Process of steam generation unit, Mechanical Engineering

Assignment Help:

Q. Process of Steam generation unit?

BFW from water treatment area is sent to the BFW Booster pumps at temperature around 105°C. The BFW is then heated and fed to the HP BFW Pumps.

Chelant and oxygen scavenger are added to inhibit scale formation and remove DO in the BFW, respectively.

The high pressure BFW is boiled in the Steam Generators to generate 80% to 100% quality steam. Wet HP steam (for steam quality less than 100%) is sent to the HP Steam Separator to remove liquid and 100% quality steam is fed to the HP steam pipelines for injection at the well pads.

Liquid blowdown from HP Steam Separator is throttled down to lower pressure and sent to the MP Steam Separator for vapour-liquid separation.

Neutralizing amine is injected into the steam condensation system to prevent corrosion. The blowdown is cooled down and fed to the Evaporator Feed Tank.


Related Discussions:- Process of steam generation unit

Annotation with leaders, Annotation with Leaders Ordinate dimensions ar...

Annotation with Leaders Ordinate dimensions are not really an dimensions at all in that they do not indicate a measurement.They annotate known as a co-ordinate points. The DIMO

Tempering, TEMPERING: The hardening treatment specified to steel rais...

TEMPERING: The hardening treatment specified to steel raises the hardness but initiates internal stresses due to different cooling rates. The internal stresses are created al

Explain concept of a corner or angled window, Question 1: Retail design...

Question 1: Retail design tends to be rapid turnover business. Your potential client needs a window display for his retail sports wear shop for the summer sales. The assumed bu

Determine tangential and normal stresses, A rectangular block of material i...

A rectangular block of material is subjected to stresses 65N/mm 2 (tensile) in x- direction and 35 N/mm 2 (tensile) in perpendicular direction. It is accompanied by shear stress

Evaluate plant load factor, a) Illustrate principal of magneto hydro dynami...

a) Illustrate principal of magneto hydro dynamic system (MHD) with diagram? b) a thermal power plant has two 60 MW units each running for 8000hrs and one 30MW unit running for 2

Equiliubrium, Review questions condition of equilibrium grade 11 unit 7

Review questions condition of equilibrium grade 11 unit 7

Explain in detail about the large excavations, Explain in detail about the ...

Explain in detail about the Large excavations Large excavations required for construction of rafts may need dewatering, depending on the ground water flow and the choice of  a

Determine the wire drawing - cold drawing processes, Determine the Wire Dra...

Determine the Wire Drawing - cold drawing processes Similar to above process bars are first pickled, washed and coated to prevent any oxidation. After this rods are passed t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd