Duration activity for cast-in-place foundation formwork, Civil Engineering

Assignment Help:

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF formwork for a cast-in-place concrete foundation using 3-crews.

Solution:   Apply the equation:  Durationactivity = Area / Productivity * Crew Size

Durationactivity =  200,000 - SF/ 1000-SF/ Crew-day * 3 crew = 66.67 days


Related Discussions:- Duration activity for cast-in-place foundation formwork

Concrete pavement, Question In case of concrete pavement, why is requir...

Question In case of concrete pavement, why is requirement of 95% by mass of quartz grains are specified in contract? Answer In universal Specification of Civil Enginee

Compute the ultimate settlement, A 2 m wide strip footing is to be constru...

A 2 m wide strip footing is to be constructed in a sandy stratum of 2 m thick. The depth of the footing is 1 m below ground surface. The sand layer is underlain by lm thick cla

Surveying, description of instruments used transfer upper floors *plumb-bob...

description of instruments used transfer upper floors *plumb-bob method *theodolite method *theodolite and target method *optical plumbing method

Analytical methods for pollutants under the clean water act, Analytical Met...

Analytical Methods for Pollutants Regulated Under the Clean Water Act? We suppose that you have knowledge of and access to the relevant analytical methods. These methods cover

Explain the properties of poly tetra fluoro ethylene, Explain the Propertie...

Explain the Properties of Poly Tetra Fluoro Ethylene? PTFE is a linear chain polymer of great molecular strength, known for its chemical inertness and low coefficient of fricti

Surveying land, principle of working from whole to part

principle of working from whole to part

Hydrographic data for design of bridge, Q.What Hydrographic data required f...

Q.What Hydrographic data required for Design of bridge? (i) Design discharge for bridge waterway and foundation with corresponding high flood levels. Frequency curve for annual

Colour code, in colour working drawing what are the colour code?

in colour working drawing what are the colour code?

Calculate the amount of cubic yards of soil, A proposed building site requi...

A proposed building site requires 135,000-ft 3 of imported fill.  A borrow site is located 5-miles Northeast of the project site where the soil has a shrinkage of 16%.  The amount

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd