A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
Using Stokes' law, determine the time of settlement of a sand particle of 0.2 mm size (specific gravity 2.67) through a depth of water of 30 cm. The viscosity of water is 0.001 N-s
Explain about reciprocal ranging
a 45 cm deep roof beam is provided on 30 cm wall of a room size 3.0m*5.0m . calculate the quantity of steel required in beam on percentage basis.
why we perform survey work from whole to the part?
LA values of different sizes of materials can be proportionately determined?
parabola by offset method
i need simple ans for this question tell me precaution of dampness
Most of the existing rubber dams are of air-filled types. Water-filled rubber dams aren't preferred for the below reasons: (i) By giving same sheet length and dam height, tensi
what is barometric leveling
State the algebraic equations showing the variation of safe bearing capacity of soil (for clay and sand to be given separately) in shallow foundation with: (i) depth of foundati
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd