation and demobilisation plan, induction and deployment schedule, broad execution schedule in excel,quantity schedule for major qu
what is the procedure for gsb proctor test for matrial sampling for lab density
Heliports and Stol Ports: Heliports Heliports are facilities for landing and take-off of helicopters. They consist of : (a) Landing and take-off area, which contai
1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd