A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
describe setting out right angle at given point on a chain line and when the point lies outside the chain line
WHY RAFTING IS REQUIRED AND WHAT PRECAUTIONS SHOULD BE TAKEN DURING RAFTING? AND WHAT IS THE ALTERNATE OF RAFTING.?
Define Fathometer with the odolite - Sounding/Sensing Devices? The horizontal scale problem in use of Fathometer can be solved by using equipment, which combines a Fathometer w
best scale
Triangular prism axis is parallel to both HP and VP
write a short on vector representation of force(addition and substraction )
how can Simulink calculate wave speed of water hammer
meaning of ferrule
Define Special considerations for underwater inspection? Once a diver enters the water, there environment changes completely. Visibility decreases and is often reduced to near
Explain Energy Grade Line (EGL) Graph of the sum of the potential, pressure and kinetic energies along a pipe or open channel. Energies are plotted along the y-axis above a dat
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd