Determine the normal completion time and cost, Operation Management

Assignment Help:

Atkinson department is installing new computer system. They have to perform several activities. Following table provides information about the project:

Activity

Immediate

Predecessor

Normal Time

(days)

Crash Time

(days)

Normal Cost ($)

Crash Cost($)

A

NONE

6

4

4200

7240

B

NONE

9

6

9800

14240

C

NONE

4

3

12000

12800

D

NONE

16

12

24000

25000

E

A

5

4

7800

9600

F

A

3

1

6700

7200

G

C

6

5

6600

7200

H

E,F

7

6

14500

15200

I

B

3

2

18000

19100

J

G

5

2

34060

38800

K

H

3

1

14000

15800

L

F, I

9

6

21000

25500

M

J

3

2

6000

6750

N

K

1

1

9500

9500

O

D,M

4

3

12500

13650

P

L,N,O

8

8

21000

21000

(a)    Draw network diagram for normal time?

(b)   What is the normal completion time and cost?

(c)    What are the critical activities and what is/are the critical path/s?

(d)   If you want to complete the project ONE day earlier, which activity or activities should be crashed?

(e)    After the crashing in part 'd' has been done, list ALL the paths in this network with the time required  for each path. Among the paths you stated which path/s is/are critical, Why?

(f)    After the crashing in part 'd' has been done, you want to reduce completion time by further ONE day. Which activity or activities should be crashed?

(g)   After the crashing in part 'f' has been done, list ALL the paths in this network with the time required  for each path. Among the paths you stated which path/s is/are critical, Why?

(h)   After the crashing in part 'f' has been done, you want to reduce completion time by further ONE day. Which activity or activities should be crashed?

(i)     After the crashing in part 'h' has been done, list ALL the paths in this network with the time required  for each path. Among the paths you stated which path/s is/are critical, Why?

Note: Beside Network diagram for part 'a', you have to draw network diagram for part d, f and h to support the work.

Part 'a' network diagram represent normal completion time: Part 'd' after crashing one day.

Part 'f' after crashing another day. : Part 'h' after crashing another day.

I am not asking maximum crashing.

Your network diagram should not have vertically upward, vertically downward and backward arrows.


Related Discussions:- Determine the normal completion time and cost

Explain processes losses be avoided, What are some processes losses that ar...

What are some processes losses that are likely to occur in teams such as those at ICU Medical Inc? How can these processes losses be avoided?

Two handed process chart and multiple activity charts, Two Handed Process C...

Two Handed Process Chart and Multiple Activity Charts Two-handed process chart  For fixed-position manual processes such as the assembly of small devices, this type of ch

Explain product focused, 1. What are the key characteristics that would cla...

1. What are the key characteristics that would classify Wheeled Coach as a repetitive focus process strategy? 2. Let's assume you are a new hire at Wheeled Coach. Your manager a

Calculate mape for each data set, DO different forecasting techniques (F1 a...

DO different forecasting techniques (F1 and F2) were used to forecast demand for cases of bottled water. Actual demand and the two sets of forecasts are as follows: PREDICTED DEMAN

Explain re-negotiate a new relationship, You are very annoyed by one of you...

You are very annoyed by one of your third-party service providers (3PL) and want to confront him and re-negotiate a new relationship. How would you go about this important task?

What is the annual carrying rate, ABC Aircraft uses 3,000 drill bits annual...

ABC Aircraft uses 3,000 drill bits annually. Each drill bit costs $50 and each order ABC places costs $25. The annual carrying rate is 40% of unit cost. ABC has contracted with the

Case studies, Bloomsday Outfitters produces T-shirts for road races. They n...

Bloomsday Outfitters produces T-shirts for road races. They need to acquire some new stamping machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per

Explain what is risk, What is risk? How does risk differ from uncertainty? ...

What is risk? How does risk differ from uncertainty? How does it impact a business?

Principle of scheduling, Principle of Scheduling First Principle optim...

Principle of Scheduling First Principle optimum Task Size : scheduling tens to achieve its maximum efficient task sizes are small and all tasks are of the same order of magnit

Describe linear programming problem, Swearingen and McDonald, a small furni...

Swearingen and McDonald, a small furniture manufacturer, produces fine hardwood tables and chairs. Each product must go through three stages in the manufacturing process - assembly

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd