A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Disadvantages of cement sand mortor
Materials that provide a path to the magnetic flux are? Answer: These are magnetic materials
Transit Sheds and Warehouses: These are sheds constructed as steel frames or RCC frames with a steel truss, with galvanised iron or asbestos cement sheets. Transit sheds may b
State the term - Relaxation of Stress in Steel If we keep a high-tensile steel wire stretched and maintained at a constant strain, the value of the force in the wire does not
Ask question #Minimum 2000 words accepted#
Question What are the major functions of following features observed in a typical manhole ? Answer (i) Groove near benching, (ii) R.S.J. (iii) double seal manhole cove
Explain briefly physical classifications of stone
what will happen if the water curing is in of and on
Defnition of obstruction
compare 2 numbers and print either the message identifying the greater than number(or) the message starting that both number are equal
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd