A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
define Structural Analysis
Q. Explain the Maximum spacing of piles? One of the factors which affect the distribution of loads from the structures to each pile is assumption of flexibility of the pile ca
Q. Afflux in rivers with non scourable bed? Afflux is defined as rise of flood level of the river upstream of a bridge as a result of the obstruction to natural flow caused by
what is wet bituminous macadam
Harbour Layout: A harbour has the following constituent parts: (a) An entrance channel, 100-300 m wide (b) A turning basin, dia 400-600 m (c) A b
Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440. The average crew-hour cost is $15,879 for this
how we can do good premix
infomation about differnt brigdes
WHAT DO WE MEAN BY AC-20 ROAD
Product Layout: Imagine a factory manufactures taps, drills, reamers and cutters. The production of each of these items needs different machines which may be placed in differe
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd