Normal approximation to compute the probability, Civil Engineering

Assignment Help:

Normal approximation to compute the probability:

A lot contains 100 articles of which 10 are defective. The lot is rejected if a random sample of 10 articles drawn from the lot contains more than 2 defectives. Use normal approximation to compute the probability that the lot is accepted.

Solution:

Let X represents the number of defective articles in the sample. The variable X follows the hypergeometric distribution with parameters

N = 100,n - 10,M = l0 and has E(X) = 10.(10/100) = 1 and

V(X) =σ2 = 10.10/100.(1-(10/100)) (100-10/100-1) =9/11

The required probability is

903_Normal approximation to compute the probability.png


Related Discussions:- Normal approximation to compute the probability

Traverse, how to fill traverse computation sheet of opened traversig ..

how to fill traverse computation sheet of opened traversig ..

Define the degree of saturation and soil moisture content, Establish the r...

Establish the relationship among degree of saturation, soil moisture content, definite gravity of soil particles, and void ratio. The volume of an undisturbed clay sample having

Epoxy-coated bars vs galvanized bars, Bonding performance to concrete: Epox...

Bonding performance to concrete: Epoxy-coated bars vs. galvanized bars  Based on the findings of CEB Bulletin 211 the bonding of galvanized bars to concrete is lower in early

Design of prestressed concrete pipes, Design of prestressed concrete pipes ...

Design of prestressed concrete pipes The design of prestressed concrete pipes should cover the following five stages : (a) Circumferential prestressing, winding with or wit

Use of primers in joint sealant, Q. Use of primers in joint sealant? Mo...

Q. Use of primers in joint sealant? Most of the joint sealants applied in concrete joints are adhesive and recommended joint width/depth of joint sealant is from 2:1 to 1:1 as

Explain the system curves - pumping system, Explain the System Curves - Pum...

Explain the System Curves - Pumping System Non-linear plot beginning on the y-axis at the Total Static Head (TSH) and plotted primarily based on the h f .

SURVEYING, TYPES OF OBSTACLES IN CHAIN SURVEYING

TYPES OF OBSTACLES IN CHAIN SURVEYING

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd