Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Calculate the cost to finance the construction project, A contractor is bid...

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Steel work design, 1) A building constructed from steelwork requires the fo...

1) A building constructed from steelwork requires the following sections to be designed: a. A beam carrying a characteristic permanent load of 11kN/m and a characteristic variable

What is the specific gravity of the soil, An oven-dried soil weighing 1.89 ...

An oven-dried soil weighing 1.89 N is placed in a pyknometer which is then filled with water. The total weight of the pyknometer with water and soil is 15.81 N. The pyknometer fill

Steel tubular marine piles, Question Give genuine reason that why are ...

Question Give genuine reason that why are steel tubular marine piles often driven open-ended? Answer In marine structure where piles are constantly topic to major la

Modulus of elasticity of light-weight concrete, Modulus of elasticity of li...

Modulus of elasticity of light-weight concrete The modulus of elasticity of light-weight concrete is about 50 to 55% of that of normal-weight concrete. The loss of prestresses

Determine the meaning of prestressed concrete, Determine the meaning of Pre...

Determine the meaning of Prestressed Concrete It is a type of concrete in which permanent internal stresses of  a suitable nature, magnitude and distribution are intentionally

Internal force of preloaded fasteners, Q. Internal force of preloaded faste...

Q. Internal force of preloaded fasteners? Force in a bolt in a bolted joint relies on the preloading force applied to it at the time of the tightening operation. For example, w

Matlab, Pls provide matlab design for transportation engg.

Pls provide matlab design for transportation engg.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd