Explain about vierendeel girder, Civil Engineering

Assignment Help:

Q. Explain about Vierendeel girder?

Vierendeel girder design is sometimes adopted in design of footbridges. Traditionally truss design, triangular shape of truss is generally used since the shape can't be changed without altering the length of its members. By applying loads only to joints of trusses, members of truss are only subjected to a uniform tensile or compressive stress across their cross sections since their lines of action pass through a common hinged joint. 

Vierendeel girder/truss is characterized by having only vertical members between the top and bottom chords and is a statically indeterminate structure. Therefore bending, shear and axial capacity of these members contribute to resistance to external loads. The use of this girder enables footbridge to span larger distances and present an attractive outlook. Though it suffers from the disadvantage that distribution of stresses is more complicated than normal truss structures.

1648_Explain about Vierendeel girder.png

Fig.Vierendeel Truss.


Related Discussions:- Explain about vierendeel girder

Survey, 3-d figure of line ranger

3-d figure of line ranger

Demonstrate the design of prestressed concrete poles, Demonstrate the Desi...

Demonstrate the Design  of Prestressed concrete poles Prestressed concrete poles are generally designed as members with uniform prestress since they are subjected to bending mo

Explain the difference in elevation between bm and tp2, Based on the inform...

Based on the information provided in Figure, the difference in elevation between BM and TP 2 is most nearly: Solution: Set up a Table as shown below and insert the kno

HIGHWAY CONSTRUCTION & MAINTENANCE, what is the difference between feasibil...

what is the difference between feasibility study and traffic counting

Ground water, Two pumping wells 1,000 m away fully penetrate the same confi...

Two pumping wells 1,000 m away fully penetrate the same confined aquifer. One of the wells pumps at a rate of 1,240 m3/day. The second well pumps at 850 m3/day. If the aquifer has

Block contouring, how to calculate contour surveyed area

how to calculate contour surveyed area

Monitoring state of reclamation, Question Geotechnical Instrumentation ...

Question Geotechnical Instrumentation is often employed for monitoring state of reclamation . From time to time two piezometers are installed inside same borehole. What is mai

Stress design method, You have been selected to assist the structural engin...

You have been selected to assist the structural engineer for a bridge replacement project.  Your task is to design the size of the footing for an interior bridge pier, based on the

What is the station at point b, What is the station at Point B? SO...

What is the station at Point B? SOLUTION 3 Station at Point A = Sta 22+45  Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273'  = Sta 32+73

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd