Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Define masonry substructure- underwater inspection of bridge, Define Masonr...

Define Masonry substructure- underwater inspection of bridge? In early days, masonry, particularly stone masonry was extensively used for bridge piers and abutments. Typically,

Fluid Mechanics, A 4-m-long, 6-cm-diameter cylinder placed normal to the fl...

A 4-m-long, 6-cm-diameter cylinder placed normal to the flow is used to measure the velocity of an air stream. If a force of 50 N is measured, the air velocity is nearest (for air

What is meaning of washers while using bolts, Question What is meaning ...

Question What is meaning of washers while using bolts? Answer Purpose of installing washers in a classic bolting system is to distribute loads under bolt heads and nu

Levelling, the cooke''s reversible level

the cooke''s reversible level

Explain the dry density and buoyant unit weight, A partially saturated soil...

A partially saturated soil from an earth fill has a natural water content of 19% and a bulk unit weight of 19.33 kN/m 3 . Suppose the specific gravity of soil solids as 2.7, comput

Consultant , how to convert a varying distributed load to a uniformly distr...

how to convert a varying distributed load to a uniformly distributed load

Ballast and sub-ballast aggregates, I want to check the grammer of report a...

I want to check the grammer of report and edit it in better sentances , reduce the Plagiarism & edit the reference to havaerd style

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Lorentz transfarmation, explain the concept of time dilation on the basis ...

explain the concept of time dilation on the basis of lorentz transfarmation equations

Explain the maximum spacing of piles, Q. Explain the Maximum spacing of pil...

Q. Explain the Maximum spacing of piles? One of the factors which affect the distribution of loads from the structures to each pile is assumption of flexibility of the pile ca

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd