Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

General about tests, 1. All testing shall be done at room temperature. 2...

1. All testing shall be done at room temperature. 2. No bearing shall be tested earlier than a week after vulcanization. 3. Bearing sections shall be cut from test bearings w

Define fatigue load test of shock transmission unit, Define Fatigue load te...

Define Fatigue load test of shock transmission unit? This test was carried out for 100,000 cycles for maximum capacity of STU, assuming the worst case that the 'Lock Up Load' i

Design, what is the procedure to design the beam and column?

what is the procedure to design the beam and column?

Beams of uniform strength, determine the cross section of a rectangular bea...

determine the cross section of a rectangular beam of uniformly strength for a simply supported beam of 6m span subjected to central concentrated load of 20kN a)by keeping depth of

Bond performance of bar reinforcement, Question Does occurrence of rust hav...

Question Does occurrence of rust have adverse collision to bond performance of bar reinforcement ? Answer In fact, presence of rust in bars cannot have adverse impact to the bo

Ships stress, brief detail about ships stresses

brief detail about ships stresses

Supply each tremie pipe with a single concrete truck, Question Througho...

Question Throughout concreting of diaphragm walls , three tremie pipes are used in single time. But, only one concrete truck is obtainable. How have to concreting works been a

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Engineering mathamatics, #question.A strain gauge arrangement is used to me...

#question.A strain gauge arrangement is used to measure the applied force of a comnplex shaped civil engineering structure. Theoretical analysis have been round the relationship be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd