Calculate the Amount put into Saving Account

If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is most nearly:

Solution: This problem could also be stated:  What is the equivalent present worth of $60,000 ten years from now if monthly money is worth 6% per year?

P = F (P/F, I, n) = $60,000(P/F, 6%, 10) = $60,000 * 0.5584 = $33,503.69

1018_Calculate the Amount put into Saving Account.png


Related Discussions:- Calculate the amount put into saving account

Building, What quantity of cement will be needed to lay 2000 blocks of 9 in...

What quantity of cement will be needed to lay 2000 blocks of 9 inches using a mortar ratio of 1:6 with a thickness of 25mm in-between blocks.

Serveying, Set out horizontal and vertical cintrol and small building for c...

Set out horizontal and vertical cintrol and small building for construction work?

What is the safe bearing capacity of a rectangular footing, What is the saf...

What is the safe bearing capacity of a rectangular footing, 1 m × 2 m, placed at a depth of 2 m in an saturated clay having unit weight of 20 kN/m 3 and unconfined compression str

BONDS, ADVANTAGE OF FLEMISH BOND

ADVANTAGE OF FLEMISH BOND

Is cbr test is an arbitrary test, CBR Test is an arbitrary test', justify. ...

CBR Test is an arbitrary test', justify. Explain the procedure for conducting the CBR test in the field. Surcharge loads are used in the CBR test; Describe their significa

What are the long spam bridge girders, What are the long spam bridge girder...

What are the long spam bridge girders The pre-tensioned construction finds more use and application in the construction of those structural concrete members which are of small

Rebound hammer.., rebound hammer working mechanism with detailed specificat...

rebound hammer working mechanism with detailed specifications of the images

Define cleaning for underwater inspection of bridge, Define Cleaning for Un...

Define Cleaning for Underwater Inspection of Bridge? Before any structure can be inspected, it is necessary to expose the surface material of the structure. Wherever there is m

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd