Q. Good surface regularity for sub-base in concrete pavement?

Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reasons:

(i) One of the primary functions of sub-base in concrete pavement is to provide a smooth and even interface amid concrete slab andsubgrade so that a uniform support is established. A regular surface of sub-base helps in decreasing the frictional and interlocking forces between concrete slab and sub-base and allowing shrinkage movement andeasier temperature.

(ii) A uniform sub-base surface is required in the construction of concrete slab of uniform thickness adopted in design. It saves the higher cost of concrete to make up the needed level.


Related Discussions:- Good surface regularity for sub-base in concrete pavement

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

Assignment, information of cement types

information of cement types

Water-bound macadam road construction for unpaved roads, how can I come up ...

how can I come up with the research on the water bound macadam road construction

Designing sewer pipes, Question While designing sewer pipes , why vitrifie...

Question While designing sewer pipes , why vitrified clay pipes commonly is used for pipe size less than 600mm still as precast concrete pipes with PVC lining is used for pipe

Settlement due to increasing load on surrounding soil, Q. Settlement due to...

Q. Settlement due to Increasing Load on Surrounding Soil? When any portion of the ground surface  has been loaded, it causes  the surface  of adjacent soil also to tilt and set

The regulations and specification that followed for compacti, what are The ...

what are The regulations and specification that followed for compaction works for earth dam in Oman.

Probable distribution function, The diameter of an electric cable, say X, i...

The diameter of an electric cable, say X, is assumed to be continous random variable with pdf;f(x)=6x(1-x), 0 b}.

Calculate the benefit-cost analysis ratio, Calculate the Benefit-Cost Analy...

Calculate the Benefit-Cost Analysis Ratio A city engineer is deciding which of two alternatives to select.  If the interest rate is 10% per year, the Benefit-Cost analysis rat

Paint system to protect steelwork from corrosion, Q. Paint system to protec...

Q. Paint system to protect steelwork from corrosion? In a typical painting system, there are generally three main layers primer, undercoat and finishing coat. Primer acts as th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd