Length is constructed in first phase of construction, Civil Engineering

Assignment Help:

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

State the coulomb wedge theory, A retaining wall is battered away from the ...

A retaining wall is battered away from the fill from bottom to top at an angle of 15° with the vertical. Height of the wall is 6 m. The fill slopes upwards at an angle 15° away fro

Calculate the change in volume, Calculate the change in volume: If the...

Calculate the change in volume: If the bar is 1 m long with rectangular cross section of 300 mm deep and 400 mm wide, compute the change in volume of the solid because of a lo

Define coefficient of consolidation, Define and distinguish among coefficie...

Define and distinguish among coefficient of volume compressibility and coefficient of consolidation. Explain clearly one method of computing coefficient of consolidation, given

Assignment , A cantilever beam is loaded with a concentrated. Force of 5kN ...

A cantilever beam is loaded with a concentrated. Force of 5kN at the free end. The length of the cantilever beam is 1m having cross section of 50×50mm. determine the equation for b

Strength of rivet joints, Ask question #Minimum 100 Please help me to...

Ask question #Minimum 100 Please help me to write a c program to determine strength and efficiency of single cover butt joint, lap joint, double cover butt joint . words ac

Estimation of design flood discharge, Q. Estimation of design flood dischar...

Q. Estimation of design flood discharge? These methods are also in vogue for estimating maximum discharge. Discharge estimated using the above three methods may be compared wit

Mechanics of solid, determine the end slope and deflection in the beam

determine the end slope and deflection in the beam

Replacement of Expansion Joint, I want to know the necessary material list ...

I want to know the necessary material list during replacement of Expansion Joint

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd