Calculate the amount put into saving account, Civil Engineering

Assignment Help:

Calculate the Amount put into Saving Account

If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is most nearly:

Solution: This problem could also be stated:  What is the equivalent present worth of $60,000 ten years from now if monthly money is worth 6% per year?

P = F (P/F, I, n) = $60,000(P/F, 6%, 10) = $60,000 * 0.5584 = $33,503.69

1018_Calculate the Amount put into Saving Account.png


Related Discussions:- Calculate the amount put into saving account

Choosing between trailer suction hopper and grab dredgers, Question In ...

Question In search reclamation, what are considerations in choosing between trailer suction hopper dredgers and grab dredgers ? Answer Trailer suction hopper dred

Surveying, Describe the two fundamental purposes of surveying

Describe the two fundamental purposes of surveying

Define the most probable error, If the standard deviation of an observation...

If the standard deviation of an observation is ± 10-ft, the most probable error would be: The most probable error is defined as the error for which there are equal chances of t

Explain rebound hammer - underwater non-destructive testing, Explain Reboun...

Explain Rebound Hammer - Underwater non-destructive testing? The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condit

Reinforcement detailing, i want to know about the detailing at beam -column...

i want to know about the detailing at beam -column joint & beam- wall joint

What is the cost of phoenix activity, Q. What is the cost of phoenix activi...

Q. What is the cost of phoenix activity? Phoenix activity has a range of impacts on the Australian economy. Employees lose entitlements when phoenix activity has occurred and w

Calculate uniform annual cost for maintenance and repair, A contractor purc...

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest

IRC class 70R, What will be the structural weight per meter for IRC class 7...

What will be the structural weight per meter for IRC class 70r bridge

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd