Length is constructed in first phase of construction, Civil Engineering

Assignment Help:

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Explain standard penetration test used in soil exploration, Explain the "St...

Explain the "Standard Penetration Test" used in soil exploration. List the information that can be obtained by the test when made in (a) clay, (b) sand. Comment on the correctio

Define lateral load - actions in pot bearings, Define Lateral Load - Action...

Define Lateral Load - Actions in POT Bearings? Lateral load is transferred from the piston to the POT by contact between the rim of the piston and the wall of the POT. The cont

Build of a cmplete home, how can we build a complete home on an area of 500...

how can we build a complete home on an area of 500 meter squares with garden and house and a garage

How can we reduced frictional losses, How can we reduced frictional losses ...

How can we reduced frictional losses Frictional losses can be reduced by several methods, such as : (a) Over-tensioning the tendons by an amount equal to the maximum frictio

Rcc and rbc, types mixing,curing,water cement ratio,qualities and workabili...

types mixing,curing,water cement ratio,qualities and workability

What is thermo-electric prestressing, What is Thermo-electric prestressing ...

What is Thermo-electric prestressing We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other mea

Plane table surveing, in plane table surveying which activity is done first...

in plane table surveying which activity is done first whether centering or levelling?

Passenger terminal building, Passenger Terminal Building: Importanc...

Passenger Terminal Building: Importance In a civil airport, the passenger terminal building is the centre of all activities. It services both inbound and outward boun

Correction in bearing, write a c program To compute interior angles and cor...

write a c program To compute interior angles and correct them for observational errors and adjusting the bearing of remaining sides when the bearings taken on a closed compass trav

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd