Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These re to be combined into workstations to create an assembly line. The assembly line operates 7 1/2 hours per day. The output requirement is 1,000 units per day.
Task - Preceding tasks - Time (Seconds) -- Task - Procedural Tasks - Time (Seconds)A - ! - 15 -- G - C - 11B - A - 24 -- H- D - 9C - A - 6 -- I - E - 14D - B - 12 -- J - F,G - 7E - B - 18 -- K - H,I - 15F - C - 7 -- L - J,K - 10
a. What is the workstation cycle time?
b. Balance the line using the longest task time based on the 1,000 unit forecast, stating which tasks would be done in each workstation.
c. For b, what is the efficiency of your line balance?
d. after production was started, marketing realized that they understated demand and must increase output to 1,100 units. What actions would you take? BE specific in quantitative terms, if appropriate.
Explain the factors affecting motivation . Factors influencing motivation: Achievement-Personal satisfaction in problem solving and job completion. Advancement-Promot
What are the issues of management does Google strategy 2010 needs to address? How could they be analysed and evaluated?
Molecular Response to Thyroid Hormones during Metamorphosis Thyroid hormones can cause obtainable tissues to break down or can remold the tissues to their adult function. The
Q. What are the various managing inventory tools? Raw material Materials and elements used to assemble or manufacture finished goods. Work-in-progress Incomplete f
Process Technology Life Cycle Process technologies have life cycles related to product life cycles as shown in figure below. Over time unit manufacturing costs diminish for ma
Explain Dummy Activity. Every project has a number of job operations or tasks that are termed as activities. An activity is a component of a project and this may be a process,
How many stamping machines are required?
How common do you think it is for people to try to justify their conduct by the argument that "Everybody's doing it"? Give examples from your own experience.
Routing Procedure For a new product or part the routing procedure consists of seven principle steps: 1.The first step is to analyze the product or articles and fabricate int
10 person assembly line, 160 valves produced during 8 hour shift, calculate the labour productivity
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd