Length is constructed in first phase of construction, Civil Engineering

Assignment Help:

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Finite elemenst, can you do finite elements using the weighted residual for...

can you do finite elements using the weighted residual formulation-galerkin method?

Particle size distribution - soil compaction, Particle Size Distribution (G...

Particle Size Distribution (Gradation): The particle size distribution is determined by passing the aggregates through a set of standard IS sieves (Figure) and determining th

Explain the traffic safety - transportation, Explain the Traffic Safety - T...

Explain the Traffic Safety - Transportation Crash rates are normally considered better indicators of risk than crash frequencies.  a. Crash rates for intersections are norma

Graphics, 1. Draw the projections of a line AB that is 50 mm long and is pa...

1. Draw the projections of a line AB that is 50 mm long and is parallel to both the HP and the VP. The line is 40 mm above the HP and 25 mm in front of the VP. 2. A line AB, 50 mm

Heating season duration , Change the model to take into account the variati...

Change the model to take into account the variation in outdoor temperature for a "typical" day in the heating season based on the heat loss by the fabric and the heating of incomin

Geotechnical engg., friction circle method of stability of slope

friction circle method of stability of slope

Marine piles circular in cross section, Question Give reason that why a...

Question Give reason that why are most marine piles circular in cross section? Answer As marine piles, there are a number of options existing for selection, name as H-

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd