A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
beam
Explain the crushing strength test
aim of prismatic compass
hi
Explain Some Points regarding to Hardness 1) Hardness removal using lime and soda is based on the solubility reactions of calcium carbonate, CaCO 3 and magnesium hydroxide, Mg
In order to make wise investments in a marketplace experiencing enhancing levels of risk, companies are turning to feasibility studies to verify if they should offer new products,
Explain Statically Indeterminate Structures Fall into two categories: 1. Beam problems with additional supports/restraints 2. Axial bar members subjected
Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by the engineer engaged in the design of pre-stressed concrete membe
Normal 0 false false false EN-IN X-NONE X-NONE
Estimation of Discharge: The estimation of discharge of a stream is necessary for determining the waterway, clearance and foundation details. Discharge is estimated from :
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd