Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Determine the grain exact gravity, (i) A dry soil has a void ratio of 0.65 ...

(i) A dry soil has a void ratio of 0.65 and its grain exact gravity is = 2.80. What is its unit weight? (ii) Water is added to the sample so that its degree of saturation is 60%

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Determine the coefficient of compressibility, A saturated clay layer 4 m th...

A saturated clay layer 4 m thick is located 6 m below GL. The void ratio of the clay is 1.0. When a raft foundation is located at 2 m below GL, the stresses at the top and bottom o

Rail tensors, A hydro stressor consists essentially of a hydraulic pump whi...

A hydro stressor consists essentially of a hydraulic pump which transmits its force through connecting vans to clamps which grips the rail. In case of mechanical tensor the force i

Roads, how to calculate number of passes while compaction

how to calculate number of passes while compaction

Manhole covers finished of cast iron same as ductile iron, Question Why are...

Question Why are manhole covers finished of cast iron as same are through of ductile iron ? Answer Usually, manholes covers are made of cast iron. Though, in viewpoint of pipe

Structural engg, how static and dynamic frames are works?

how static and dynamic frames are works?

Explain rcra and hswa - hazardous waste regulations, Explain RCRA and HSWA ...

Explain RCRA and HSWA - Hazardous Waste Regulations 1. In 1976, Congress passed the Resource Conservation and Recovery Act (RCRA) and directed EPA to establish hazardous waste

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd