A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Explain the Inventory inspections - Inspection of Bridge? These inspections are normally performed following new construction, modifications, or repair to establish as-built or
Discuss about the post-tensioning systems In most of post-tensioning systems, when the cable is tensioned and the jack is released to transfer prestress to concrete, the fricti
I want to know the necessary material list during replacement of Expansion Joint
maintenance of wbm roadstion
A steam turbine with base 6 m × 3.6 m weighs 10,000 kN. It is to be placed on a clay soil with c = 135 kN/m 2 . Find the size of the foundation needed if the factor of safety is to
resection
various continuous triangular load
Determine the Basic Concepts of Prestressing In the year 1904, Freyssinet tried to introduce prestresses in concrete to resist stresses developed due to external loads. Later,
what is the application of silica,aluminaand magnesium in bricks?
pariods of one hundred years
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd