A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.
Solution: Apply the equation: Durationactivity = Area / Productivity * Crew Size
Durationactivity = 200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days
what should we do if alkalinity in water is greater than 25
how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#
how to establish temporary benchmark
DESCRIBE ON THE TOPIK OF VULCANIZATION
Define Physical deterioration - underwater inspection of bridges Typical defects include: - Scaling - Cracking - Spalling - Disintegration - Abrasion
tupes of dam
#All of them
component of bridge flooring
Comparison of pre and post-tensioning A comparison between pre-tensioned and post-tensioned concrete members can be made on the basis of the following considerations. (a) T
types of cement
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd