Calculate the cost to finance the construction project, Civil Engineering

Assignment Help:

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of 14-months. The Contractor secured a bank loan with an interest rate of 1% per month on the outstanding balance. The Contractor will borrow $100,000 per month to reconcile costs at the end of months 1 through 12. Calculate the cost to finance the project that will be included as part of the bid.

Solution: At the end of month 12, the contractor will have borrowed 12 payments of $100,000 each.  The owner is scheduled to pay the contractor at the end of month 14 at which time the contractor will repay the bank.  Use the following equation to calculate the future value then extract the cost of financing the project:  

F = $100,000 (F/A, 1%, 12) (F/P, 1%, 2)   = $1,293,700

                                         Amount Borrowed =$1,200,000

                                    Amount of interest =$     93,700


Related Discussions:- Calculate the cost to finance the construction project

Explain the selected bridges - underwater inspection, Explain the Selected ...

Explain the Selected Bridges - Underwater Inspection? Those bridges, which require underwater inspection must be noted for individual inspection and inventory records as well b

Highway pavement design, Explain the important factors affecting the design...

Explain the important factors affecting the design of pavement?

Concrete technology, chemical compositions of Rapid Hardening Cement

chemical compositions of Rapid Hardening Cement

What do you understand by percolation of water, Q. What do you understand b...

Q. What do you understand by Percolation of water? Percolation of water into the ground or embankment takes place, causing rise in water table and / or saturation of the body.

Concrete surround for drainage pipes, Concrete surround is generally adopte...

Concrete surround is generally adopted for rigid drainage pipes to resist high traffic loads (for instance under shallow covers) and to allow for using pipes with lower strength. F

Explain the underwater problems and material defects, Explain the Underwate...

Explain the Underwater Problems and Material Defects? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as

Force system, show the diagram for non coplanar non concurrent force system...

show the diagram for non coplanar non concurrent force system

Bearings, what is the difference between whole circle bearing and reduced b...

what is the difference between whole circle bearing and reduced bearing?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd