A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
how to design a staircase?
collect the field deta manualy and drw the drawing as per scale
The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c
what is the difference between feasibility study and traffic counting
Define Hydraulic Grade Line (HGL) Graph of the sum of the pressure and potential energies at a position along a pipe or open channel. The difference between the EGL and the HGL
Sketch typical complete grain-size distribution curves for (i) well graded soil and (ii) uniform silty sand. Form the curves, evaluate the uniformity coefficient and effective size
State the term- friction in tendon Considerable frictional loss takes place due to friction between the tendon and the material surrounding it, namely the concrete or the sheat
Definatiom
20MM AGGRIGATE PASSING SHEDULE
derive equation of radial pressure and loop stresses of thick cylinder
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd