A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Define Types of Inspection of Bridge? Underwater inspections are generally categorised into five types: - Inventory - Routine - Damage - In-depth - Interim
A square pile group of 9 piles passes by a recently filled up material of 4.5 m depth. The diameter of the pile is 30 cm and pile spacing is 90 cm centre to centre. If the unconfin
three point problem
Q. Purpose of tar in bituminous materials? Tar is usually incorporated in bituminous materials due to the below reasons: (i) Blending of tar with bitumen possesses better b
input and output devices used
Differentiate between Short Column and Slender Column Short Column It is a column of rectangular section, the effective length of which does not exceed 12 times of its lea
Soil Compaction: Soils used in road construction need to be thoroughly rolled and compacted. Compaction of soil is needed for the following reasons. (a) A well compacted s
what are advantage of stepping stone
HWY
reinforcement.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd