Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Designing of watermain, Question In designing of watermain , regular p...

Question In designing of watermain , regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than 600mm. Give some speci

Determine the concept of resultant force at a section, Resultant force at a...

Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

What is activated sludge process, Q. What is Activated Sludge process? ...

Q. What is Activated Sludge process? The term Activated Sludge is used to indicate the sludge which is obtained by settling sewage in presence of abundant oxygen. The Activated

PLANKING AND STRUTING FOR SHALLOW EXCAVATION, DEFINITION TYPE STEP OF CON...

DEFINITION TYPE STEP OF CONSTRUCTION STEP OF SAFETY

Measure the stress increment, A raft of size 4 m × 4 m carries a uniform lo...

A raft of size 4 m × 4 m carries a uniform load of 200 kN/m 2 . Using the point load approximation with four equivalent point loads, measure the stress increment at a point in the

Retaining walls, Retaining Walls: A wall used to retain some material ...

Retaining Walls: A wall used to retain some material on one or both sides of it can be termed as retaining wall. Commonly, it is used to retain soil at two different levels on

Fire resistance of steelwork, Q. Fire resistance of steelwork Because ...

Q. Fire resistance of steelwork Because of the high thermal conductivity of steel, temperature of unprotected steel is almost the same as temperature of fire. Because the yiel

Design Mix M35/C35, What is the actual mix propotion for M35/ C35 design mi...

What is the actual mix propotion for M35/ C35 design mix concrete

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd