Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Concrete, What is Polymer Concrete?

What is Polymer Concrete?

Maintenance of airport pavements, Maintenance of Airport Pavements: ...

Maintenance of Airport Pavements: Maintenance Elements The maintenance of airport pavements is an important task of a civil engineer, since the safe movement of aircr

Surveying, if bearing of AB is 190& that of CB is 260,the included angle AB...

if bearing of AB is 190& that of CB is 260,the included angle ABC is how?

Surveying, what is the trignomerty leveling

what is the trignomerty leveling

Moment, what is a couple?

what is a couple?

How to determine the water content and bulk density, The wet weight of a sa...

The wet weight of a sample is missing in a Proctor test. The oven-dry weight of this sample is 189 N. The volume of the mould used is 1000 cm 3 . If the degree of saturation of

#title.steel desogn, Tension memebers example for a two channel connected t...

Tension memebers example for a two channel connected to a gusset .find the tensile capacity

Concrete technology, material for formwork and their specifications

material for formwork and their specifications

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd