Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Self compacting concrete, what will be the w/c ration and cement/fly ash ra...

what will be the w/c ration and cement/fly ash ration for the particular mix design

Obstacles, Obstacles which can be ranged

Obstacles which can be ranged

Usage of double air valves and single air valves, Question In designig ...

Question In designig of watermains, how to decide usage of double air valves and single air valves ? Answer Single air control device let squeezing air out of p

Void ratio, why void ratio is greater for fine gained soil then course grai...

why void ratio is greater for fine gained soil then course grained soil.

Lagrange''s mean value theorem, Write some appplications of lagrange''s mea...

Write some appplications of lagrange''s mean value thorem

Concrete, types of concrete and its uses

types of concrete and its uses

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd