Explain pressure balance method and compressed air method, Civil Engineering

Assignment Help:

Pressure balance method vs. compressed air method in pipe jacking

Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand.  Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools. 

The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit. 

Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.


Related Discussions:- Explain pressure balance method and compressed air method

Aggregate value, how to calibrate AGGREGATE IMPACT VALUE TESTING MACHINE

how to calibrate AGGREGATE IMPACT VALUE TESTING MACHINE

Wearing course or additional thickness be designed on piers, Question S...

Question Shall layer of wearing course or additional thickness be designed on surface of piers ? Answer In designing of piers , considerations have to be given to

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Properties of matter, Properties of Matter: Due to surface tension,...

Properties of Matter: Due to surface tension, the free surface of a liquid behaves like a stretched elastic membrane tending to contract so as to have minimum surface area.

High temperature in laying bituminous pavement, High temperature in laying ...

High temperature in laying bituminous pavement Generally bituminous materials are also broadly categorized into two types viz bitumen McAdamsand hot-rolled asphalts. At the ti

Define the thiem equations for confined aquifers, Define the Thiem Equation...

Define the Thiem Equations for Confined Aquifers   Using natural log:  Q = 2pKm(h 2 - h 1 )/ln(r 2 /r 1 )   Using log 10 :    Q = 2Km(h 2 - h 1 )/((1055)log(r 2 /r 1 ))

Structural analysis & design, This is an optional team assignment. This gra...

This is an optional team assignment. This grade will replace your lowest two homework grades. You may work in teams of 3-4 students. Design the lightest concrete cantilever beam

Classification of timber based on durability, Classification Based on Durab...

Classification Based on Durability: Durability tests are conducted by the forest research establishment. They cover test specimen of size 600 × 50 × 50 mm in the ground to hal

Vibration in structures – resilient bearings, Q. Vibration in structures - ...

Q. Vibration in structures - resilient bearings? When railway tunnels are built close to buildings, ground-borne vibration is transmitted to buildingsthrough compression and sh

Open channel, design of irrigation channel permissible velocity table

design of irrigation channel permissible velocity table

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd