Good surface regularity for sub-base in concrete pavement, Civil Engineering

Assignment Help:

Q. Good surface regularity for sub-base in concrete pavement?

Surfaces of sub-base material for concrete carriageway must be built in a regular manner due to the following reasons:

(i) One of the primary functions of sub-base in concrete pavement is to provide a smooth and even interface amid concrete slab andsubgrade so that a uniform support is established. A regular surface of sub-base helps in decreasing the frictional and interlocking forces between concrete slab and sub-base and allowing shrinkage movement andeasier temperature.

(ii) A uniform sub-base surface is required in the construction of concrete slab of uniform thickness adopted in design. It saves the higher cost of concrete to make up the needed level.


Related Discussions:- Good surface regularity for sub-base in concrete pavement

Retaining walls, Retaining Walls: Needed to retain the fill portion, a...

Retaining Walls: Needed to retain the fill portion, and generally constructed in dry stone masonry with pucca bunds (Figure). Figure: Typical Design for a Retaining

Design an equalization basin with a safety factor, A storm occurs with rain...

A storm occurs with rain of varying intensity falling over a commercial area. The area has a combined sewer system. Two interceptor sewers direct flow to the wastewater treatment p

Explain a critical path - construction management, Explain a Critical Path ...

Explain a Critical Path The series of activities which determines the earliest possible date of project completion Usually defined as those activities with minimal or

Find the settlement at the centre and at edge of the footing, A load of 300...

A load of 3000 kN is being taken by a square column footing. Side of the column is 3 m, footing rests on a silty soil with a Poisson's ratio = 0.3. Modulus of elasticity of the soi

Design of elastomeric bearings, Q. Design of elastomeric bearings? The ...

Q. Design of elastomeric bearings? The standard drawings of bridge bearings issued by RDSO are on the basis of UIC 772-R. To maintain uniformity of approach, the design of elas

Chain, describe and sketch a survey chain

describe and sketch a survey chain

Design of prestressed concrete pipes, Design of prestressed concrete pipes ...

Design of prestressed concrete pipes The design of prestressed concrete pipes should cover the following five stages : (a) Circumferential prestressing, winding with or wit

Effect of pile installation method, Effect of pile installation method to l...

Effect of pile installation method to load carrying capacity of piles The construction of piles by driving method causes an increase in density of surrounding soils. Therefore

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd