Consider the WBS shown below:

1.00.00
1.1.0
1.1.1
1.1.2
1.2.0
1.2.1
1.2.2

If the total program costs $100,000 and 1.2.1 and 1.2.2 are each $20 K, then the cost of 1.1.0 is:

Answer

$20 K

$40 K

$60 K

Cannot be determined


Related Discussions:- Determine the wbs shown below

Explain basic concepts of construction management, How does the transformat...

How does the transformation process apply to the field of construction management, and how you might apply the basic concepts?

Operation research, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Explain key aspects of operations management, 1- With respect to a firm's s...

1- With respect to a firm's supply chain design, what are some key challenges in terms of achieving an optimal level of mass customization? 2 - Articulate key aspects of operati

Scheduling and sequencing, In what sequence would the jobs be ranked accord...

In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS (b) EDD, (c) SPT, and (d) LPT? All dates are specified as manufacturing planning calen

Explain development of a strategic plan, What are the primary external orga...

What are the primary external organizational considerations for the development of a strategic plan? Which consideration is the most important? Why?

Explain selling verses marketing concept, Explain Selling Vs Marketing Conc...

Explain Selling Vs Marketing Concept. Selling Vs Marketing Concept : The concept of selling is a management orientation which assumes that consumers will normally not buy suff

Describe how the marketing mix differs for each segment, Select an everyday...

Select an everyday product (personal fitness training, CDs, dog food, cell phones, shoes for example). Show how different versions of your product are aimed toward different market

Explain how the project scope will be defined, The project scope planning p...

The project scope planning processes include all of the following EXCEPT: A. How the project scope will be defined B. How the requirements will be collected C. How the work brea

Would like for you to advice changes that would significant, Your boss woul...

Your boss would like for you to suggest changes that would significant shorten it. what would you suggest?

Explain what is the current state of hrm, What is the current state of HRM-...

What is the current state of HRM-r related technologies in your organization? What are organizational leaders' positions as they relate to using HRM-r related technologies (for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd