Calculate the cost to finance the construction project, Civil Engineering

Assignment Help:

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of 14-months. The Contractor secured a bank loan with an interest rate of 1% per month on the outstanding balance. The Contractor will borrow $100,000 per month to reconcile costs at the end of months 1 through 12. Calculate the cost to finance the project that will be included as part of the bid.

Solution: At the end of month 12, the contractor will have borrowed 12 payments of $100,000 each.  The owner is scheduled to pay the contractor at the end of month 14 at which time the contractor will repay the bank.  Use the following equation to calculate the future value then extract the cost of financing the project:  

F = $100,000 (F/A, 1%, 12) (F/P, 1%, 2)   = $1,293,700

                                         Amount Borrowed =$1,200,000

                                    Amount of interest =$     93,700


Related Discussions:- Calculate the cost to finance the construction project

Calculate the degree of saturation, A sample of clay taken from a natural s...

A sample of clay taken from a natural stratum was originated to be partially saturated and when tested in the laboratory gave the following results. Calculate the degree of saturat

Key role of drilling fluid in rotary drilling, Question What is key rol...

Question What is key role of drilling fluid in rotary drilling in site search? Answer Drill fluid in rotating serves two main reasons. (i) Facilitate rotation of

Stress design method, You have been selected to assist the structural engin...

You have been selected to assist the structural engineer for a bridge replacement project.  Your task is to design the size of the footing for an interior bridge pier, based on the

Softening point test, Softening Point Test: The temperature at which ...

Softening Point Test: The temperature at which bitumen softens is determined by the "Ring and Ball" test (Figure). (a) Diagram of Apparatus at Beginning of Test  (b

Compare the values of active and passive earth pressures, A retaining wall ...

A retaining wall 12 metres high is proposed to hold sand. The values of void ratio and φ in the loose state are 0.63 and 30° whereas they are 0.42 and 40° in the dense state. Suppo

Masonry, Sketches for English bond, Stretcher bond, Header bond, Flemish bo...

Sketches for English bond, Stretcher bond, Header bond, Flemish bond in first & second layer plan, elevation and 3 dimensional view of brick bond.

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Calculate dead, A building cross section is shown below. The building consi...

A building cross section is shown below. The building consists of eight (8) of the shown frames placed at distance of 20 feet oc for a total length of 140 feet. The glulam beams ar

Mass effect, how the effective mass of charge carrier less than the rest ma...

how the effective mass of charge carrier less than the rest mass

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd