Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Calculate the number of paths and critical paths, Calculate the Number of P...

Calculate the Number of Paths, Number of Critical Paths and Project Duration For the project network shown, the total number of paths through the network; number of critical pa

Geotechnical engineering, Explain coulomb''s wedge theory-definition and de...

Explain coulomb''s wedge theory-definition and derivation

Interface between base plates and footings, Interface between base plates a...

Interface between base plates and footings Surface of footings is generally quite rough so that some levelling has to be carried out for base plates. Interface between base pl

Determine the head loss due to friction, Determine the head loss due to fri...

Determine the head loss due to friction using the Darcy-Weisbach equation. The water is pumped at 3.0 gallons per minute, has a temperature of 60 °F and is pumped through a 1inch s

How can you design side slope of bank, Q. How can you design Side Slope of ...

Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about

Determine the flow area of storm water, Storm water flows at a depth of 4 f...

Storm water flows at a depth of 4 ft in the natural channel as shown in the figure. The channel has a slope of 0.0l ft/ft and n = 0.025. 1. Determine the flow area:

Define types of deterioration in steel substructure, Define Types of Deteri...

Define Types of Deterioration in Steel Substructure There are 5 major types of deterioration in steel substructure in the marine environment: - Corrosion - Abrasion - Loo

Machanics, write a short on vector representation of force(addition and sub...

write a short on vector representation of force(addition and substraction )

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd