Software project planning, Computer Engineering

Assignment Help:

Software Project Planning

In the previous days of computing software costs comprised a small % of overall computer based system cost. In order of magnitude error software cost had relatively little impact in estimates of. Presently, software is the most expensive elements in most computer-based systems. With large cost estimation error can make the variation among loss and profit. For the developer Cost overrun can be disastrous.

Software effort and cost estimation will never be an exact science.  There are Too many variables human Technical, Environmental, Political can affect the ultimate effort and cost of software applied to build it. However software project estimation can be transformed from a mysterious art to a series of systematic steps that gives estimates with acceptable risk.

To achieve reliable effort and cost estimates a number of options arise.

1.    The Delay estimation until late in the project (obviously, we can achieve 100% accurate estimates after the project is completed)

2.    The Base estimates on same projects that have already been completed.

3.    The Use relatively simple decomposition techniques to generate project effort and cost estimates.

4.    The Use one or more empirical models for software cost and effort estimation.

Unfortunately, the first option moreover attractive is not practical.  The Cost estimates must be provided up- front.   However, we will recognize that the longer we wait the more we know and the more we know the less likely we are to make serious errors in our estimates.

The option can work reasonably well if the present project is quite same to previous efforts and other project   influences  for example business   conditions,   the   customer,   the   SEE   deadlines  are   equivalent. Unfortunately, previous experience has not always been a good indicator of future results.

The remaining options are viable approaches to software project estimation. Ideally, the method noted for each option should be applied in tandems each used as a cross-check for the other.  The Decomposition techniques will take a divide and conquer approach to software project estimation. By decomposing a project into a major functions and related software engineering activities effort and cost estimation can be performed in a stepwise fashion.  Empirical estimation models can be used to complement decomposition methods and offer a potentially valuable estimation approach in their own right.  The model is based on experience historical data and takes the form.

d=f(Vi)

Where d is one of a number of estimated values example for effort, cost, project duration and Vi are selected independent parameters for example estimated LOC or FP

The Automated estimation tools implements one or more decomposition methods or empirical models.

When combined with an interactive human machine interface automated tools give an attractive option for estimating. Like systems the characteristics of the development company for example experience, environment and the software to be developed are described.  Effort and Cost estimates are derived from these data.

As the historical data used to seed the estimate each of the viable software cost estimation options is only as good. If no historical data exist costing rests on a very shaky foundation.


Related Discussions:- Software project planning

Rdbms, what is physical data structure in internals of rdbms?

what is physical data structure in internals of rdbms?

Explain the real time system, What is real time system? A real time sys...

What is real time system? A real time system has well explained, fixed time constraints. Processing must be done within the explained constraints, or the system will fail. It i

Data validation and data transfer, Data Validation condition: The following...

Data Validation condition: The following condition stated below must be met for a data to be valid as is shown in the figure 3a below. 1. The data on the SDA line must remain stabl

Vliw instruction word, VLIW instruction word is compacted to have floating-...

VLIW instruction word is compacted to have floating-point addition, one branch, floating point multiply, and one integer arithmetic and load/store operation as displayed in Figure

Write a program to perform multiplication of two numbers, Q. Write a progr...

Q. Write a program to perform multiplication of two numbers in specified radix. Check that entered numbers are in specified radix or not else error message should be displayed.

Show the conflict in register, Q. Show the conflict in register? All mi...

Q. Show the conflict in register? All micro-operations written on a line are to be executed at same time provided the statements or a group of statements to be implemented toge

What are the advantages of open source system, What are the advantages of o...

What are the advantages of open source system? High-quality software Lesser hardware costs Integrated management No vendor lock-in Take control of our softwa

CONVERT NUMBER TO ALPHABET, HOW TO CONVERT THE NUMBER INTO ALPHABET USING C...

HOW TO CONVERT THE NUMBER INTO ALPHABET USING C/C++ PROGRAM

Parallel computer architecture , Parallel Computer Architecture Intr...

Parallel Computer Architecture Introduction We have talked about the classification of parallel computers and their interconnection networks in that order in units 2 and

Minimum number of two input nand gates in assembly line, An assembly line c...

An assembly line consists of 3 fail safe sensors and one emergency shutdown switch. The line must keep moving unless any of the given conditions occur: a. When the emergency swi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd