Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These re to be combined into workstations to create an assembly line. The assembly line operates 7 1/2 hours per day. The output requirement is 1,000 units per day.
Task - Preceding tasks - Time (Seconds) -- Task - Procedural Tasks - Time (Seconds)A - ! - 15 -- G - C - 11B - A - 24 -- H- D - 9C - A - 6 -- I - E - 14D - B - 12 -- J - F,G - 7E - B - 18 -- K - H,I - 15F - C - 7 -- L - J,K - 10
a. What is the workstation cycle time?
b. Balance the line using the longest task time based on the 1,000 unit forecast, stating which tasks would be done in each workstation.
c. For b, what is the efficiency of your line balance?
d. after production was started, marketing realized that they understated demand and must increase output to 1,100 units. What actions would you take? BE specific in quantitative terms, if appropriate.
You are a middle manager helping to implement a new corporate cost-cutting strategy, and your meeting scepticism, resistance, and in some cases, outright hostility from your subord
Identify and discuss factors that can increase the size and complexity of the information system structure (beyond those discussed in the text). •Make at least three recommendation
Using the product life cycle, describe a product at each stage of the PLC and support your choice.
You are writing a System Safety Program Plan (SSPP). What are some of the key elements/tasks you should include in the SSPP to make this plan effective?
What are the demand management strategies? Demand management strategies: It is aims to affect customer demand levels at exact times, so as to match demand closer to the o
Porter's value system shows the organisation in terms of The value chains of suppliers, channels and the customer.
Order Qualifiers - Operations Strategy These are not essential to winning business in their own right. They may however, determine the entry level whereby the organisation is
Why do projects start slow and end slow?
Your company, a large online high school, is planning to implement a new innovative social networking technology for their students. The technology would allow students to get to k
Operation Planning and Scheduling System Operation planning g and scheduling system concern the volume and timing of the outputs utilizations of the operations capacity and the
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd