Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Construction water, what should we do if alkalinity in water is greater tha...

what should we do if alkalinity in water is greater than 25

#title beam design, how to calculate loads acting on a simple supported bea...

how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#

Levelling, how to establish temporary benchmark

how to establish temporary benchmark

Physical deterioration - underwater inspection of bridges, Define Physical ...

Define Physical deterioration - underwater inspection of bridges Typical defects include: -   Scaling -   Cracking -   Spalling -   Disintegration -   Abrasion

Dam, tupes of dam

tupes of dam

Comparison of pre and post-tensioning, Comparison of pre and post-tensionin...

Comparison of pre and post-tensioning A comparison between pre-tensioned and post-tensioned concrete members can be made on the basis of the following considerations. (a) T

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd