Calculate the invert elevation of the sewer pipe, Civil Engineering

Assignment Help:

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly:

2. A design engineer commissioned a test pit to determine the top of pipe elevation for a sewer extension project.  The existing sewer pipe is an 8-ft o.d. reinforced concrete pipe with wall thickness 10-in.  A back sight to a local benchmark with an established elevation of 45.66-ft is obtained with a level and a rod reading of 4.91-ft.

 A foresight is taken to a rod resting on the top of pipe with a reading of 12.43-ft.   

Calculate The invert elevation (ft) of the sewer pipe.


Related Discussions:- Calculate the invert elevation of the sewer pipe

Determine the viscosity of water, A soil sample consists of particles rangi...

A soil sample consists of particles ranging in size from 0.6 mm to 0.02 mm. The average exact gravity of the particles is 2.66. Verify the time of settlement of the coarsest and fi

Dielectric materials are what kind of materials, Dielectric materials are w...

Dielectric materials are what kind of materials ? Answer: It is  insulating materials.

What is bore hole, What is Bore Hole In exploration of  area of  limit...

What is Bore Hole In exploration of  area of  limited extent  the borings should preferably be located near the comers of  the area. A minimum of three holes should be made un

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

Varigon theorem, Ask questio #Minimum 100 words accepted# what is varigon ...

Ask questio #Minimum 100 words accepted# what is varigon theorem and what are their application ? its examples

Assessing maintenance needs, Assessing Maintenance Needs: Maintenance...

Assessing Maintenance Needs: Maintenance needs can be assessed by a careful inspection of roads at regular intervals, observing defects such as : potholes cracks

#tile.., Material for formwork and their specifications

Material for formwork and their specifications

Large catchments in estimating peak runoff, Question Is it true that ra...

Question Is it true that rational process has to not be used for large catchments in estimating peak runoff ? Answer Rational process is appropriate for small catchme

Steel structures, how does battening differ from lacing?

how does battening differ from lacing?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd