What is the estimated cost of the whole project, Project Management

Assignment Help:

Question 1:

(a) Using information from Table 1, build a network diagram for the project.

(b) Perform a Forward Pass on the network diagram and deduce the duration of the project.

(c) What is the estimated cost of the whole project?

(d) Perform a Backward Pass on the network diagram and deduce the float for each task.

(e) What can you say about flexibility in the project in the light of the above?

Question 2:

(a) What is the rationale behind earned value analysis in project monitoring and how is it helpful?

(b) Using information in Table 2, calculate the schedule variance and cost variance for each task in the project at timenow 30 days

(c) In light of calculations above, comment on the progress of the project with respect to the schedule. What is the expected duration of project if started (but incomplete) tasks continue on the same trend and if tasks which have not started yet proceed as per schedule?

(d) In light of calculations above, what is the expected cost of the project now?

(e) What corrective action would you recommend at this stage of the project?


Related Discussions:- What is the estimated cost of the whole project

Professional boundaries, An enrolled nurse has been assigned to care for a ...

An enrolled nurse has been assigned to care for a close relative who she cares for deeply who has been admitted to hospital with chest pain.  Nobody knows that this patient is rela

Discuss the importance of proper design for a hospitality, Question 1: ...

Question 1: Discuss the importance of proper design for a hospitality unit of your choice. Support your answer with relevant examples from the appropriate industry. Q

Determine the critical path by activities and duration, Determine the criti...

Determine the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

Manufacturer''s promotional activity, Explain how a manufacturer's promotio...

Explain how a manufacturer's promotional activity might vary depending upon the sort of distribution channel that operates. Distribution includes getting the right products to

What do project managers do, Q.  What do project managers do? First of ...

Q.  What do project managers do? First of all project managers have to take responsibility for leading the project effort towards the stated and agreed upon goals and objective

Describe incremental approach to testing by unit test, Describe the increme...

Describe the incremental approach to testing represented by the orderly unit (module) test. Unit (module) test: Along with the incremental approach to testing, every unit

PMP, critical analysis of the pmp

critical analysis of the pmp

Strategic Procurement and SCM, determine the most significant changes that ...

determine the most significant changes that have occurred in procurement in the last few years and what this means for your organization or an organization of your choice.

Nancy, explain the main typical data input errors that affect deliver of pr...

explain the main typical data input errors that affect deliver of project

Caselet, what action should be taken by various functioal managers to meet ...

what action should be taken by various functioal managers to meet the scheduled dates

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd