Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

R.c.c square overhead tank, problems in estimating especially in reinforcem...

problems in estimating especially in reinforcement works

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Determine the load which a square footing, Two load tests were performed at...

Two load tests were performed at a site-one with a 50 cm square plate and the other with a 75 cm square plate. For a settlement of 15 mm, the loads were recorded as 50 kN and 90 kN

Illustrate the term - failure due to rupture of steel, Failure Due to Ruptu...

Failure Due to Rupture of Steel This mode of  failure is likely in lightly reinforced concrete members in which the ultimate strength of  steel is attained before the concrete

Determine the concept of resultant force at a section, Resultant force at a...

Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw

Determine the active thrust on the wall by culmann method, A retaining wall...

A retaining wall with its face inclined at 75° with horizontal is 10 m high and retains soil inclined at a uniform surcharge angle of 10°. If the angle of internal friction of the

Upper bound of indirect tensile strength, Question While designing rese...

Question While designing reservoirs, indirect tensile strength of the concrete mix is particular to be less than a specific value such as 2.8N/mm2 for potable water. Why ought

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd