Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Weigh batching, measurement of gauge box for sand ?

measurement of gauge box for sand ?

Define ways of providing the anti slip device - by stops, Define Ways of pr...

Define Ways of providing the anti slip device - By stops? In this method stopper plates or angles are welded to the underside of the girder and embedded in the bed block. It sh

Assignment, How to do assignment on the basis of azetropic mixture

How to do assignment on the basis of azetropic mixture

Bending moment , The internal forces in any cross-section of a symmetric me...

The internal forces in any cross-section of a symmetric member in pure bending are equivalent toa couple M The moment of the couple is referred to as the bending moment in the s

General requirement for civil engineering, Question General requirement for...

Question General requirement for Civil Engineering Works in 1992 Edition, Clause 15.09 details that tying wires for strengthening adjacent to and above Class F4 and F5 closes must

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd