Different strategies that lg use to manage the conflict, Project Management

Assignment Help:

LG, the Managing Director of NWP Company, recently announced to the workforce that the Board had agreed to the establishment of a set of new working practices which should lead to improved productivity. The new working practices will mean the introduction of weekend working and the rotation of shifts for all workers.

Discuss the different strategies that LG could use to manage the conflict occurring in NWP Company.


There are a number of dissimilar ways LG could handle the vertical conflict in NWP Company which is occurring as a result of the announcement to introduce latest working practices. For instance, he could make use of the five conflict handling strategies identified by Thomas which are based on two conflict management dimensions:

    the degree of assertiveness in pursuit of one's interests, and
    the level of cooperation in attempting to satisfy others' interests.


Related Discussions:- Different strategies that lg use to manage the conflict

Earned value management is a systematic approach, Question: (a) Earned...

Question: (a) Earned Value Management is a systematic approach to the integration and measurement of cost, schedule, and technical accomplishments in a project. List the benef

Prepare an action plan based on your findings, As a newly appointed rector ...

As a newly appointed rector of your school, you have received many complaints from students .It is your aim to " democratise quality ", that is to make quality control comprehensib

Effective project control, Project control processes cannot be overemphasis...

Project control processes cannot be overemphasised in their significance to the success of a project. The project manager must continually take a pro-active approach in controlling

Bidding , Bidding is a process in which you  quote money in exchange of go...

Bidding is a process in which you  quote money in exchange of goods or services through an auction. They are two types of auctions: open auction and silent auction. In an open auc

Project organisation structure, P roject organisation In this type of ...

P roject organisation In this type of organisation, the project management needs of all divisions of the company are served by a centralized separate division of skilled manag

What are the pros and cons of a pure project organisation, What are the pro...

What are the pros and cons of a ‘pure’ project organisation compared along with a project operating into a matrix structure? A ‘pure’ project organisation comprises into itself

What is buffering in risk management, What is Buffering in risk management?...

What is Buffering in risk management? Buffering: Buffering or slack is the allowance of additional cost, resources or time for example ‘just in case’ specific events or r

What is the role of strategy in project management, Problem 1: a) What ...

Problem 1: a) What is the role of strategy in project management? b Explain the importance of aligning H.R projects with the organizational strategy. c) What are the impa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd