A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
#questiohin..
types of concrete and its uses
what''s a distomat?
timber roof joints
Determine about the pre-stressed concrete beam A pre-stressed concrete beam has a width of 200 mm and an overall depth of 400 mm. The permissible stresses in tension and compre
describe in detail the various parts of a total station
Rock reinforcement - how it works? For rocks with widespread fractures, individual blocks resulting from these fractures can fall out and as a result slope failure can take pl
How do you treat High Sulfate soils, Gypsum? Is it good practice to build on it?
WHAT IS FLYBBACK LEVELLING
A continuous wall footing, 1 m wide, rests on sand, the water table lying at a great depth. The corrected N-value for the sand is 10. Verify the load which the footing can support
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd