A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha
In this question we consider a bended outlet of pipe flow AB. End A is attached to an incoming pipe by a flange connection. The pipe diameter at A is the same as the incoming pipe,
rolling steel door
Question If concrete compression test not pass, So Schmidt hammer test will be adopted as an alternative test to confirm concrete strength ? Answer Schmidt hammer test is
how to get shear force
method of estimation
Construction black cotton soil
Question Have to emulsified asphalts or cutback asphalts be selected as staple coat in bituminous road works? Answer Emulsified asphalt is a postponement of asphalt
What is the special feature of this system rather than other?? What do you mean by principal of looping system?
are u familiar with elfen software?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd