A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
expressions for calculating corrections for earth curvature
Q. Explain Use of Scour Valve? Scour Valve - Scour Valve at depressions on the main for clearing and emptying the pipes. It is also called blow off valve or Drain valve. This t
Cross-sectional Elements: The terms used in the cross-section of a road are : Carriageway The portion where traffic moves. Shoulder The portion outside the ca
What is Thermo-electric prestressing We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other mea
Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng
What is the rate of application of Prime coat over WBM
what is the manufacturing process of regular portland cement
whatiscreepofmetal&typesdescribe
processes of chemical prestressing
what is focal point ratio
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd