A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
An undisturbed sample of sand has a dry weight of 18.9 N and a volume of 1143 cm 3 . The solids have a specific gravity of 2.72. Laboratory tests indicate void ratios of 0.40 and 0
what is civil
Grouted or Penetration Macadam:
Zones of smear around vertical drains Smear zones are produced during the installation of vertical drains in that zone of soils surrounding the band drains are disturbed. Soil
how do i Setting up The total station theodolite?
how to calculate number of passes while compaction
Find out the joint distribution: Let X I and X 2 be two independent random variables each distributed uniformly in the interval [ 0, a ], where a > 0 is a constant. Find out
Q. Necessity of pile tip cover for rock-socketed H-piles? In current practice concrete cover is generally provided at the pile tips of pre-bored H-piles socketed in rock. The o
semi dense bitumnous concrete overlays for roads
WHAT IS THE DIFFERENCE BETWEEN FERROUS AND NON FERROUS METALS
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd