Define the arrow diagramming method, Civil Engineering

Assignment Help:

Define the Arrow Diagramming Method

  • Activity-on-Arrow (Branch) with nodes as dependencies
  • Uses finish-to-start precedence only. The solution method for an activity on arrow problem is essentially the same as for the activity-on-node problems requiring forward and backward passes to determine the earliest and latest dates.
  • May require use of dummy activities to maintain proper logic of various construction activities. If two activities have the same starting and ending events, a dummy node is required to give one activity a uniquely identifiable completion event.
  • A dummy is treated as an activity (represented by a dotted line on the arrow network diagram), that indicates that any activity following the dummy cannot be started until the activity or activities preceding the dummy are completed. The dummy activity does not consume time or any resource.
  • Review Figure Activity-on-Arrow diagram below. Note the dummy activity showing the relationship between the material procurement and installation of the components.

 

1152_Define the Arrow Diagramming Method.png

Diagram- Activity on Arrow Diagram

 


Related Discussions:- Define the arrow diagramming method

What is the main reason being for the phenomenon, Sometimes side of concret...

Sometimes side of concrete bridges is observed to turn black in colour . What is the main reason being for the phenomenon ?

Distomat, Feactures and uses of distomat

Feactures and uses of distomat

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

What do you mean by synoptic coverage, Q. What do you mean by Synoptic Cove...

Q. What do you mean by Synoptic Coverage? Depending upon the area of interest, areas covering few hundred sq m to thousands of sq km can be suitably collected and studied. Phot

Walls, partition walls

partition walls

Evaluate the length of guide bund, Q. Evaluate the Length of guide bund? ...

Q. Evaluate the Length of guide bund? For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Concrete pavement, Question In case of concrete pavement, why is requir...

Question In case of concrete pavement, why is requirement of 95% by mass of quartz grains are specified in contract? Answer In universal Specification of Civil Enginee

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd