Software project planning, Computer Engineering

Assignment Help:

Software Project Planning

In the previous days of computing software costs comprised a small % of overall computer based system cost. In order of magnitude error software cost had relatively little impact in estimates of. Presently, software is the most expensive elements in most computer-based systems. With large cost estimation error can make the variation among loss and profit. For the developer Cost overrun can be disastrous.

Software effort and cost estimation will never be an exact science.  There are Too many variables human Technical, Environmental, Political can affect the ultimate effort and cost of software applied to build it. However software project estimation can be transformed from a mysterious art to a series of systematic steps that gives estimates with acceptable risk.

To achieve reliable effort and cost estimates a number of options arise.

1.    The Delay estimation until late in the project (obviously, we can achieve 100% accurate estimates after the project is completed)

2.    The Base estimates on same projects that have already been completed.

3.    The Use relatively simple decomposition techniques to generate project effort and cost estimates.

4.    The Use one or more empirical models for software cost and effort estimation.

Unfortunately, the first option moreover attractive is not practical.  The Cost estimates must be provided up- front.   However, we will recognize that the longer we wait the more we know and the more we know the less likely we are to make serious errors in our estimates.

The option can work reasonably well if the present project is quite same to previous efforts and other project   influences  for example business   conditions,   the   customer,   the   SEE   deadlines  are   equivalent. Unfortunately, previous experience has not always been a good indicator of future results.

The remaining options are viable approaches to software project estimation. Ideally, the method noted for each option should be applied in tandems each used as a cross-check for the other.  The Decomposition techniques will take a divide and conquer approach to software project estimation. By decomposing a project into a major functions and related software engineering activities effort and cost estimation can be performed in a stepwise fashion.  Empirical estimation models can be used to complement decomposition methods and offer a potentially valuable estimation approach in their own right.  The model is based on experience historical data and takes the form.

d=f(Vi)

Where d is one of a number of estimated values example for effort, cost, project duration and Vi are selected independent parameters for example estimated LOC or FP

The Automated estimation tools implements one or more decomposition methods or empirical models.

When combined with an interactive human machine interface automated tools give an attractive option for estimating. Like systems the characteristics of the development company for example experience, environment and the software to be developed are described.  Effort and Cost estimates are derived from these data.

As the historical data used to seed the estimate each of the viable software cost estimation options is only as good. If no historical data exist costing rests on a very shaky foundation.


Related Discussions:- Software project planning

Explain the semantics of each field of ethernet frame, Give the format of E...

Give the format of Ethernet frame and explain the semantics of each field. An Ethernet frame starts with headers which have three fields. The 64-bit preamble, which precedes th

Illustrate about the macros and give its example, Illustrate about the macr...

Illustrate about the macros and give its example For instance, assume you want some data to be input into a spreadsheet if result of a calculation in cell K40 is negative: m

What are the advantages offered by data mining, What are the advantages off...

What are the advantages offered by data mining? Advantages offered through Data Mining are given below: a) Facilitates discovery of knowledge through massive, large data set

What do you mean by best fit, What do you mean by best fit?  Best fit a...

What do you mean by best fit?  Best fit allocates the smallest hole that is big enough. The whole list has to be searched, unless it is sorted by size. This method makes the sm

Hazard, how to calculate delay for hazard?

how to calculate delay for hazard?

Construct a shift register from S-R flip-flops, Construct a shift register ...

Construct a shift register from S-R flip-flops. Explain its working. Ans: S-R Flip-Flop Shift Register: Shift registers can be built through using SR flip-flops. Fig.(a)

Ending transactions - data phase, Ending transactions: Either side may...

Ending transactions: Either side may request that a burst end after the present data phase. Simple PCI component that do not support multi-word bursts will always request this

What is the functionality of remote login, What is the functionality of Rem...

What is the functionality of Remote Login? Remote Login gives similar functionality of telnet, along with the added functionality of not involving a password from trusted cli

Equivalence between vhdl and c, Equivalence between VHDL and C? There i...

Equivalence between VHDL and C? There is concept of understanding in C there is structure.Based upon requirement structure provide facility to store collection of various data

What do you mean by decoders, Q. What do you mean by Decoders? Decoder ...

Q. What do you mean by Decoders? Decoder transforms one kind of coded information to other form. A decoder has n inputs and one enable line (sort of selection line) and 2 n ou

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd