Consider the WBS shown below:

1.00.00
1.1.0
1.1.1
1.1.2
1.2.0
1.2.1
1.2.2

If the total program costs $100,000 and 1.2.1 and 1.2.2 are each $20 K, then the cost of 1.1.0 is:

Answer

$20 K

$40 K

$60 K

Cannot be determined


Related Discussions:- Determine the wbs shown below

Give expectancy theory claims that motivation is a function, Expectancy the...

Expectancy theory claims that motivation is a function of Answer efforts, performance, and rewards. individual traits and supervisory skills. aptitude, training, and op

Define the importance of management systems, 1. Propose a definition of inn...

1. Propose a definition of innovation in your own words (50-100 words). 2. Compare the concepts of innovation, invention, and creativity. 3. Describe the relationship between

Explain safety stock would provide a stock out risk, The injection moulding...

The injection moulding department of a company uses an average of 30 gallons of special lubricant a day. The supply of the lubricant is replenished when the amount on hand is 170 g

Results and enabler are features of which quality management, Results and e...

Results and enablers are features of which quality management The European Foundation for Quality Management (EFQM) excellence model

Case study, what is continuous improvements

what is continuous improvements

Description of the setting as well as participants, Being a minority (Afro-...

Being a minority (Afro-American) in a class non-minority spending three months in this class I need to describe the following: Prepare a report of your discoveries by answering the

Explain the defined retirement plan, 1. Why would the government not tax us...

1. Why would the government not tax us for the Employee Benefits we receive? 2. As a percent of payroll, how much does employer pay for Employee Benefits? 3. Explain the defe

Explain develop an mrp planning schedule showing gross, Assume that Z is ma...

Assume that Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of ea

Key performance objectives of operation strategy, Key Performance Objective...

Key Performance Objectives of Operation Strategy There is broad consensus that supports the view that operational competitive priorities which satisfy customers such as price

Planning tools or techniques, Planning Tools or Techniques General Fra...

Planning Tools or Techniques General Framework Discuss the Planning function in the context of the work of the manager.  Illustrate with a case study. Individual Compone

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd