Calculate the amount put into saving account, Civil Engineering

Assignment Help:

Calculate the Amount put into Saving Account

If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is most nearly:

Solution: This problem could also be stated:  What is the equivalent present worth of $60,000 ten years from now if monthly money is worth 6% per year?

P = F (P/F, I, n) = $60,000(P/F, 6%, 10) = $60,000 * 0.5584 = $33,503.69

1018_Calculate the Amount put into Saving Account.png


Related Discussions:- Calculate the amount put into saving account

Show the application of concrete crash barriers, Q. Show the application of...

Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl

Main principle of post-grouting for mini-piles, Question What is main p...

Question What is main principle of post-grouting for mini-piles? Answer During course of post-grouting , a tube with a hole at its base is lowered into pile and g

Acetylene gas cylinder for gas welding, Q. Acetylene gas cylinder for gas w...

Q. Acetylene gas cylinder for gas welding to be erected in upright position Acetylene gas is normally used for gas welding due to its simplicity in production and transportati

Strength of materials, Enlongations in solids based on elastic constants

Enlongations in solids based on elastic constants

Discuss about the fibre reinforced concrete, Discuss about the fibre reinfo...

Discuss about the fibre reinforced concrete Tensile strength of concrete may be improved by using a higher grade of concrete or by using special concretes such as fibre reinfor

Soil mechanics, what is the total volume required for the gravel material o...

what is the total volume required for the gravel material of 6.5mx2314mx0.1m with a relative density of 2.919 and a loose bulk density of 1668kg/m3

Holes in steel plates connecting to H-piles, Q. Holes in steel plates conne...

Q. Holes in steel plates connecting to H-piles There are two types of holes present in the steel plate associated to H-piles in the pile cap. The first type of holes is design

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd