Explain mild and high-yield steel, Civil Engineering

Assignment Help:

High-yield steel vs. mild steel as road reinforcement

High yield steel is the preferred material for the reinforcement of concrete carriageway due to the subsequent reasons:

(i)  The primary function of steel reinforcement in concrete pavement is to control cracking. If mild steel is adopted for reinforcement, upon initiation of crack formation mild steel becomes overstressed and is prone to yielding. High yield steel provides resistance to crack growth. The above situation is generally encountered where there is abnormal traffic loads on concrete carriageway exceeding the design limit. 

(ii) High-yield steel is less prone to deformation and bending at the time of routine handling operation.

(iii)In the current market, steel mesh reinforcement is generally of high-yield steel type and usage of mild steel as road reinforcement needs the placing of special orders to the suppliers.


Related Discussions:- Explain mild and high-yield steel

Surveying, sample problems with solutions for probable value

sample problems with solutions for probable value

Smallest size of a325 bolts needed for two plates in tension, What is the s...

What is the smallest size of A325 bolts required for the two plates in tension noted below, assuming the thickness of each plate is 1.0-in. and the applied force at each end is P=2

Steps to determine brake (bhp) and motor horsepower (mhp), Steps to determi...

Steps to determine the brake (bhp) and motor horsepower (mhp):  1) Determine water horsepower (whp). h A (Qgpm) (SG) / 3956 OR h A (Qcfs) (SG) / 8.814 2) Apply the pump

Explain flash butt welding, Q. Explain Flash Butt welding? In this proc...

Q. Explain Flash Butt welding? In this process the ends of two rails are kept at fixed distance apart and a mould (designed to suit the rail section ) is fitted on. The rail en

Light and rapid rail transit, Light Rail Transit (LRT) Light Rail Tra...

Light Rail Transit (LRT) Light Rail Transit is also known by the name train. LRT can be run on the surface if road space is available (as in Kolkata) or as elevated, with pil

Ground water, Two pumping wells 1,000 m away fully penetrate the same confi...

Two pumping wells 1,000 m away fully penetrate the same confined aquifer. One of the wells pumps at a rate of 1,240 m3/day. The second well pumps at 850 m3/day. If the aquifer has

Measure the ultimate settlement due to pumping, A clay stratum of 18 metres...

A clay stratum of 18 metres thickness was found above a sand stratum when a boring was made. The clay was consolidated under the present overburden pressure. The hydrostatic pressu

Surveying, what is meant by geodetic survey

what is meant by geodetic survey

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd