Question
For underwater concreting, tremie pipes are normally used with aid of hoppers. From time to time tubes are put in inside the hoppers and with reasons?
Answer
At place of concrete by tremie pipes, hoppers are connected to their peak for receiving newly placed concrete. Though, air might be trapped inside tremie pipes if there is rapid feeding of fresh concrete. To release trapped air inside tremie pipes, hoses are also called ventilation tubes are inserted and lowered down through hoppers.
Q. Test for determination of Ultimate Compressive Strength The test pieces are to be loaded either till the failure of the steel laiminate or till the irreversible squeezing ou
Pre-tensioning systems In the previous unit we have seen different steps in a pretensioning operation. Tendon wires or strands (formed as a rope type arrangement made of sever
Maximum thermal stress in circular tapering section is
Depth of Boring for Multi-storeyed Building Peck has recommended that first drill hole is to be made up to depth at which the presence of a thick layer of soft clay with a hig
Classification Based on Grading: IS 883-1970 classifies the structural timber into 3 grades-select grade, grade I and grade II. The classification is depend on, defects, permi
Ground settlement occurs ahead or behind the jacking face for pipe-jacking? It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 ti
The thickness of a saturated specimen of clay under a consolidation pressure of 100 kN/m 2 of is 24 mm and its water content is 20%. On enhance of the consolidation pressure to 20
Q. Best efficiency point and operating point for pumps? In a pumping system, a system curve can be derived based on static head needed to lift up the fluid and variable head be
A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widen
Q. Explain the Design discharge for bridge waterway? Design discharge for bridge waterway should be a flood of 50 year frequency. For very large bridges damage to which is like
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd