A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
h = u + pv is a combination of properties and hence must also be a property. h is the SPECIFIC ENTHALPY in kJ/kg H = U + pV is the ENTHALPY in kJ
uses of Earth moving equipment
Pls provide matlab design for transportation engg.
what is dredge line
why road project late
modified pratt truss with detailing in 3D
Relaxation losses in prestressing steels The relaxation losses in prestressing steels vary with type of steel, initial prestress, age, and temperature and, therefore, shall be
Q. Show Suspended Impurities in water? The solid particles which are dispersed in water are referred as suspended Impurities. These are microscopic as under-
explain the construction while aligning roads on hilly areas
The exciting force in a constant force type of excitation was 120 kN. The natural frequency of the machine foundation is 4 Hz. The damping factor is 0.36. Verify the magnificati
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd