Determine the governing effective length of a steel column, Civil Engineering

Assignment Help:

Determine the governing effective length of a steel column?

Determine the governing effective length of a W12 x 106 steel column that is 12' high, pinned at each end, and braced at mid-height about the weaker y-axis. Assume rx / ry = 1.76.

Solution:

- About weak y-axis, K*Ly = 6'

- About strong x-axis, K*Lx = 12'

- The equivalent effective length about the major axis with respect to y-axis is:

954_Determine the governing effective length of a steel column.png


Related Discussions:- Determine the governing effective length of a steel column

Define the shock transmission unit, Define the Shock Transmission Unit? ...

Define the Shock Transmission Unit? Ever since engineers have started designing multi span simply supported bridges, they have been dreaming of connecting all the spans togethe

Pre-tensioned concrete elements, Pre-tensioned concrete elements It is ...

Pre-tensioned concrete elements It is the act of transferring the stress in prestressing tendons to the concrete member. In the case of pre-tensioned concrete elements, this st

Underwater Rebound Hammer, Would there be a difference in the result of an ...

Would there be a difference in the result of an underwater rebound hammer versus a typical rebound hammer?

Surveying, What''re the procedures of contouring by graphical interpolation...

What''re the procedures of contouring by graphical interpolation

Theorem of three moments, Theorem of three moments: You have been intr...

Theorem of three moments: You have been introduced to the analysis of one of the important class of structures, namely Statically Indeterminate Structures. You have been intro

Dam details, how to prepare a project of final year

how to prepare a project of final year

Compute the degree of saturation, The maximum dry density and optimum moist...

The maximum dry density and optimum moisture content of a soil from standard proctor's test are 18 kN/m 3 and 16% respectively. Compute the degree of saturation of the sample,

Explain a critical path - construction management, Explain a Critical Path ...

Explain a Critical Path The series of activities which determines the earliest possible date of project completion Usually defined as those activities with minimal or

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd