Q. Good surface regularity for sub-base in concrete pavement?
Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reasons:
(i) One of the primary functions of sub-base in concrete pavement is to provide a smooth and even interface amid concrete slab andsubgrade so that a uniform support is established. A regular surface of sub-base helps in decreasing the frictional and interlocking forces between concrete slab and sub-base and allowing shrinkage movement andeasier temperature.
(ii) A uniform sub-base surface is required in the construction of concrete slab of uniform thickness adopted in design. It saves the higher cost of concrete to make up the needed level.
Rock reinforcement - how it works? For rocks with widespread fractures, individual blocks resulting from these fractures can fall out and as a result slope failure can take pl
Explain briefly physical classifications of stone
what is the procedure for gsb proctor test for matrial sampling for lab density
State the Needs for high strength steel and concrete In prestressed concrete construction, tendons have 3 small area of cross-section compared to the cross-sectional area
explain the principle of working from whole to part, as used in surveying
Q. Explain the design of graded filter? Use of graded filter has been traditionally used below the revetment and protection works. The material used in the granular / graded fi
Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di
Q. Explain Hot weather Patrolling ? Hot weather Patrolling is done for LWR and CWR tracks when the rail temperature reaches td + 20 0 C and above and td + 14 0 C for Central
types of windows
Question For a l ong slender structure similar to beams, propping is compulsory after elimination of formwork with reasons? Answer After concreting, time at which arresting of
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd