Good surface regularity for sub-base in concrete pavement, Civil Engineering

Assignment Help:

Q. Good surface regularity for sub-base in concrete pavement?

Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reasons:

(i) One of the primary functions of sub-base in concrete pavement is to provide a smooth and even interface amid concrete slab andsubgrade so that a uniform support is established. A regular surface of sub-base helps in decreasing the frictional and interlocking forces between concrete slab and sub-base and allowing shrinkage movement andeasier temperature.

(ii) A uniform sub-base surface is required in the construction of concrete slab of uniform thickness adopted in design. It saves the higher cost of concrete to make up the needed level.


Related Discussions:- Good surface regularity for sub-base in concrete pavement

Leveling, how to find the correction on leveling calculation

how to find the correction on leveling calculation

Culverts, Can anyone help me in finding the formula for submerged and unsub...

Can anyone help me in finding the formula for submerged and unsubmerged flow in culverts?

Bridge engineering, long span bridge or continuous bridge which is more pre...

long span bridge or continuous bridge which is more preferable and why ??? what is the major problem in continuous bridge and what would be its effect if there is any differential

Ranging, describe reciprocal ranging

describe reciprocal ranging

Determine the permissible stresses in steel, Permissible Stresses in Steel ...

Permissible Stresses in Steel As per the Indian code, the permissible stresses in the tendons at the time of initial prestressing should not exceed 80% of the characteristic t

Fluid mechanism, tell me something about velocity profile?

tell me something about velocity profile?

Design concrete structures and foundatri, What you need to do in my assignm...

What you need to do in my assignment only for the calculation part for project Task CalculateSG A: Ground Level, SG B: First Level, SG C: Second > Level, SG D: Third Level, and Su

Raft foundation, after formation of the soil under raft some area around th...

after formation of the soil under raft some area around the lift pit for example will be on tipping shape and some column placed in the same area the question how we place the col

State the coulomb wedge theory, A retaining wall is battered away from the ...

A retaining wall is battered away from the fill from bottom to top at an angle of 15° with the vertical. Height of the wall is 6 m. The fill slopes upwards at an angle 15° away fro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd