Determine minimum radius that can used on horizontal curve, Civil Engineering

Assignment Help:

What is the minimum radius, Rmin, that can be used on a horizontal curve with a 70 mph design speed, a maximum superelevation, emax = 8%, and a side friction factor, f = 0.10?

Answer:

0.01e + f = V2/15R

Rmin = V2mph / 15 (0.01e + f) = 702 / 15 (0.01*8+0.10) = 1814.80 ft


Related Discussions:- Determine minimum radius that can used on horizontal curve

Dimples in polytetrafluoroethylene, Dimples in Polytetrafluoroethylene (PTF...

Dimples in Polytetrafluoroethylene (PTFE) PTFE is a fluorocarbon polymer that possesses good chemical resistance and can function in a wide range of temperature. The most signi

Assignment help job, Can I apply for "online assignment help job" for civil...

Can I apply for "online assignment help job" for civil engineering,physics & maths etc?

How to design marginal embankments, Q. How to design Marginal Embankments? ...

Q. How to design Marginal Embankments? Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below

Methods of design of prestressed concrete member, Methods of design of pres...

Methods of design of prestressed concrete member What are different approaches or methods of design of prestressed concrete members? What are important considerations  in th

How to calculate the dry density and void ratio, A moist soil sample compac...

A moist soil sample compacted into a mould of 1000 cm 3 capacity and weight 35 N, weighs 53.5 N with the mould. A representative sample of soil taken from it has an initial weight

Precast pile, when a precast pile is single point lifting and when double p...

when a precast pile is single point lifting and when double point lifting- what are the moment coefficient of them?

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

W/c ratio, first of all i want to think you for this helpful website , and ...

first of all i want to think you for this helpful website , and let me ask you this question . how to calculate w/c ratio ? thank you so much for you .

What is the sludge volume index, What is the Sludge Volume Index? Two 1...

What is the Sludge Volume Index? Two 1 L samples of mixed liquor are taken from a lagoon. After settling for 30 min in a graduated cylinder, 250 mL of solids have settled out i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd