A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Syphon, what is the design of syphon

what is the design of syphon

Surveying, explain operations of direct and indirect leveling?

explain operations of direct and indirect leveling?

Building, What quantity of cement will be needed to lay 2000 blocks of 9 in...

What quantity of cement will be needed to lay 2000 blocks of 9 inches using a mortar ratio of 1:6 with a thickness of 25mm in-between blocks.

Surveying, what do you understand by the term local attraction

what do you understand by the term local attraction

How the water table is lowered, The water table is lowered from a depth of ...

The water table is lowered from a depth of 3 m to a depth of 6 m in a deposit of silt. The silt remains saturated even after the water table is lowered. What would be the enhance i

Continuous beam reaction by equilibrium equation, Solve problem of continu...

Solve problem of continuous beam with equilibrium equation

Harbour, typical layout showing dock,quay.jetties,turning circle,pier

typical layout showing dock,quay.jetties,turning circle,pier

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd