A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Q. Pulverized fly ash as cement replacement? Pulverized fly ash is a type of pozzolans. It is analuminous or siliceous material that possesses no binding ability by itself. Whe
What areb the philosophical elements of strategic planning?
Question Why is it best to design storm water drains to match soffit? Answer Storm water drains gather storm water in their corresponding catchment areas throughout rainst
Question What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures? Answer In design
Question What is main importance of geotextiles and sand in reclamation works? Answer For geotextiles used in recovery, they serve mainly subsequent two purposes
The liquid limit and plastic limit of clay are 100% and 25%, respectively. From a hydrometer analysis it has been found that the clay soil having of 50% of particles smaller than 0
State the Modulus of Elasticity of Concrete The Young's modulus of elasticity of concrete is primarily influenced by the elastic properties of the aggregate and to a lesser ex
Question Why is slump specified in concrete carriageway comparatively low like 30mmwhen compared with normal concrete like 75mm? Answer Slump of concrete carriageway
Explain the Signalized Intersections Cycle length - the time required for one complete sequence of all signal indications Phase - the right-of-way (green), change (yellow),
What would be the best way to evaluate the field performance benefits of subsurface drainage in a flexible pavement? Short term and long term, thick or thin HMA..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd