Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Assignment, on timber, varieties , preservation, and seasoning of timber

on timber, varieties , preservation, and seasoning of timber

Determine the coordinate for point r, For the project work points (x,y) sho...

For the project work points (x,y) shown in the figure the bearing of point R is due West. The coordinate for point R is most nearly:    Solution: Determine the length o

Principle for conducting surface regularity test, Question What is dist...

Question What is distinction in principle for conducting surface regularity test and sand test? Answer Purpose of surface regularity test is to assess riding quality

One layered spatial structures, Classification of the damage according to t...

Classification of the damage according to the type of structures The level of damage in spatial trusses has also been classified into three different levels based on th

Foundation, why is the foundation failure?

why is the foundation failure?

Drawing, parabola by offset method

parabola by offset method

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd