Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Define the shock transmission unit, Define the Shock Transmission Unit? ...

Define the Shock Transmission Unit? Ever since engineers have started designing multi span simply supported bridges, they have been dreaming of connecting all the spans togethe

FLAMISH BOND, TH ADVANTAGES OF FLAMISH BOND

TH ADVANTAGES OF FLAMISH BOND

Determine the term - final tension, Determine the term - Final Tension ...

Determine the term - Final Tension The tension in tendons after losses of prestress have taken place is called as final tension. Final tension is taken to be corresponding  to

What do you understand by pressure line, What do you understand by Pressure...

What do you understand by Pressure line If we determine the locations of resultant force at various sections of a pre-stressed beam, as in Example, we can draw a curve showing

Determine the term - degree of prestressing, Determine the term - Degree of...

Determine the term - Degree of Prestressing Degree of Prestressing It is a measure of the magnitude of the prestressing force related to the resultant stress occurring in

Assigning central pier and abutment as fixed piers, What are beneficial poi...

What are beneficial points of assigning central pier and abutment as fixed piers ?

Main function of followers in driven h-piles, Question What is main fun...

Question What is main function of followers in driven H-piles ? Answer A follower is an extension between pile head and hammers which transfers blow to pile in which

Explain the difference in elevation between bm and tp2, Based on the inform...

Based on the information provided in Figure, the difference in elevation between BM and TP 2 is most nearly: Solution: Set up a Table as shown below and insert the kno

Structural analysis 1, derive equation of radial pressure and loop stresses...

derive equation of radial pressure and loop stresses of thick cylinder

Break even point, Break even point: EM Electricals, Inc., contains fix...

Break even point: EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd