Use single lock nuts or double lock nuts, Civil Engineering

Assignment Help:

Question

In linking fenders to pier organizations, would single lock nuts or double lock nuts be used?


Answer

In pier structures connection offenders to piers is achieved by using single lock nuts. But, they do not perform well since some timber fenders loosen additional easily when subject to vibrating loads due to berthing, wave and tidal actions. To explain this problem, double lock nuts must be adopted as they prove to function satisfactory in structural elements that are subject to frequent vibration loads.

 


Related Discussions:- Use single lock nuts or double lock nuts

Explain the unconfined compression strength of the clay, A square group of ...

A square group of 9 piles was driven into soft clay extending to a large depth. The diameter and length of the piles were 30 cm and 9 m respectively. If the unconfined compression

Define vertical curves - transportation, Define Vertical Curves  - Transpor...

Define Vertical Curves  - Transportation 1) Vertical curves are used to change the grade of a highway. 2) Most vertical curves take the shape of an equal-tangent parabola.

Show the overlays on concrete bridge deck, Q. Show the Overlays on concrete...

Q. Show the Overlays on concrete bridge deck? After years of servicing, some overlays can be applied on the top surface of bridges. Overlays on concrete bridge decks achieve th

Parabola, how to draw a parabola

how to draw a parabola

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Practice to form washout regulators, Question Why are two gate regulato...

Question Why are two gate regulators necessary in regular practice to form washout regulators ? Answer In fact, situation is analogous to that of fire hydrants in tha

Explain the design of waterway, Q. Explain the Design of waterway? When...

Q. Explain the Design of waterway? When the river flows between high banks and the whole width is actively functioning during high floods, the bridge waterway should practicall

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd