Define the term - pre- tensioning, Civil Engineering

Assignment Help:

Define the term - pre- tensioning

It is a method of prestressing in which tendons are placed, inside ducts or passages provided in concrete, after concrete gains sufficient strength. Tendons are then stretched and anchored at the ends of the concrete member. The transfer mechanism of prestressing force in this form of prestressing is different from that in the case of pre-tensioning. In this form of prestressing, the prestressing force is transferred to concrete through anchorages provided at the ends - not due to bond between concrete and tendons.


Related Discussions:- Define the term - pre- tensioning

Loss of prestress due to elastic shortening of concrete, Loss of Prestress ...

Loss of Prestress due to Elastic Shortening of Concrete Due to elastic shortening of  concrete, tendons are able to reduce their stretched length to the same extent upto which

Radial flow pumps for small flows and high heads, Radial flow pumps for sma...

Radial flow pumps for small flows and high heads In radial flow pumps, a diffuser/volute is generally designed at it outlet to convert the kinetic energy obtained during the pu

Determine minimum radius that can used on horizontal curve, What is the min...

What is the minimum radius, R min , that can be used on a horizontal curve with a 70 mph design speed, a maximum superelevation, e max = 8%, and a side friction factor, f = 0.10?

Define the meanings of texture, a) Define the meanings of 'texture' and 'st...

a) Define the meanings of 'texture' and 'structure' of a soil. b) Write the meaning of 'black cotton soil'? Indicate the geological and climatic conditions that tend to make

Calculate concrete yield in cubic feet per sack of cement, Calculate the Co...

Calculate the Concrete Yield in Cubic Feet per Sack of Cement A concrete mix design is 1: 1.9: 2.8 by weight.  The water cement ratio is 7 gallons of water per sack.  The aggre

Surveying, What is the shrinkage factor

What is the shrinkage factor

Assignment, do u do drawing assignment ( 3rd angle projection)

do u do drawing assignment ( 3rd angle projection)

Immersed tube method for underwater crossings, Immersed tube method for und...

Immersed tube method for underwater crossing includes the following basic construction steps: (i)  Prefabricating long tunnel units (concrete orsteel shell) in a dry-dock or shi

Explain the toxic characteristics - hazardous waste, Explain the Toxic Char...

Explain the Toxic Characteristics - Hazardous Waste - From the results of either  - Extraction Procedure(EP) toxicity (prior to March 1990) or Toxicity Characteristic Leachi

Light-weight aggregate prestressed concrete, Light-weight Aggregate Prestre...

Light-weight Aggregate Prestressed Concrete The use of  light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of  light-

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd