The purpose of a project initiation document, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Describe to S Company the purpose of a project initiation document and what should have been included in the document for the hotel refurbishment project.

 

At the starting of a project a Project Initiation Document (PID) should be produced. This is sometimes referred to as the project charter. The purpose of the project initiation document (PID) is to define the overall mission, scope and deliverables needed, and the roles and responsibilities of the project stakeholders in order to provide the overriding terms of reference for the life of the project. The document can then act as a base document against which progress can be assessed.

Contents

Purpose Statement

From the detailed discussions with the hotel, information should be collected to describe why the project is essential i.e. why the refurbishment is being undertaken.

Scope statement

This should put boundaries to the hotel project by outlining the main activities. This section is significant in preventing 'scope creep' where additional activities are added making achievement of the cost and time objectives fully impossible. This appears to be what is happening with the hotel project and why a meeting is required.

Deliverables

This would list the objectives and tangible elements of the project like reports, assets and desired outcomes.  For the hotel project that would be the exact requirements for the refurbishment.

 


Related Discussions:- The purpose of a project initiation document

What are the claimed advantages of rad approaches, What have RAD and extrem...

What have RAD and extreme programming got in common? What are the claimed advantages of these approaches? Both XP and RAD have as their common intention, and when their primary

Explain the terms - product and work package, Explain the terms "product" a...

Explain the terms "product" and "work package" and describe how these are related to each other. A product is a particular deliverable from a project and this may also make a wo

Program management process , Define the concept of Program Management Proce...

Define the concept of Program Management Process  As we learnt in the previous section Program?s process depends mostly on the characteristics of the product/service offered by

Risk managemet, How do I create a risk management plan

How do I create a risk management plan

Explain feasibility analysis and product development process, Q. Explain Fe...

Q. Explain Feasibility Analysis and Product development process? Once the product concepts have been  formed, the feasibility studies are conducted. This study involves the fol

How are carrying costs varied with quantity order, How are carrying costs v...

How are carrying costs varied with quantity order? Carrying Costs, that vary along with quantity ordered, contained as a. There Interest on capital investment b. There Co

Launch a new school, how we launch a new school? which steps should keep in...

how we launch a new school? which steps should keep in mind? whats srategies and policies can apply? what is the history of ne school? i need urgent answer

Describe edgar scheins levels of organisational culture, Problem 1: Des...

Problem 1: Describe the importance of Employee Relations Management in an organisation. Describe employee relations management Importance of employee relations managem

NETWORK DIAGRAMS, AHOW TO FIND THE VARIANCE OF AN ACTIVITY AND THE THE PROB...

AHOW TO FIND THE VARIANCE OF AN ACTIVITY AND THE THE PROBABILTY THAT A WORK WILL BE FINISHED IN A GIVEN NUMBER OF DAYSsk question #Minimum 100 words accepted#

Structure, Differences between wbs and product breakdown structure, Project...

Differences between wbs and product breakdown structure, Project Management

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd