Plants aeration period:

Problem:

What is the plant's aeration period?

Solution

The plant's aeration period is the number of hours that the wastewater is aerated during the activated sludge process. These equivalents the hydraulic detention time of the biological reactor

θ= V/Q = 5, 000, 000 l/33.75 × 106 l / day = 0.15 day = 3.6 hours.


Related Discussions:- Plants aeration period

Define cast iron substructure - inspection of bridge, Define Cast iron subs...

Define Cast iron substructure - Inspection of bridge? Cast Iron also has the problem of corrosion due to atmosphere, which is similar to that of steel. However, in acidic or br

Differences between pipe jacking and micro-tunnelling, Q. Differences betwe...

Q. Differences between pipe jacking and micro-tunnelling? Pipe jacking is a general scheme of installation of pipes with a tunnelling shield in front and the pipes are jacked f

Minimum and maximum area of reinforcement, Q. Minimum and maximum area of r...

Q. Minimum and maximum area of reinforcement? Minimum area of reinforcement vs. maximum area of reinforcement Beams can be designed to be larger than required for strength

Soil plug in marine piling system of steel tubular pile, Soil plug in marin...

Soil plug in marine piling system of steel tubular pile with reinforced concrete infill At the time of initial driving process, open-ended steel piles are driven through the s

Shear strength of concrete., why do we use effective depth ''d'' in calcula...

why do we use effective depth ''d'' in calculating the shear capacity of uncracked Concrete beam. If it is uncracked, why cant we use the full depth ''D''.

Manage civil work design, Ask question #Minimum 1Make a detailed list of al...

Ask question #Minimum 1Make a detailed list of all constraints and requirements to the bridge design00 words accepted#

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Theodolote, List out the permanent adjustments of dumpy level.

List out the permanent adjustments of dumpy level.

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd