A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Feactures and uses of distomat
how to design asewa system ??
how many scale are there and what are they use
Resultant Force on a Given Area of a Vertical Plane The resultant force is calculated from the average pressure: R = (AVERAGE Ρ)(A)
Define the Fatigue failure - underwater inspection of bridge? Fatigue failure results in the fracture of structural members as a consequence of repeated high loading. Fatigue
Define Safety Precautions for Underwater Inspection of Bridge? The working agency should have its own diving safety manual, which should be strictly followed. This manual shoul
Two crops are grown on land of 20ha.The cost of raising crop 1 is 3unit/ha, while for crop 2 it is 1 unit/ha.The benefit from crop 1 is 5unit/ha and from crop 2, it is 2 unit/ha. A
explain re inforced brick work?
describe the two fundermental purposes of surveying
Explain the Contracted Rectangular Weir Weir plate has sides which extend above the maximum water surface, directing the flow through an opening (b = weir length). Typically th
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd