It is a method of prestressing in which tendons are placed, inside ducts or passages provided in concrete, after concrete gains sufficient strength. Tendons are then stretched and anchored at the ends of the concrete member. The transfer mechanism of prestressing force in this form of prestressing is different from that in the case of pre-tensioning. In this form of prestressing, the prestressing force is transferred to concrete through anchorages provided at the ends - not due to bond between concrete and tendons.


Related Discussions:- Define the term - pre- tensioning

Assignment help job, Can I apply for "online assignment help job" for civil...

Can I apply for "online assignment help job" for civil engineering,physics & maths etc?

Types of loads and resulting stresses, • Applied loads result in internal f...

• Applied loads result in internal forces consisting of a shear force (from the shear stress distribution) and a bending moment (from the normal stress distribution) • Bending s

Explain the statements about construction contract process, Explain the Sta...

Explain the Statements about the Construction Contract Process I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is

Example of magnetic dip, Example : Line AB was drawn with a magnetic ...

Example : Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what m

Functioning of a septic tank in a sewerage disposal system, Q. Write short ...

Q. Write short notes on the following : a) Points to be kept in mind while collecting water samples for testing from tap, stream & T/well separately. b) Where and why foot

Illustrate the design discharge for foundation, Q. Illustrate the Design di...

Q. Illustrate the Design discharge for foundation? To provide for an adequate margin of safety, the foundation and protective works of a bridge should be designed for a flood d

Determine the liquidity index and void ratio of the sample, A piece of clay...

A piece of clay taken from a sampling tube has a wet weight of 1.553 N and volume of 95.3 cm . After drying in an oven for 24 hours at 105°C, its weight is 1.087 N. The liquid and

State the problem and phases of site investigation, State the Problem and p...

State the Problem and phases of site investigation The site investigation is to be performed to obtain the solution for the following problems: i)  Foundation problems ii

Inadequate pile founding level, Reasons of common occurrence of "inadequate...

Reasons of common occurrence of "inadequate pile founding level" in piles of piers The most severe load on piers usually is the horizontal load owing to berthing and mooring o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd