Length is constructed in first phase of construction, Civil Engineering

Assignment Help:

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Define sulphate attack - underwater inspection of bridge, Define Sulphate A...

Define Sulphate Attack - underwater inspection of bridge? Cement contains a proportion of tricalcium aluminates, which takes part in the hydration process. These can react with

Determine the coefficient of compressibility, A saturated clay layer 4 m th...

A saturated clay layer 4 m thick is located 6 m below GL. The void ratio of the clay is 1.0. When a raft foundation is located at 2 m below GL, the stresses at the top and bottom o

Engineering mechanics, Characteristics of couple #Minimum 150 words accepte...

Characteristics of couple #Minimum 150 words accepted#

Define seismic isolation bearings - bridge bearing, Define Seismic Isolati...

Define Seismic Isolation Bearings  - Bridge Bearing? Many bridges had been built before the proper seismic design specifications were known to us. These bridges require strengt

Calculate the energy loss in the piping system, The head (energy) loss in t...

The head (energy) loss in the piping system between points 1 and 7 is the most nearly. Solution: 3 ft. The difference between point 1 and point 7 = 10 ƒt - 7 ƒt = 3 ƒt

System analysis and management techiniques, Question 2: A software company ...

Question 2: A software company is considering translating its program into French. Each unit of the program sells for $50 and incurs a variable cost of $10 to produce. Currently, t

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd