Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Pressure balance method vs. compressed air method in pipe jacking
Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is usually adopted to provide the balance of earth pressure and groundwater in front of boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of cutting wheel through slurry pipes. Excavated materials drop into a crusher for reduction in material size. Afterwards the debris and spoils would enter the spoil removal chamber near the invert of shield and would be transported to ground level via slurry discharge pipes. This method of construction is generally adopted in gravel andsand. Though, it suffers from the disadvantage that it is quite tough to remove large rock boulders at the time of advancement of the machine. It is quite time-consuming for workers to go inside the comparatively small airlock chamber and remove large bounders by hand tools.
The other kind of pressure balance technique is known as earth pressure balance method that is commonly used in clay and silty soils. It makes use of principle of sustaining the pressure of excavation chamber the same as the pressure in ground. Excavated materials are transported through screw conveyor to jacking pit.
Compressed air method in pipe jacking is generally adopted in locations where groundwater table is high. An air pressure of less than 1 bar is normally sustained to provide the face support and to avoid water ingress. Depressurization and Pressurization has to be conducted for workers leaving and entering the pipe-jacked tunnels. In the case of porous ground, certain ground treatment such as grouting has to be carried out. Removal of boulders by this method is convenient however it hasthe demerits of slow progress and significant noise problem produced by generators and compressors.
in what condition curve s-t curve is concave and convex
how to calculate section properties
what is plastic?its types and composition and its uses as engineering material
evaluate limsin3theta over theta
Culverts, Causeway and Bridges: Roads have to cross several natural streams like - rivers and canals. They also have to cross railway lines and cross-roads. The structures nee
Determine the example of tendon splices Following are some examples of tendon splices. (a) Torpedo splice (b) Clamp splice (c) Screw connectors
To determine a trusses ,beams and frames of two degree by compatibility equations and by castiglanoes theorem
Ask question #Minimum 100 words accepted2812539076# you
Q. Illustrate Weld Failures in Track? These are failures occurring to defects in welding the joint. These defects are either because of improper composition of thermit metal or
Q. Location of construction joints? Construction joints are generally required in construction works since there is limited supply of fresh concrete in concrete batching plants
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd