Good surface regularity for sub-base in concrete pavement, Civil Engineering

Assignment Help:

Q. Good surface regularity for sub-base in concrete pavement?

Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reasons:

(i) One of the primary functions of sub-base in concrete pavement is to provide a smooth and even interface amid concrete slab andsubgrade so that a uniform support is established. A regular surface of sub-base helps in decreasing the frictional and interlocking forces between concrete slab and sub-base and allowing shrinkage movement andeasier temperature.

(ii) A uniform sub-base surface is required in the construction of concrete slab of uniform thickness adopted in design. It saves the higher cost of concrete to make up the needed level.


Related Discussions:- Good surface regularity for sub-base in concrete pavement

How to design banks, Q. How to design banks? When approach banks are of...

Q. How to design banks? When approach banks are of medium height upto 3 m, the material may be homogeneous. For bigger heights zoned section with impervious core and pervious o

Show the direction of gunning in shotcreting, Q. Show the Direction of gunn...

Q. Show the Direction of gunning in shotcreting? At the time of the construction of shotcrete, it is intended at gunning the full thickness in one single operation and this hel

Explain resultant force on a area of a vertical plane, Resultant Force on a...

Resultant Force on a Given Area of a Vertical Plane The resultant force is calculated from the average pressure: R = (AVERAGE Ρ)(A)

Explain the swell factor of soil, Explain the Swell Factor of Soil A so...

Explain the Swell Factor of Soil A soil's swell factor represents the fact that the volume of soil placed by nature in the ground is not the same as the volume of the same mass

Define the meaning of circular prestressing, Define the meaning of circular...

Define the meaning of circular prestressing In circular prestressing, tendon wires are wrapped under tension over the concrete pipes which are pre-cast. The tension in the ten

Reinforcement, Where we can provided overlap in columns

Where we can provided overlap in columns

Engineering indicators in case of multi speed restriction, Multi Speed Rest...

Multi Speed Restriction (i.e. existence of two or more than two speed restrictions in continuation) When work of deep screening or sleeper renewal is in progress, there is situ

Explain statically indeterminate structures, Explain Statically Indetermina...

Explain Statically Indeterminate Structures  Fall into two categories:   1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd