A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
have a beam with one lateral restraint at bottom and top flange and load on top flange, should I use 2 segments or one segment of the beam ignoring bottom restraint as it is not in
LOSS OF PRESTRESS DUE TO SHRINKAGE OF CONCRETE We know that concrete shrinks in volume when it dries up. This volume reduction takes place in the form of reduction of all dime
what is expected of them
what is barometric leveling
Question Is it resourceful that engineers rely solely on Hiley's formula in designing of H-piles? Answer About 90 percent of H-piles accept Hiley's formula for desig
definition for double type scaffolding
Define Fathometer with the odolite - Sounding/Sensing Devices? The horizontal scale problem in use of Fathometer can be solved by using equipment, which combines a Fathometer w
A sample in a variable head permeameter is 8 cm in diameter and 10 cm high. The permeability of the sample is estimated to be 10 × 10 -4 cm/s. If it is desired that the head in th
write a program to design two way slab
Defnition of obstruction
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd