Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Illustrate shaft grouting for friction barrettes, Q. Illustrate Shaft grout...

Q. Illustrate Shaft grouting for friction barrettes? For the construction of friction barrettes, some grout pipes are designed at periphery of the barrettes. Within a short dur

Surveying, obstacle to ranging but not chaining inthat when line may not vi...

obstacle to ranging but not chaining inthat when line may not visible from intermediate point pls if required explain with diagram

Fluid mechanics , i have three civil engineering fluid mechanics. 1 manomet...

i have three civil engineering fluid mechanics. 1 manometer problem 2 estimate the discharge for a channel 3 pipe system - direction of flow in line and what the value of flow in l

Hiley formula in designing of h-piles, Question Is it resourceful that ...

Question Is it resourceful that engineers rely solely on Hiley's formula in designing of H-piles? Answer About 90 percent of H-piles accept Hiley's formula for desig

Movement accommodation factor for joint sealant, Movement accommodation fac...

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint

Determine the flow area of storm water, Storm water flows at a depth of 4 f...

Storm water flows at a depth of 4 ft in the natural channel as shown in the figure. The channel has a slope of 0.0l ft/ft and n = 0.025. 1. Determine the flow area:

Explain equation for change interval, Explain equation for Change Interval ...

Explain equation for Change Interval y = t + v / 2a + 64.4G Where:  y = length of yellow interval (sec)     t = driver perception/reaction time (1.0 sec generally used)

How to determine the water content and bulk density, The wet weight of a sa...

The wet weight of a sample is missing in a Proctor test. The oven-dry weight of this sample is 189 N. The volume of the mould used is 1000 cm 3 . If the degree of saturation of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd