Define the equations for a contracted rectangular weir, Civil Engineering

Assignment Help:

Define the Equations for a Contracted Rectangular Weir

If the rectangular weir is a contracted weir and the flow is restricted from passing freely through the weir opening, a reduction in Q is accounted for by reducing the weir length b:

 beffective = bactual - 0.1(N)(H) 

Q = 2/3 (C1) (bactual - 0.1(N)(H)) √2g (H)1.5 = Q = 3.33(L - 0.2H) H1.5

 


Related Discussions:- Define the equations for a contracted rectangular weir

Use single lock nuts or double lock nuts, Question In linking fenders t...

Question In linking fenders to pier organizations, would single lock nuts or double lock nuts be used? Answer In pier structures connection offenders to piers is a

Determine the water content of the sand sample, In order to determine the w...

In order to determine the water content of a wet sand, a sample weighing 4 N was put in a pyknometer. Water  was then poured to fill it and the weight of the pyknometer and its con

Calculate the invert elevation of the sewer pipe, 1. The center line elevat...

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly: 2. A design engineer c

Determine the head loss due to friction, Determine the head loss due to fri...

Determine the head loss due to friction using the Darcy-Weisbach equation. The water is pumped at 3.0 gallons per minute, has a temperature of 60 °F and is pumped through a 1inch s

Construction measurment, calculating quantity of excavation, formwork, conc...

calculating quantity of excavation, formwork, concrete

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

Calculate the effective annual interest rate, A credit card advertises a no...

A credit card advertises a nominal rate of 18% compounded monthly. If no monthly payments are made, the effective annual interest rate is most nearly: The actual rate is, (18%

Wet mix macadam - road pavements, Wet Mix Macadam: For heavily traffi...

Wet Mix Macadam: For heavily trafficked highways, the granular bases are constructed using Wet Mix Macadam (WMM). The WMM is a specification in which well graded aggregate is

Surveying, Use of optical square in chain surveying?

Use of optical square in chain surveying?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd