Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

P.h.e, procedure for designing of sewage scheme

procedure for designing of sewage scheme

Determine the allowable bearing pressure of the sand, Two load tests were c...

Two load tests were conducted at a site-one with a 0.5 m square test plate and the other with a 1.0 m square test plate. For a settlement of 25 mm, the loads were found to be 60 kN

Explain the statements about the differential levelling, Explain the Statem...

Explain the Statements about the Differential Levelling I.  Bench mark (BM) - relatively permanent point of known elevation as indicated on the Contract drawings  II. Back s

Cumulative error, diffrence between cumilative compensative error

diffrence between cumilative compensative error

Distomat, applications of distomat in briefly

applications of distomat in briefly

Define dupuit equations for unconfined aquifers, Define Dupuit Equations fo...

Define Dupuit Equations for Unconfined Aquifers Using natural log: Q = ΠK((h 2 ) 2 - (h 1 ) 2 )/ln(r 2 /r 1 )     Using log 10 : Q = K((h 2 ) 2 - (h 1 ) 2 )/((1,055)l

What is the unit weight of water, In a pipette analysis, 0.5 N of dry soil ...

In a pipette analysis, 0.5 N of dry soil (fine fraction) of specific gravity 2.72 were mixed in water to form half a litre of uniform suspension. A pipette of 10 ml capacity was

Heating season duration , Change the model to take into account the variati...

Change the model to take into account the variation in outdoor temperature for a "typical" day in the heating season based on the heat loss by the fabric and the heating of incomin

Lime, LIME It is significant binding material utilized in building con...

LIME It is significant binding material utilized in building construction. Lime has been utilized as the material of construction from ancient time. While it is mixed with san

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd