A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of 14-months. The Contractor secured a bank loan with an interest rate of 1% per month on the outstanding balance. The Contractor will borrow $100,000 per month to reconcile costs at the end of months 1 through 12. Calculate the cost to finance the project that will be included as part of the bid.
Solution: At the end of month 12, the contractor will have borrowed 12 payments of $100,000 each. The owner is scheduled to pay the contractor at the end of month 14 at which time the contractor will repay the bank. Use the following equation to calculate the future value then extract the cost of financing the project:
F = $100,000 (F/A, 1%, 12) (F/P, 1%, 2) = $1,293,700
Amount Borrowed =$1,200,000
Amount of interest =$ 93,700
what are the details of aluminium sections and how are they connected for making a door or window
Breast Walls Needed to buttress uphill slopes. Figure : Breast Check Walls Small retaining structures provided in series to arrest landslides. Gabio
construction & working of rope brake dynamometr
Q. Internal force of preloaded fasteners? Force in a bolt in a bolted joint relies on the preloading force applied to it at the time of the tightening operation. For example, w
Test on specially moulded test piece The test piece shall be moulded by the manufacturer with identical compound and under identical vulcanizing conditions as used in manufact
gradation of materials used in wet mix macadam
Explain some Important Points for Hazardous Waste The mixture rule prevents dilution of waste for the purposes of escaping RCRA regulation. Mixtures of a listed hazardous w
whatiscreepofmetal&typesdescribe
Specific Gravity & Water Absorption of Fine Aggregate
effective CBR
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd