A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Analyse the continuous beam using moment distribution. A continuous beam ABCDE fixed at A carry a load of 2KN one metre from A at AB 3m. BC 3m, carry a UDL of 3KN/m and hinge at
explain
relationship between included angles and whole circle bearing
A rectangular channel is 3 m in width and draws water from a lake. The channel slope is 0.001 and the Manning’s n is 0.0013. What will be the discharge in the channel when the lake
What is Under vibration of fresh concrete?
What is WBM road. How it is constructed?
how to estimate stone in road soling
derivation for above topic
Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be
Q. What is Diamond Crossing? Diamond Crossing is provided when two tracks cross each other either of the same gauge or of different gauges. It consists of two acute crossing (
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd