A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Explain Fluid Mechanics or Properties – Viscosity A measure of a fluid's resistance to flow when acted upon by an external force such as pressure or gravity. Also termed, "Abso
A retaining wall with a smooth vertical back retains a purely cohesive fill. Height of wall is 12 m. Unit weight of fill is 20 kN/m 3 . Cohesion is 1 N/cm 2 . What is the total act
Q. Write short note on Stock Verification? It is desirable that there should be a frequent reconciliation of the balances as shown in the numerical ledgers kept by the subordin
Derivation of Moment-Area Method
how to compute the compound elements particularly outstanding element of compression flange if 2-ismb300 are placed side by side
Explain coulomb''s wedge theory-definition and derivation
kankar lime
Triangular prism axis is parallel to both HP and VP
Low Cost Roads Connecting Villages: Problem of Village Connectivity It is estimated that nearly 45 per cent of India's villages are not connected by an all-weather ro
causes for decay of timber
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd