A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Location and spacing of borings The location, spacing of geophysical profiles, soundings and borings should be such that, you will be in a position to accurately predict the
Explain the "Standard Penetration Test" used in soil exploration. List the information that can be obtained by the test when made in (a) clay, (b) sand. Comment on the correctio
Classification of lintels
Poisson distribution function: Let X I , X 2 , ..., X,& b e n independently and identically distributed random variables each having the same cdf F ( x ). What is the pdf of t
Question What are main dissimilarities in function between rock anchors and rock sockets ? Answer Rock anchors are used first and foremost for resisting uplift forc
sway portal frame
design a 3-meter cantilever slab to carry a uniform total dead load of 8.2KN/m^2 and a concentrated live load at the free end of 30 KN/m. f''c=28Mpa fy=420Mpa.
turbine details
Explain briefly shallow foundation?
Why hoisting and conveying equipment is very important in civil engineering?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd