A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
A pole which leans 11o from the vertical toward the sun casts a shadow 12m long when the angle of elevation of the sun is 40o. Find the length of the pole
slope deflection with settlement
WHAT IS THE DIFFERENCE BETWEEN FERROUS AND NON FERROUS METALS
what is bending moment
Define Safety Precautions for Underwater Inspection of Bridge? The working agency should have its own diving safety manual, which should be strictly followed. This manual shoul
Define Role of Diver in Underwater Inspection of Bridge? Diver's role is primarily to point out a potential scour problem. The diver can use one of the following equipment to m
collect the field deta manualy and drw the drawing as per scale
Explain Equations for a triangular (V-notch weir) Used for small flow rates. C 2 is a coefficient which varies from 0.58 to 0.61 depending upon the notch angle. Q = C
what is meant by white topping cement
please explain about system engineering in civil
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd