A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
channel section-design of simple section
the conventional symbol used in building plan
construct parabolic shapes using the envelop method and the offset method with dimensions 80 by 120
floors
What are the types of foundation. With figure
A retaining wall 9 m high retains cohesion less soil, with an angle of internal friction 33°. The surface is level with the top of the wall. The unit weight of the top 3 m of the f
types of truss of 15 m cantilever with 1000 kg on free end. May be steel or any lightest material aluminium anodized truss. thanks
help ive got my curry stuck in my hair
Example: Convert the following reduced bearings into whole circle bearings: (i) N 65° E (ii) S 43° 15′ E (iii) S 52° 30′ W (iv)
Q. Air chamber vs. surge tank in pressurized pipelines? Air chambers and surge tanks are generally installed in water main to ease the stress on the system when valves or pumps
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd