A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
assignment on role of civil engineer
why only frustum cone use in slump
how many bag of cement make a cubic
The inner diameters of a sampling tube and that of a cutting edge are 70 mm and 68 mm correspondingly, their outer diameters are 72 and 74 mm respectively. Verify the inside cle
Describe municipal water treatment?
closed traverse maths problems
Define the Working of Ground Penetrating Radar? Ground penetrating radars (GPR) and low frequency sound are also used in scour survey. These are good in shallow water but not v
Traffic Surveys: The following traffic surveys are needed for preparing a good road project: Classified Volume Counts This survey is normally carried out for 7 days,
what is the reciprocal ranging ? with neat sketch ?
Explain the Design Criteria Sedimentation basin Surface Loading rate (or overflow rate), Vo = Q/A (flow rate/surface area) Detention time t or ? = V/Q (Volume /Flow rate)
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd