A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
procedure of water bound macadam
1(a)Explain the difference between a concurrent and a non concurrent force system . (b)If a non coplanar force system is acted upon by equal and opposite forces,it must be in equil
Solve the following problems and show all steps and calculations clearly: 1. A water treatment plant uses a dual media filter. The two media used are: a) Anthracite coal with ef
study of cross staff
i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar
Different tape corrections
Question What is major disparity between fasteners , bolts and screws ? Answer Fastener is a broad term to explain something that is used as a restraint for holding
The plastic limit and liquid limit of a soil are 33% and 45% respectively. The percentage volume change from the liquid limit to the dry state is 36% of the dry volume. Likewise, t
Ask questio #Minimum 100 words accepted# what is varigon theorem and what are their application ? its examples
Simple bending theory
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd