Good surface regularity for sub-base in concrete pavement, Civil Engineering

Assignment Help:

Q. Good surface regularity for sub-base in concrete pavement?

Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reasons:

(i) One of the primary functions of sub-base in concrete pavement is to provide a smooth and even interface amid concrete slab andsubgrade so that a uniform support is established. A regular surface of sub-base helps in decreasing the frictional and interlocking forces between concrete slab and sub-base and allowing shrinkage movement andeasier temperature.

(ii) A uniform sub-base surface is required in the construction of concrete slab of uniform thickness adopted in design. It saves the higher cost of concrete to make up the needed level.


Related Discussions:- Good surface regularity for sub-base in concrete pavement

Of obstacles to both chaining and ranging.., #questof obstacles to both cha...

#questof obstacles to both chaining and ranging. ion..

Determine the natural frequencies - shear building, For the shear building ...

For the shear building shown, determine the natural frequencies (RAD/SEC) and the modal matrix. Also, sketch the deflected buildings in their normal modes using the top floor as th

Geometric design of roads, Geometric Design Of Roads: Geometric design...

Geometric Design Of Roads: Geometric design of roads deals with elements such as cross-section, horizontal and vertical alignment, sight distances, lateral and vertical cleara

Cutting edge in well foundation, Q. Cutting edge in well foundation? Th...

Q. Cutting edge in well foundation? The function of cutting edge on well foundation is basically to cut through the earth which being sunk. The angle of well curb pushes the ea

AUTOCAD, do you people deal with autocad

do you people deal with autocad

Modulus of elasticity of light-weight concrete, Modulus of elasticity of li...

Modulus of elasticity of light-weight concrete The modulus of elasticity of light-weight concrete is about 50 to 55% of that of normal-weight concrete. The loss of prestresses

Determine the soil shrinkage, Soil at a borrow area has a total unit weight...

Soil at a borrow area has a total unit weight of 120-PCF and a water content of 15 percent.  The soil from the borrow area will be used as structural fill and compacted to an avera

Mechanics of solids, if we take brass & steel and on applying temperature t...

if we take brass & steel and on applying temperature the brass contracts the steel expands how it is possible

Keywords of airport management, Keywords of Airport management: Air T...

Keywords of Airport management: Air Traffic Control: A system by which air routes, flight rules for flying aircraft and navigational facilities are provided in an airport.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd