Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

What is thermo-electric prestressing, What is Thermo-electric prestressing ...

What is Thermo-electric prestressing We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other mea

How the bursting tensile forces produced, How the Bursting Tensile Forces p...

How the Bursting Tensile Forces produced These are tensile forces produced due to concentrated longitudinally applied prestressing forces in the end zone of a post-tensioned co

Determine about the tensile stresses, Determine about the tensile stresses ...

Determine about the tensile stresses Unifody prestressed members designed for equal flexure in opposite directions,without permitting tensile stresses under working loads, requ

Analysis of the two stage construction, A County is planning to build a new...

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widen

Design the 2-span continuous center, Design the 2-span continuous center T-...

Design the 2-span continuous center T-beam, B2, for the floor syetem shown below. The girders that the beam frames into are all 24" wide. Using fc'= 5 ksi, and fy = 60 ksi. The ser

Road survay, how many programmes in road survey by level matichine and ts?

how many programmes in road survey by level matichine and ts?

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Brick masonry., an opening of width 3m and height 2.7 in a brick masonary h...

an opening of width 3m and height 2.7 in a brick masonary has to be provided with door cum window. plan, elevation, section and 2 joining details

Rmc, about rmc and what are the safety measures taken and which licences ar...

about rmc and what are the safety measures taken and which licences are required

Paint, Description of paint

Description of paint

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd