Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Doors and windows, important considerations in case doors and windows

important considerations in case doors and windows

Explain the scaling - underwater inspection of bridges, Explain the Scaling...

Explain the Scaling - underwater inspection of bridges? Scaling is the gradual and continuing loss of the surface mortar and aggregate over an area. This condition is commonly

Pre-tensioned concrete elements, Pre-tensioned concrete elements It is ...

Pre-tensioned concrete elements It is the act of transferring the stress in prestressing tendons to the concrete member. In the case of pre-tensioned concrete elements, this st

Bedding of precast concrete paving units, Q. Sand layer vs. cement sand use...

Q. Sand layer vs. cement sand used as bedding of precast concrete paving units Cement sand is a mixture of sand and cement and it behaves as a cohesive mass once mixed. Usuall

Measure the stress increment, A raft of size 4 m × 4 m carries a uniform lo...

A raft of size 4 m × 4 m carries a uniform load of 200 kN/m 2 . Using the point load approximation with four equivalent point loads, measure the stress increment at a point in the

Steel truss 15 m span, types of truss of 15 m cantilever with 1000 kg on fr...

types of truss of 15 m cantilever with 1000 kg on free end. May be steel or any lightest material aluminium anodized truss. thanks

State average increase of pressure in the clay stratum, A building was to b...

A building was to be constructed on a clay stratum. Preliminary analysis showed a settlement of 60 mm in 6 years and an ultimate settlement of 250 mm. The average enhance of pressu

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd