A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Question What are main boundaries of Rational Method in calculating runoff? Answer Calculation of runoff is compound matter that depends on a lot of factors similar to ground
Question In linking fenders to pier organizations, would single lock nuts or double lock nuts be used? Answer In pier structures connection offenders to piers is a
classification of lintel
how we can do good premix
what is barometric leveling
three point problem
Binders : Cement: Cement as a Binder Cement is one of the main ingredients of concrete. When cement sets (with the addition of water), it forms a paste and binds the
Types of Pavements: On the basis of structural performance of pavements, there are basically two types of pavements: (a) Flexible, and (b) Rigid. A flexible pavement
reinforcement.
how would you perform a rantangular tie ,using an optical square
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd