Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Stabilised pavement layers, Stabilised Pavement Layers: Soil stabilis...

Stabilised Pavement Layers: Soil stabilisation is the process of treating a soil in such a manner as to alter and improve its properties for use as a pavement layer on sub-gr

Show the earth pressure on abutment, Q. Show the Earth pressure on abutment...

Q. Show the Earth pressure on abutment? The magnitude of earth pressure coefficient in calculating the earth pressure on bridge abutment reliesconsiderably on the degree of res

What is portal cranes, Q. What is Portal Cranes? The Portal crane is a ...

Q. What is Portal Cranes? The Portal crane is a hydraulically driven four wheeled machine and is meant for carrying sleepers or track panels. The power for running and working

Explain the normal depth equation, Explain the Normal Depth Equation T...

Explain the Normal Depth Equation The equation is derived from the Chezy-Manning equation. As written below it determines the diameter of a circular storm or sanitary sewer wh

Fracking, cons and pros of fracking

cons and pros of fracking

Reinforced Concrete Design, Design a continuous one-way solid slab supporte...

Design a continuous one-way solid slab supported on beams spaced at 4.2m o.c. the width of the beam is 300mm, leaving clear slab spans of 3.9. The slab carries a uniform DL= 6 KPa.

Dam, tupes of dam

tupes of dam

Determine the soil shrinkage, Soil at a borrow area has a total unit weight...

Soil at a borrow area has a total unit weight of 120-PCF and a water content of 15 percent.  The soil from the borrow area will be used as structural fill and compacted to an avera

Test leakage of constructed gravity pipelines, Question Have air test o...

Question Have air test or water tests be selected to test leakage of constructed gravity pipelines ? Answer For gravity pipes, air tests are carried out after completi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd