Software project planning, Computer Engineering

Assignment Help:

Software Project Planning

In the previous days of computing software costs comprised a small % of overall computer based system cost. In order of magnitude error software cost had relatively little impact in estimates of. Presently, software is the most expensive elements in most computer-based systems. With large cost estimation error can make the variation among loss and profit. For the developer Cost overrun can be disastrous.

Software effort and cost estimation will never be an exact science.  There are Too many variables human Technical, Environmental, Political can affect the ultimate effort and cost of software applied to build it. However software project estimation can be transformed from a mysterious art to a series of systematic steps that gives estimates with acceptable risk.

To achieve reliable effort and cost estimates a number of options arise.

1.    The Delay estimation until late in the project (obviously, we can achieve 100% accurate estimates after the project is completed)

2.    The Base estimates on same projects that have already been completed.

3.    The Use relatively simple decomposition techniques to generate project effort and cost estimates.

4.    The Use one or more empirical models for software cost and effort estimation.

Unfortunately, the first option moreover attractive is not practical.  The Cost estimates must be provided up- front.   However, we will recognize that the longer we wait the more we know and the more we know the less likely we are to make serious errors in our estimates.

The option can work reasonably well if the present project is quite same to previous efforts and other project   influences  for example business   conditions,   the   customer,   the   SEE   deadlines  are   equivalent. Unfortunately, previous experience has not always been a good indicator of future results.

The remaining options are viable approaches to software project estimation. Ideally, the method noted for each option should be applied in tandems each used as a cross-check for the other.  The Decomposition techniques will take a divide and conquer approach to software project estimation. By decomposing a project into a major functions and related software engineering activities effort and cost estimation can be performed in a stepwise fashion.  Empirical estimation models can be used to complement decomposition methods and offer a potentially valuable estimation approach in their own right.  The model is based on experience historical data and takes the form.

d=f(Vi)

Where d is one of a number of estimated values example for effort, cost, project duration and Vi are selected independent parameters for example estimated LOC or FP

The Automated estimation tools implements one or more decomposition methods or empirical models.

When combined with an interactive human machine interface automated tools give an attractive option for estimating. Like systems the characteristics of the development company for example experience, environment and the software to be developed are described.  Effort and Cost estimates are derived from these data.

As the historical data used to seed the estimate each of the viable software cost estimation options is only as good. If no historical data exist costing rests on a very shaky foundation.


Related Discussions:- Software project planning

State the web server security through ssl, Web server security through SSL ...

Web server security through SSL (Secure Socket Layer) As it is well known that the Intranets and internet are purely based on use of powerful web servers to deliver information

Design a 4:1 mux in verilog, Design a 4:1 mux in Verilog   Mult...

Design a 4:1 mux in Verilog   Multiple styles of coding. e.g. Using if-else statements if(sel_1 == 0 && sel_0 == 0) output = I0; else if(sel_1 == 0 && sel_0 ==

Explain about the term rtl fix, Explain about the term RTL Fix. RTL Fix...

Explain about the term RTL Fix. RTL Fix: An RTL fix implies you change the Verilog/VHDL code and you resynthesize. This generally means a new Plance and Route. RTL fixes wou

Define about exe programs, Q. Define about EXE Programs? An EXE program...

Q. Define about EXE Programs? An EXE program is stored on disk with extension .exe. EXE programs are longer than COM programs as every EXE program is related with an EXE header

Operation of micro-programmed control unit, Micro-instructions are stored i...

Micro-instructions are stored in control memory. Address register for control memory comprises the address of subsequent instruction which is to be read. Control memory Buffer Regi

What is a work process, What is a work process? A work process is where ...

What is a work process? A work process is where individual dialog steps are in fact processed and the work is done.  Every work process ocuurs one type of request.

Application layer in tcp/ip model corresponds to for what, Application laye...

Application layer (layer 4) in TCP/IP model corresponds to? In OSI model, application layer (layer 4) in TCP/IP model corresponds to layer 6 and layer 7.

Paging, specification of paging ram size is 12 frames

specification of paging ram size is 12 frames

Differentiate b/w program translation and interpretation, Differentiate bet...

Differentiate between program translation and program interpretation. The program translation model makes the execution gap through translating a program written in a program

Characteristics of decision support system, Q. Characteristics of decision ...

Q. Characteristics of decision support system? Characteristics of DSS- The qualities of the DSS are as follows: - 1. DSS focus on towards providing assistance in analyzing s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd