A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
describe in detail the uses of concrete
What is the difference between Dense bituminous Macadam and bituminous macadam
Minimum volume of sump volume for pumps Maximum pumping rate = Q P Volume of sump = V Inflow Rate = Q i Cycle Time T c = t 1 + t 2 t 1 = V / Q P - Q i t 2
What is the special feature of this system rather than other?? What do you mean by principal of looping system?
write buckling and dislodging of brick slip?
evaluate limsin3theta over theta
Sealing moving cracks and non-moving cracks In developing a suitable method to seal up cracks detected on concrete surface, it's of paramount importance to conclude if further
parts of Bridges & culverts
by estimation
Question In modeling a nonrigid mat foundation by using elastic springs, have a uniform modulus of subgrade reaction be used along whole base of mat ? Answer A bed of
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd