BFW from water treatment area is sent to the BFW Booster pumps at temperature around 105°C. The BFW is then heated and fed to the HP BFW Pumps.

Chelant and oxygen scavenger are added to inhibit scale formation and remove DO in the BFW, respectively.

The high pressure BFW is boiled in the Steam Generators to generate 80% to 100% quality steam. Wet HP steam (for steam quality less than 100%) is sent to the HP Steam Separator to remove liquid and 100% quality steam is fed to the HP steam pipelines for injection at the well pads.

Liquid blowdown from HP Steam Separator is throttled down to lower pressure and sent to the MP Steam Separator for vapour-liquid separation.

Neutralizing amine is injected into the steam condensation system to prevent corrosion. The blowdown is cooled down and fed to the Evaporator Feed Tank.


Related Discussions:- Process of steam generation unit

Kennedy’s theorem-klein’s construction, Kennedy’s Theorem: According to t...

Kennedy’s Theorem: According to this theorem the relative instantaneous centres on whichever three bodies that contain motion relative to each other are collinear. Higher Pa

Introduction service and maintenance procedures , INTRODUCTIO : In Motorc...

INTRODUCTIO : In Motorcycle Servicing, we studied about servicing of a motorcycle. Here, you will study about the detailed procedures for motorcycle service and maintenance. The s

About Transfer Function block, How can i change the normal function block p...

How can i change the normal function block parameter[1 1]=>(s+1) to (s-1)?

How to select the project if not yet done - general phase, To select the pr...

To select the project, if not already done - Radial Drilling Machine Due to above Problem?s in RADIALL DRILLING machine, now the select the project and solves the problems and

Plant level - safety organization, Plant level - Safety Organization ...

Plant level - Safety Organization This level works at plant level and would directly report to general manager safety. There must be four plant safety managers as recognized

Crystal structure , Explain with neat sketches the various types of crystal...

Explain with neat sketches the various types of crystal imperfections

Project quality plan, Project Quality Plan Design verification require...

Project Quality Plan Design verification requirements for a project are to be established in the Quality Plan sub-section of the Project Execution Plan. The Lead Mechanical E

Determine the maximum stress - spring , Determine the maximum stress: ...

Determine the maximum stress: A laminated spring of the quarter elliptic type, 0.6 m long, is to give a static deflection of 80 mm under an end load of 2000 N. If the leaf mat

Find out the reactions at point, Find out the reactions at point: A be...

Find out the reactions at point: A beam AB is hinged at A and is supported at C. It is loaded as revealed in Figure. Find out the reactions at A and C. Solution L

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd