Length is constructed in first phase of construction, Civil Engineering

Assignment Help:

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Write short note on pressure filter, Q. Write short notes on Pressure filte...

Q. Write short notes on Pressure filter for drinking water supply. What are pressure filters and what are its advantages / disadvantages over the normal filter bed. What is p

How do you determine specific gravity of cement, Cement is usually purchase...

Cement is usually purchased as a powdery substance that is mixed with sand, aggregate, gravel, and water to form concrete. As the cement itself is usually a powder, it is hard to c

Explain the coordinate system, Explain the Coordinate System 1. A Bench...

Explain the Coordinate System 1. A Benchmark provides only elevation data. 2. Coordinate System provides northing and easting coordinates within a defined system. 3. Coor

Transportatoin engineening, explain the construction while aligning roads o...

explain the construction while aligning roads on hilly areas

Cycle, what is motor cycle. please explain.

what is motor cycle. please explain.

#frames, confusion on shear force diagram, bending moment diagram

confusion on shear force diagram, bending moment diagram

Designing of corbel beams in a pump station, Question In designing of ...

Question In designing of corbel beams in a pump station , why are shear links designed in top 2/3 of section? What is general advice on designing? Answer Corbel

Explain the kinematic viscosity, Explain the Kinematic Viscosity Ratio ...

Explain the Kinematic Viscosity Ratio of a fluid's Viscosity to the same fluid's Density.  Greek symbol: ν nu    ν = μ/ρ = Absolute Viscosity/Mass Density    Units: ft

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd