In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Explain about void ratio drops, A clay layer 25 metres thick has a saturate...

A clay layer 25 metres thick has a saturated unit weight of 19.2 kN/m 2 . Ground water level occurs at a depth of 5 metres. It is proposed to construct a reinforced concrete founda

Spalling reinforcement for pre stressing works, Spalling reinforcement for ...

Spalling reinforcement for pre stressing works in anchor blocks Reinforcement of anchor blocks in prestressing works usuallycomprises equilibrium reinforcement, bursting reinfo

Bending moments& shear force, calculate bending &shear force of 16kn/m and ...

calculate bending &shear force of 16kn/m and draw the shear force and bending moment diagrams

Disparities between regular precast and pipe jacking, Question What are...

Question What are main disparities in design between regular precast concrete pipes and pipes used for pipe jacking ? Answer For pipes used for pipe jacking, they h

Laplace transform, Using Laplace transfom, the following differential equat...

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

Explain gap survey and adjustment of gap, Q. Explain Gap Survey and adjustm...

Q. Explain Gap Survey and adjustment of Gap? Gap survey and rectification of gaps is to be carried out, in stretches where track develops excessive creep jammed joints, sun kin

Introduction to engineering mechanics, Deternim the angle A for which the m...

Deternim the angle A for which the moment of the 500N force is maximum about a point o. also find the maximum momentum

Manufacturing of cement, describe with neat sketch the process of manufactu...

describe with neat sketch the process of manufacturing of cement in the modern factory by dry process

Simply supported steel frame help, I need some help sizing a rectangular pl...

I need some help sizing a rectangular plate that will distribute my load to the simply supported beams below.

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd