Calculate the amount put into saving account, Civil Engineering

Assignment Help:

Calculate the Amount put into Saving Account

If you want to have $60,000 in 10 years, the amount that should be put into a 6.0% (effective annual rate) savings account now is most nearly:

Solution: This problem could also be stated:  What is the equivalent present worth of $60,000 ten years from now if monthly money is worth 6% per year?

P = F (P/F, I, n) = $60,000(P/F, 6%, 10) = $60,000 * 0.5584 = $33,503.69

1018_Calculate the Amount put into Saving Account.png


Related Discussions:- Calculate the amount put into saving account

Mechanics, laws of solid friction?

laws of solid friction?

TRIGONOMETRIC RATIOS, GIVE EXAMPLESS OF TRIGONOMETRIC RATIOS AND HOW TO SOL...

GIVE EXAMPLESS OF TRIGONOMETRIC RATIOS AND HOW TO SOLVE THEM

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Explain the permissible settlement, Q. Explain the Permissible Settlement? ...

Q. Explain the Permissible Settlement? Any foundation may fail in shear or by excessive settlement. The failure due to shear is checked by adopting safe value of bearing capa

Softening test point, the importance of softening point of a bitumen materi...

the importance of softening point of a bitumen material in the design of a pavement

Write short notes on impact test, Q. Write short notes on Impact Test? ...

Q. Write short notes on Impact Test? Impact test for ballast shall be carried out using Impact testing machine. The test sample shall be prepared out of ballast so as to con

Measure the cohesion of internal friction of the soil, A cylindrical specim...

A cylindrical specimen of a saturated soil fails under an axial stress 150 kN/m 2 in an unconfined compression test. The failure plane makes an angle of 52° with the horizontal.

Major bridge and important bridge, Major bridge - Major bridge is one of wh...

Major bridge - Major bridge is one of which has a total linear waterway of 18 m or more for multiple span and total linear water way of 12 m or more for single span. Important b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd