In General Specification for Civil Engineering Works, designing of roadbase material is based on recipe approach. Give reason.


Answer

Designing of roadbase material is based on recipe move towards, as Hong Kong government follows the traditional British practice by adopting recipe plan in which aggregate grading envelope, quantity and grade of bitumen are specified in bituminous mix. This recipe of bituminous mix is derived based on precedent experience and first-rate workmanship during construction. In information, several countries now adopt special design mix of roadbase that proves to produce satisfactory bituminous mixes to suit different site and design situation.

In real, recipe specification of bituminous materials does suffer from quite a lot of drawbacks. Firstly, conditions of traffic and climate of newly constructed bituminous road possibly will differ from conditions on which recipe design is based. In case regulation has to be made to recipe design, it is extremely difficult to determine and assess modifications required. Secondly, it creates intricacy to site engineers to assess effects of minor non-compliance if recipe specification is adopted. At last, recipe mix might not be most economical design that is dependent on site conditions.

 


Related Discussions:- Designing of roadbase material

Concrete, types of concrete and its uses

types of concrete and its uses

Aslar masonry, different types of ashlar masonry

different types of ashlar masonry

Explain the equation for length of spiral curve, Explain the Equation for L...

Explain the Equation for Length of Spiral Curve Length of Spiral Curve can be calculated using the following equation L s = 3.15V 3 /RC Where: V - Design Speed in MPH

Diffraction analysis in determining wave force on piles, The Morison equati...

The Morison equation vs. diffraction analysis in determining wave force on piles The choice between Morison's equation and diffraction analysis in determining the wave forces o

Diffrence between concrete road and bituminous road, Q. Diffrence between C...

Q. Diffrence between Concrete road and bituminous road? Concrete road belongs to rigid pavement and they don't deflect under traffic loads. Quite the reverse, bituminous pavem

Stone tiles for construction material, Q. Stone tiles for construction mate...

Q. Stone tiles for construction material? For Public toilet bath rooms kitchen etc. we may be use stones tiles ( marble , kota stone , Polished Kuddapa stone or polished Dhura

Masonry, Sketches for English bond, Stretcher bond, Header bond, Flemish bo...

Sketches for English bond, Stretcher bond, Header bond, Flemish bond in first & second layer plan, elevation and 3 dimensional view of brick bond.

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd