Good surface regularity for sub-base in concrete pavement, Civil Engineering

Assignment Help:

Q. Good surface regularity for sub-base in concrete pavement?

Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reasons:

(i) One of the primary functions of sub-base in concrete pavement is to provide a smooth and even interface amid concrete slab andsubgrade so that a uniform support is established. A regular surface of sub-base helps in decreasing the frictional and interlocking forces between concrete slab and sub-base and allowing shrinkage movement andeasier temperature.

(ii) A uniform sub-base surface is required in the construction of concrete slab of uniform thickness adopted in design. It saves the higher cost of concrete to make up the needed level.


Related Discussions:- Good surface regularity for sub-base in concrete pavement

Determine the area ratio of a thin walled tube, Determine the area ratio of...

Determine the area ratio of a thin walled tube samples having an external diameter of 6 cm and a wall thickness of 2.25 mm. Do you recommend the sampler for getting undisturbed soi

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Types of cement, Types of Cement In addition to ordinary Portland ceme...

Types of Cement In addition to ordinary Portland cement there are various varieties of cement. Significant varieties are briefly explained below: (i) White Cement: The ce

Commercial building, i) Describe the general significant of energy performa...

i) Describe the general significant of energy performance in industrial or commercial buildings.  ii) Draw the building layout and produce an overall description that will have

Determine the latitude and departure - transportation, Determine the latitu...

Determine the latitude and departure of each side of the closed traverse ABCDA.  Total the latitudes and departures. TIP: For Closed Traverse, Sum of Latitudes is Z

How to find back bearings?, Example: The following fore bearings were ...

Example: The following fore bearings were observed respectively for lines, AB, BC, CD, DE, EF and FG. Find out their back bearings: (i) 148°                          (ii

Define truss analysis-stability, Define Truss analysis-stability   ...

Define Truss analysis-stability   Identify whether a truss is determinate or indeterminate. Identify if the truss is stable or unstable   m = number of membe

Smallest size of a325 bolts needed for two plates in tension, What is the s...

What is the smallest size of A325 bolts required for the two plates in tension noted below, assuming the thickness of each plate is 1.0-in. and the applied force at each end is P=2

Pumping at joints in concrete carriageway, Q. Pumping at joints in concrete...

Q. Pumping at joints in concrete carriageway? Pumping at joints in concrete carriageway takes place in the presence of the below factors: (i)  Fine-grained subgrade (ii)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd