Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Contours, how can you draw contours of a non square grid?

how can you draw contours of a non square grid?

Explain the swell factor of soil, Explain the Swell Factor of Soil A so...

Explain the Swell Factor of Soil A soil's swell factor represents the fact that the volume of soil placed by nature in the ground is not the same as the volume of the same mass

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

Enthalpy, h = u + pv is a combination of properties and hence must also be ...

h = u + pv is a combination of properties and hence must also be a property.  h is the SPECIFIC ENTHALPY in kJ/kg  H = U + pV is the ENTHALPY in kJ

Determine the coefficient of compressibility, A saturated clay layer 4 m th...

A saturated clay layer 4 m thick is located 6 m below GL. The void ratio of the clay is 1.0. When a raft foundation is located at 2 m below GL, the stresses at the top and bottom o

Walls, partition walls

partition walls

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd