Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Load transmission, • The transmission of load through a structure can be co...

• The transmission of load through a structure can be complex but in any particular case            - The applied load can usually be classified into 4 types                •

Coating on concrete – complete im-permeability to moisture, Q. Coating on c...

Q. Coating on concrete – complete im-permeability to moisture? In designing protective coating on concrete structures, stoppage of water ingress by the coating is generally req

Importance of racking load for a pre-stressed concrete beam, Importance of ...

Importance of racking load for a pre-stressed concrete beam Evaluation of cracking load for a pre-stressed concrete beam member is important for the following cases/reasons.

Define recommendations for confined elastomeric pad, Define Recommendations...

Define Recommendations for confined elastomeric pad?  (a) Permissible limits for confined pressure on elastomer pad depends upon effectiveness of internal seal preventing it fr

Settlement due to lowering of water table, Q. Settlement due to Lowering of...

Q. Settlement due to Lowering of Water Table? Water table is encountered with, whenever any excavations are made for foundations. The water is to be out for working conditions.

., WHAT IS PILE CORROSION

WHAT IS PILE CORROSION

State about the pre-tensioned concrete beam, State about the pre-tensioned ...

State about the pre-tensioned concrete beam A pre-tensioned concrete beam, 200 mm wide and 300 mm deep, is prestressed by straight wires carrying an initial force of 150 kN at

M.o.c, lime saturation factor meaning with simple english

lime saturation factor meaning with simple english

Compute interior or intersection angle, Compute Interior or Intersection An...

Compute Interior or Intersection Angle for the following circular curve:   Answer- I = 180° - 60° - 60°= 60

Determine the equivalent of free float, The free float is equal to: a. L...

The free float is equal to: a. Latest allowable event occurrence time + Early finish time b. Earliest event occurrence time + early finish time c. Latest allowable event o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd