A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
how can you draw contours of a non square grid?
Explain the Swell Factor of Soil A soil's swell factor represents the fact that the volume of soil placed by nature in the ground is not the same as the volume of the same mass
what is meant by white topping cement
sieve analsis full asignment
Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate
solution of the book
h = u + pv is a combination of properties and hence must also be a property. h is the SPECIFIC ENTHALPY in kJ/kg H = U + pV is the ENTHALPY in kJ
Write down psedo force with example
A saturated clay layer 4 m thick is located 6 m below GL. The void ratio of the clay is 1.0. When a raft foundation is located at 2 m below GL, the stresses at the top and bottom o
partition walls
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd