In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Routing maintenance and major maintenance, What is the difference between r...

What is the difference between routing maintenance and major maintenance in school facilities? Ans) The routine maintenance is the minor and consistent repairs that are engaged

Classification of timber based on mode of growth, Classification Based on M...

Classification Based on Mode of Growth: On the basis of mode of growth trees are classified as (a) Exogeneous and (b) Endogeneous (a) Exogeneous Trees: These trees grow outwa

Determine concentration of total solids and volatile solids, The following ...

The following test results were obtained for a 100 ml wastewater sample taken at the inlet to wastewater treatment plant.  The tests were performed using the standard methods. Dete

Explain about viscous flow loss, Q. Explain about Viscous flow loss? Ab...

Q. Explain about Viscous flow loss? Absorptive material comprises interconnected voids and pores into which sound energy will propagate. When sound waves pass throughthe materi

Explain forty-five degree spread rule for driven piles, Q. Explain Forty-fi...

Q. Explain Forty-five degree spread rule for driven piles ? For driven piles the length of piles driven into the ground is generally based on dynamic driving formula such as Hi

Surveying, Describe the two fundamental purpose of surveying.

Describe the two fundamental purpose of surveying.

Rb slab, #questionshow me picture..

#questionshow me picture..

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd