Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Location of construction joints, Q. Location of construction joints? Co...

Q. Location of construction joints? Construction joints are generally required in construction works since there is limited supply of fresh concrete in concrete batching plants

Surface-protecting fenders and energy-absorbing fenders, Question What ...

Question What is main difference in application of surface-protecting fenders and energy-absorbing fenders ? Answer Surface-protecting fenders are fenders that make

In marine pile type of steel tubular piles, Question In marine pile typ...

Question In marine pile type of steel tubular piles with reinforced concrete infill, least toe level is frequently specified in contract drawings. What is the purpose in your v

Dam, how can i prepare a project on dam

how can i prepare a project on dam

Plumbing, what is the different kinds of pipes and fittings

what is the different kinds of pipes and fittings

Question.A , #q strain gauge arrangement is used to measuuestion..

#q strain gauge arrangement is used to measuuestion..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd