A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Define the Impact Damage - underwater inspection of bridge? Impact from moving vessels or logs carried during the floods can inflict damage to the structure. The impact or coll
Q. Use of PFA and GGBS? Both PFA and GGBS are by-products of industry and use of them is ecologically friendly. Most significantly, with PFA and GBS adopted as partial replacem
report
#questiosssn..
state and prove Heisenberg uncertainity principle?
The drainage system of a cantilever wall shown in Figure As 1 became blocked after a heavy rainstorm and the groundwater level, which was originally below the base, rose to1.5 (m)
Flaky and elongation index
N-type semiconductor is an example of what semiconductor? Answer : N-type semiconductor is an example of extrinsic semiconductor.
what is barometric leveling
Describe about the Baur-Leonhardt system The Baur-Leonhardt system is included in the third type of anchorages which work under the principle of looping tendon wires at the en
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd