Q. Back fill behind the abutments of bridges?

Dry Rubble - At the bank of all bridge abutments and wing walls, the space next to the masonry is to be filled in by a hand-packed dry rubble backing, to the thickness shown on the plans, or as directed by the Engineer.

Filling- Behind this dry rubble, the space upto the back of the excavation is to be filled with moorum, good granular yellow soil or other sound granular materials. Under no circumstances is black cotton or any clayey or silty soil to be used. This filling will be water and rammed in layer thickness. Each layer should have a slope of 45 o towards ground level, the slope to commence from immediately behind the abutment.


Related Discussions:- Back fill behind the abutments of bridges

Flemish bond, what is the advantages of Flemish bond

what is the advantages of Flemish bond

Define the thiem equations for confined aquifers, Define the Thiem Equation...

Define the Thiem Equations for Confined Aquifers   Using natural log:  Q = 2ΠKm(h 2 - h 1 )/ln(r 2 /r 1 )      m = aquifer thickness (ft) Using log 10 :   Q = 2Km(h 2 - h

Strength of materials, distribution of shear stress in triangular section

distribution of shear stress in triangular section

Mechanics, in what condition curve s-t curve is concave and convex

in what condition curve s-t curve is concave and convex

Steady flow energy equation, If there is steady flow, nothing changes with ...

If there is steady flow, nothing changes with time.  1. The properties of the fluid at entry and exit are constant. 2.  The properties of the fluid at any point in the contro

Installation of band drains, Question For drained reclamation, what wil...

Question For drained reclamation, what will significance of smear zone bring by installation of band drains ? Answer Throughout installation of band drains, smear zon

Contour interpolation, given A,B,C,and D are four plotted points at 2 centi...

given A,B,C,and D are four plotted points at 2 centimeter apart and their ground reduced levels are 57.5 meter 63.2 meter 68.2 meter and 59.2 respectively.it is required to draw co

Important items during level crossing inspection, Q.7.- Write the important...

Q.7.- Write the important items to be inspected during level Crossing inspection. How do you take census of traffic at level crossing. Ans.-Important items to be inspected duri

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd